Status Report for October 2019
- Report Date
- October 2019
Summary
Low level design workshops complete and LLD documentation in progress. College and USG/CSG leads issued with draft project plan for review/discussion internally taking account of caveats provided. Additional documentation on wireless survey reviews and buildings included/excluded to be issued in the next week.
Additional time has been included for completion of LLD sign off and the documentation has been separated into applicable sections to allow parts to be signed off and work continue. Final documentation sign off will be end of November. Central technology staging due to complete in January 2020. Implementation of central technologies into the live environment is expected to complete around late March 2020. This will be followed by early adopter edge site installations, and a full review of this early implementation will take place April 2020 prior to commencing full rollout. Full rollout is currently anticipated to complete around June 2021.
Achievements in Last Period
- amendments to the Major Governance Assessment survey toolkit continues
- draft detailed implementation plans discussed with College and Service Leads
- discussions on changes to IT practice and service model continue
- design workshops complete
- LLD documentation in progress
- new Project Manager in post for handover in December
Issues and Risks
Next Steps
- amendments to the Major Governance Assessment survey toolkit complete
- draft detailed implementation plan initial comments to be received back prior to next Board meeting
- invitations to test Major Governance Assessment survey will be reviewed and presented back to Board meeting
- discussions on changes to IT practice and service model continue
- LLD documentation continues
Future Milestones
| Deliver | Migration of ACE distribution sites complete | No date available | No |
| Deliver | Rollout of ACE edge and wireless complete | No date available | No |
| Analyse | In Room AP Pilot | No date available | No |
| Deliver | Rollout of campus edge and wireless complete | No date available | No |
| Plan | Low level design workshops complete | 18-Oct-2019 | Yes |
| Initiate | Planning | 31-Oct-2019 | Yes |
| Deliver | Migration of campus distribution sites complete | 27-Mar-2020 | No |
| Deliver | Completion of Central Technologies | 04-Apr-2020 | No |
| Deliver | Early adopter edge sites complete | 19-Apr-2020 | No |
| Deliver | Completion of wired and wireless edge deployment | 30-Jul-2021 | No |
| Close | Project Closure | 27-Aug-2021 | No |
- Approved budget
- 450.0 days
- Activity this month
- 31.0 days
- Activity this year
- 166.5 days
- Activity to date
- 166.5 days
- Estimate to complete current year
- 220.5 days
- Estimate to complete future years
- 100.0 days