Section One: Programme Commentary, RAG and Resources Update
The programme is in reasonable shape at mid-year review position. WEB007 and WEB008 are both scheduled to deliver soon, although they have eperienced some delays. It is important that WEB009 is planned as soon as posible given the effort to complete this financial year. For that reason, the programme is shown as AMBER this month.
Overall Programme RAG: AMBER
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP56-076 Notifications Service | This phase of the project will start after feedback has been obtained and analysed from the WEB007 proof of concept (likely early 2016). |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||
WEB007 Notifications Backbone [Year 1] Discretionary Milestones (to be confirmed with Project Sponsor)
RAG Status AMBER | Report by Colin Watt for January 2016
Achievements in Last Period
Issues
Next Steps
The project current status is AMBER due to delays in UAT and business sign off. | ||||||||||||
WEB008 MyEd Enhanced Mobile Interface Discretionary Milestones
RAG Status AMBER | Report by Karen Stirling for January 2016
Achievements this period
Issues
Next Steps
The project current status is AMBER duen to delays in business area sign off for UAT | ||||||||||||
WEB009 Responsive MyEd and EdWeb Integration Discretionary Milestones
RAG Status GREEN | Report by Tim Gray for November 2015Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
WEB003 Mobile Information Solution With MyEd - Phase 1 Compliance | Report by Maurice Franceschi The project was closed on the 31st July |
WEB005 Mobile Information Solution With MyEd - Configuration Discretionary | Report by Maurice Franceschi The project was closed on the 12th December |
WEB006 MyEd Continuous Improvement | Report by Maurice Franceschi The project was closed on the 3rd July. |
Notes from Programme Meeting
Note | Action | Status |
---|---|---|
WEB007: - Paul is available until early October - We'll combine the analysis and design phases (Richard and Michael to work on this). - Learn notifications to be used during PoC. - Next phase of project will start after feedback has been obtained and analysed (likely Jan 2016). | Complete | |
WEB008: - Build phase done, test deployment needed. - UAT to be planned for Sep. - Martin will check if Jo and her team can test. - Adam to review Colin's workload / may need to assign another PM. | Complete | |
Responsive MyEd and EdWeb Integration: - Plan to do R&D while Paul still here. - Adam to confirm where the time will be recorded. | Complete | |
Book.ed - Info to be passed around meeting attendees. | Complete |