Progress with server build

There has been good progress with the server build. The current situation is that it is looking good for Kinetics to be able to start their tasks from Monday 13th. We currently have a call in with ITI to set up Kinetics remote access to the server with a note on the call that they need to be able to start work on Monday. Will escalate this call if no progress have been made with it today (Friday 10th)

Update on 13/03

Kinetics now have access to the server and have requested the server collation is changed to be the same as the existing servers. Dev Tech have done the update, and Kinetics are able to proceed with the install

 

Current budget

Current Budget

 

AttachmentSize
Image icon Current Budget56.31 KB

Project Info

Project
Upgrade Kx Database Infrastructure
Code
ACS036
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Claire Barnish
Current Stage
Close
Status
Closed
Start Date
09-Sep-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Sep-2017
Category
Discretionary