Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • In October the failover scripts which manage the failover of databases and websites was resolved.  As result the DSOR was held and approval given for sign-off.  The revision of the SLA has been identified by the sponsor as a necessary requirement before approval can be given for closure and this task is being completed by AS IT & Comms manager and the head of Production Management.

 

Issues

  • Milestones revised

Next Steps

  • Completion: 30/11/12

 

Target dateTitle
30-Nov-2012Close

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Consolidate AS Infrastructure
Code
ACS027
Programme
Accommodation Catering and Events (ACE)
Project Manager
Iain Dobson
Project Sponsor
Claire Barnish
Current Stage
Close
Status
Closed
Start Date
17-Jun-2009
Planning Date
n/a
Delivery Date
n/a
Close Date
21-Dec-2012