Status Report for December 2019
- Report Date
- December 2019
Summary
Low Level design has been completed however, some consultation still required with colleges.
Central technology staging due to complete in January 2020. Implementation of central technologies into the live environment is expected to complete around late April 2020. This will be followed by early adopter edge site installations, and a full review of this early implementation will take place around May 2020 prior to commencing full rollout. Full rollout is currently anticipated to complete around June 2021.
Achievements in Last Period
- Major Governance Toolkit results shared with the board
- LLD complete
- Service model continues to be refined
- WP 1 ready for implementation first week of January
- Partial completion of acceptance testing documentation
- Live publish of project information website
Issues and Risks
Next Steps
- Completion of acceptance testing documentation
- WP2 to be developed and signed off
- Review of implementation plan
- Continued communication with stakeholders about starting implementation period
Future Milestones
| Deliver | Migration of ACE distribution sites complete | No date available | No |
| Deliver | Rollout of ACE edge and wireless complete | No date available | No |
| Analyse | In Room AP Pilot | No date available | No |
| Deliver | Rollout of campus edge and wireless complete | No date available | No |
| Plan | Low level design workshops complete | 18-Oct-2019 | Yes |
| Initiate | Planning | 31-Oct-2019 | Yes |
| Deliver | Migration of campus distribution sites complete | 27-Mar-2020 | No |
| Deliver | Completion of Central Technologies | 04-Apr-2020 | No |
| Deliver | Early adopter edge sites complete | 19-Apr-2020 | No |
| Deliver | Completion of wired and wireless edge deployment | 30-Jul-2021 | No |
| Close | Project Closure | 27-Aug-2021 | No |
- Approved budget
- 450.0 days
- Activity this month
- 50.0 days
- Activity this year
- 216.5 days
- Activity to date
- 216.5 days
- Estimate to complete current year
- 170.5 days
- Estimate to complete future years
- 100.0 days