Project on track

Report Date
November 2017

Summary

Project replanned due to change in PM.

Achievements in Last Period

  • Specification drafted for Firewall requirements

Issues and Risks

  • none

Next Steps

  • Final specification to be produced
  • Review CCS framework catalogue to see if off-the-shelf product available

 

Future Milestones

to be produced

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
Change : Time status is at red due to the delay with loss of PM. Project is now being replanned and will return to green in the next report.
Change Status
Activity
Approved budget
20.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
19.0 days

Project Info

Project
Security/Firewall Enhancements
Code
CIS013
Programme
ITI - Communications Infrastructure (CIS)
Management Office
ISG PMO
Project Manager
Karen Wilson
Project Sponsor
David Graham
Current Stage
Close
Status
Withdrawn
Start Date
06-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Feb-2018
Overall Priority
Normal
Category
Discretionary