Monthly Report

Report Date
March 2019
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Due to the costs involved this has been dropped from a showcase to a seminar room.
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
CT-Informatics Forum - G03
Code
AV2743
Programme
ISG Learning and Teaching Spaces: CSE (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Alastair Scobie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
01-Oct-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Aug-2019
Overall Priority
Normal
Category
Compliance

Documentation

Not available.