Report for February 2016

Report Date
February 2016
 

Report compiled by Adam Wadee, IS Apps Programme Manager for Martin Morrey  (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

The programme is in good shape as we approach the end of the first quarter of the year.  WEB007 and WEB008 are both scheduled to deliver soon, and WEB009 is now planned.  The final project in the programme (Notifications Service) will start in March.

Overall Programme RAG: GREEN

 

 

 Section Two: Projects Not Started

 

 

Project InfoProject Manager's Commentary
AP56-076 Notifications ServiceProject due to start w/c 7th March - WEB010 Website now available and PM assigned (Jason Fiddes).

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

WEB007

Notifications Backbone [Year 1]

Discretionary

Milestones (to be confirmed with Project Sponsor)

 
25-Mar-2016Acceptance Sign Off
08-Apr-2016Close

 

 

RAG Status

GREEN

Report by Colin Watt for February 2016

 

Achievements in Last Period

  • Draft UAT plan produced; UAT plan expected to be agreed w/c 29/02/16.

 

Issues

  • currently awaiting UAT, and agreement on revised milestones with Project Sponsor, closure now expected Apr 2016.

 

Next Steps

  • Review Milestones with Project Sponsor.
  • Complete UAT and any necessary rework.
  • Acceptance and closure.

 

The project current status is GREEN as when UAT complete and signed off the project can move into closure.

WEB008

MyEd Enhanced Mobile Interface

Discretionary

Milestones

 
03-Mar-16Deployment - Timetabling Portlet and Email PreviewDeliver
03-Mar-16Deployment - Learn PortletDeliver
17-Mar-16ClosureClose

 

 

 

RAG Status

GREEN

Report by Karen Stirling for February 2016

 

Achievements this period

  • Meeting with Timetabling team to confirm any fixes required to sign off acceptance, some minor changes requested however if these are not completed prior to deployment date they are happy for these to be taken forward ion WEB009. Timetabling have now confirmed sign off of UAT provided by Scott Rosie
  • Learn Portlet fixes completed and retested by Learn Service team – UAT sign off given by Myles Blaney
  • Acceptance sign off now completed
  • Service Alerts in place for 3rd March
  • Final updates to Implementation Plan

Issues

  • Availability of developer resource due to annual leave - minor changes now fixed for Timetabling and testing completed in advance of deployment to Live on 3rd March.
  • Review remaining budget to cover deployment and closure

Next Steps

  • Deploy to Live on 3rd March
  • Complete project closure

 

The project is GREEN

WEB009

Responsive MyEd and EdWeb Integration

Discretionary

Milestones

20-Apr-2016Phase 1: DEV Build ReviewDeliver
02-Jun-2016Phase 1: Integration ReviewIntegrate
30-Jun-2016Phase 1 Acceptance ReviewAccept
06-Jul-2016Phase 2 BETA Build ReviewBuild
14-Jul-2016Phase 1 Deploy to LIVEDeliver
29-Jul-2016Phase 1 Deployment ReviewDeliver
11-Aug-2016Phase 2 DEV Build ReviewBuild
19-Sep-2016Phase 2 Integration ReviewIntegrate
24-Oct-2016Phase 2 Acceptance ReviewAccept
08-Nov-2016Phase 2 DeploymentDeliver
30-Nov-2016Phase 2 Deployment ReviewDeliver
15-Feb-2017Phase 3 Improved alignment between MyEd and EdWebDeliver

RAG Status

GREEN

Report by Tim Gray for February 2015

 

Achievements this period

  • Estimation and planning completed 
  • Planning Review completed

Issues

  • No issues

Next Steps

  • Start infrastructure build
  • Start BETA uPortal upgrade

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

WEB003

Mobile Information Solution With MyEd - Phase 1

Compliance

Report by Maurice Franceschi

The project was closed on the 31st July

Completion Report.

WEB005

Mobile Information Solution With MyEd - Configuration Discretionary

Report by Maurice Franceschi

The project was closed on the 12th December

WEB006

MyEd Continuous Improvement

Report by Maurice Franceschi

The project was closed on the 3rd July.

 

Notes from Programme Meeting

NoteActionStatus

WEB007:

- Paul is available until early October

- We'll combine the analysis and design phases (Richard and Michael to work on this).

- Learn notifications to be used during PoC.

- Next phase of project will start after feedback has been obtained and analysed (likely Jan 2016).

 Complete

WEB008:

- Build phase done, test deployment needed.

- UAT to be planned for Sep.

- Martin will check if Jo and her team can test.

- Adam to review Colin's workload / may need to assign another PM.

 Complete

Responsive MyEd and EdWeb Integration:

- Plan to do R&D while Paul still here.

- Adam to confirm where the time will be recorded.

 Complete

Book.ed

- Info to be passed around meeting attendees.

- Project info

 Complete

 

 

Documentation

Not available.