Network Infrastructure Deployment - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 450.0 days 216.5 days 270.5
Content
Status
In Progress
Current Stage
Design
Start Date
Monday, 7 January 2019
Planning Date
Thursday, 31 October 2019
Delivery Date
Friday, 30 July 2021
Close Date
Friday, 27 August 2021
Project information
Project Code
CIS014
Programme
ITI - Communications Infrastructure (CIS)
Session
20/21
19/20
18/19
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Compliance
Project Classification
Transform
Funding Source
Road Map
Programme Priority
1
Overall Priority
Highest
Student Impact
Project deliverables will be used by students