Roslin Institute AV 2019
Roslin Institute AV 2019
Home
Projects
Roslin Institute AV 2019
Status
Monthly Report
Monthly Report
Report Date
August 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Procurement, install and payment timescales are tight. We are in discussion with CMVM over ways to speed up the process.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Sep 18, 2019
Project Info
Project
Roslin Institute AV 2019
Code
AV2842
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
Eddy O'Hare
Project Sponsor
Anthony Davie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
30-May-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2019
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Not available.