Report for April 2019
- Report Date
- April 2019
Section One: Commentary, RAG and Resources Update
Programme Commentary
This month progress has been made on both active projects. Google Tag Manager has been successfully deployed. An issue with resourcing has resulted in less development than planned, however, a plan is in place to resolve this in the next reporting period. Additional scope has been added to both active projects, a review of Apps/WAC communications in UWP023 and more EdWeb Development in UWP023.
RAG Status and Forward Look
Resources
Section Two: Projects Not Started
Project | Programme Comment |
---|---|
This year's only project is now in flight |
Section Three: Projects in Progress
|
Project Managers Commentary |
||||||||||||||||||||||||||||||||
UWP022 EdWeb: GPDR Follow Up Work Compliance Milestones
RAG GREEN |
Report by Tim Gray for March 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||
Discretionary Milestones
RAG GREEN |
Report by Chris Copner for April 2019 Achievements in Last Period
Issues
Next steps
|
||||||||||||||||||||||||||||||||
EdWeb and EdGEL - Powering collaborative development Discretionary Milestones Please add RAG GREEN |
Report by Bruce Darby for April 2019 Completed actions
Ongoing actions
Planned actions
|
||||||||||||||||||||||||||||||||
Discretionary Milestones on going RAG GREEN |
Report by Stuart McVicar for April 2019 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
UWP017 Drupal 8 Implementation Planning Compliance |
Report by Tim Gray This project was submitted for closure on 11/01/2019 (WIS Notes 11/01/19) Please see the Completion Report for further information |
UWP021 Implement GPDR Compliance Requirements Compliance
|
Report by Tim Gray This project was closed on 07/09/18 (WIS Notes 07/09/18) Please see the Completion Report for further information |
UWP016-Implementation of University Search Engine Compliance |
Report by Emma McNab This project was closed on 07/09/18 (WIS Notes 15/03/19) Please see the Completion Report for further information |
Section Five: Actions/Notes from monthly meeting on 14th March 2019
Project | Action / Notes | Responsibility | Status |
UWP099 | This project will continue to report for the remainder of the year. | BD | On-going |