Report for July 2015
- Report Date
- July 2015
Report compiled by Adam Wadee, IS Apps Programme Manager for Martin Morrey (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The programme is shown as AMBER this month as decisions need to be made on WEB007 and WEB008, which may have an impact on the 15/16 plan.
Overall Programme RAG: AMBER
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | |||||||||||||||||||||
WEB007 Notifications Backbone [Year 1] Discretionary Milestones
RAG Status AMBER | Report by Colin Watt for July 2015
Achievements in Last Period
Issues
Next Steps
| |||||||||||||||||||||
WEB008 MyEd Enhanced Mobile Interface Discretionary Milestones
NB Milestone dates to be revised due to project team leave.
RAG Status AMBER | Report by Colin Watt for June 2015
Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
WEB003 Mobile Information Solution With MyEd - Phase 1 Compliance | Report by Maurice Franceschi The project was closed on the 31st July |
WEB005 Mobile Information Solution With MyEd - Configuration Discretionary | Report by Maurice Franceschi The project was closed on the 12th December |
WEB006 MyEd Continuous Improvement | Report by Maurice Franceschi The project was closed on the 3rd July. |
Notes from Programme Meeting
Note | Action | Status |
---|---|---|
WEB007: - Paul is available until early October - We'll combine the analysis and design phases (Richard and Michael to work on this). - Learn notifications to be used during PoC. - Next phase of project will start after feedback has been obtained and analysed (likely Jan 2016). | ||
WEB008: - Build phase done, test deployment needed. - UAT to be planned for Sep. - Martin will check if Jo and her team can test. - Adam to review Colin's workload / may need to assign another PM. | ||
Responsive MyEd and EdWeb Integration: - Plan to do R&D while Paul still here. - Adam to confirm where the time will be recorded. | ||
Book.ed - Info to be passed around meeting attendees. |