Report for August 2016
- Report Date
- August 2016
Report compiled by Adam Wadee, IS Apps Programme Manager for Martin Morrey (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
At the start of 16/17 year the programme has two projects in progress. WEB009 is progressing well, however WEB010 has continued into the year as unplanned, which means that the programme budget needs to be reconciled.
Overall Programme RAG: AMBER
Forward Look and RAG for July 2016
Resource Position to end July 2016
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Responsive MyEd and EdWeb Integration Discretionary Milestones
RAG Status GREEN | Achievements this period
Issues
Next Steps
Milestones
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WEB010 Notifications Service Discretionary Milestones To be replanned
RAG Status RED | Report by Iain McLaughlin for August 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
WEB007 Notifications Backbone [Year 1] | Report by Colin Watt The project was closed on the 3rd June 2016. |
WEB008 MyEd Enhanced Mobile Interface | Report by Karen Stirling The project was closed in May 2016. |
Notes from Programme Meeting
Note | Action | Status |
---|---|---|