Report for October 2019

Report Date
October 2019

Achievements This Period

  • On-going discussions with Core Finance team regarding data interfaces 
  • Whilst the first draft of the functional question set and associated process flows has been prepared, this cannot be completed until clarification of data transfer requirements regarding the Core Finance system have been defined 

Issues

  • The completion of the functional question sets will now be delayed until clarification of Core Finance requirements are defined.   As a result the project will require to be re-planned 

Next Steps

  • Confirm potential suppliers 
  • Prepare ITQ with regards to 
    • creation of functional question set and associated process flows
    • clarify requirements for Core System interface (if possible)
    • creation of technical question set 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
As it has not been possible to confirm the data interface requirements with the Core Finance system, there will be delay in finalising the procurement question sets, and as a result the project will require to re-planned once these details have been finalised. A delay at this stage will not impact on the business as it is the intention to deploy the solution along the Core Finance system implementation schedule.
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
There will be the project procurement phases once the Core Finance system requirements have been clarified
Activity
Approved budget
40.0 days
Activity this month
0.1 days
Activity this year
7.9 days
Activity to date
7.9 days
Estimate to complete current year
28.8 days
Estimate to complete future years
0.0 days

Project Info

Project
Delivered Catering Procurement
Code
ACS042
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Ian Macaulay
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
30-Aug-2019
Planning Date
20-Sep-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation