Report for May 2016
- Report Date
- May 2016
Report compiled by Adam Wadee, IS Apps Programme Manager for Martin Morrey (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The programme is in reasonable shape as we approach the end of the financial year. WEB007 and WEB008 have both closed and WEB009 is progressing well. The final project in the programme (Notifications Service) will has started, however it will continue into 16/17.
Overall Programme RAG: AMBER
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||
WEB009 Responsive MyEd and EdWeb Integration Discretionary Milestones
RAG Status GREEN | Report by Tim Gray for March 2015
Achievements this period
Issues
Next Steps
Milestones
| ||||||||||||||||||||||||||||||||||||||||||||||||||||
WEB010 Notifications Service Discretionary Milestones
RAG Status RED | Report by Iain McLaughlin for May 2016
Achievements this period
Issues
Next Steps
RAG Status RED due to delivery date changing by more than one month. Also risk to programme budget for 16/17 as the project is continuing into September 2016.
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
WEB003 Mobile Information Solution With MyEd - Phase 1 Compliance | Report by Maurice Franceschi The project was closed on the 31st July |
WEB005 Mobile Information Solution With MyEd - Configuration Discretionary | Report by Maurice Franceschi The project was closed on the 12th December |
WEB006 MyEd Continuous Improvement | Report by Maurice Franceschi The project was closed on the 3rd July. |
WEB007 Notifications Backbone [Year 1] | Report by Colin Watt The project was closed on the 3rd June 2016. |
WEB008 MyEd Enhanced Mobile Interface | Report by Karen Stirling The project was closed in May 2016. |
Notes from Programme Meeting
Note | Action | Status |
---|---|---|