Project on track
- Report Date
- November 2017
Summary
Project replanned due to change in PM.
Achievements in Last Period
- Specification drafted for Firewall requirements
Issues and Risks
- none
Next Steps
- Final specification to be produced
- Review CCS framework catalogue to see if off-the-shelf product available
Future Milestones
to be produced
- Approved budget
- 20.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 19.0 days