Project Report - July 2017

Report Date
July 2017
  • Complete discussions with relevant staff members in each of the divisions relating to their current student communication priorities, methods and objectives.
  • Following on from these discussions, identification of any methods or messages that have been particularly strong or worked well.
  • Review of discussions relating to student communications with CAM and EUSA.
  • Liaison with other projects in the ISG Change Communication and Branding theme.
  • Completion of initial draft report outlining recommendations and modifications to be made.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Stakeholder Engagement: Communicating with Students
Code
CCB005
Programme
IS Change - Communications and Branding (CCB)
Management Office
ISG PMO
Project Manager
Serena Fredrick
Project Sponsor
Jeremy Upton
Current Stage
Plan
Status
In Progress
Start Date
03-Feb-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a

Documentation