Report for March 2019
- Report Date
- March 2019
Section One: Commentary, RAG and Resources Update
Programme Commentary
In this reporting period work started again on both EdWeb projects. This work is progressing well with first deployments scheduled for mid-April. CAM have agreed to fund an additional 61 days of effort to develop user stories created from various Requests for Chneg submitted last year. The Search Implementation project has also finally been closed.
RAG Status and Forward Look
Resources
Section Two: Projects Not Started
Project | Programme Comment |
---|---|
This year's only project is now in flight |
Section Three: Projects in Progress
|
Project Managers Commentary |
||||||||||||||
UWP022 EdWeb: GPDR Follow Up Work Compliance Milestones
RAG AMBER |
Report by Tim Gray for March 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||
Discretionary Milestones
RAG GREEN |
Report by Chris Copner for March 2019 Achievements in Last Period
Issues
Next steps
|
||||||||||||||
EdWeb and EdGEL - Powering collaborative development Discretionary Milestones Please add RAG Please add |
Report by Bruce Darby for March 2019 Completed actions
Ongoing actions
Planned actions
|
||||||||||||||
Discretionary Milestones on going RAG GREEN |
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
UWP017 Drupal 8 Implementation Planning Compliance |
Report by Tim Gray This project was submitted for closure on 11/01/2019 (WIS Notes 11/01/19) Please see the Completion Report for further information |
UWP021 Implement GPDR Compliance Requirements Compliance
|
Report by Tim Gray This project was closed on 07/09/18 (WIS Notes 07/09/18) Please see the Completion Report for further information |
UWP016-Implementation of University Search Engine Compliance |
Report by Emma McNab This project was closed on 07/09/18 (WIS Notes 15/03/19) Please see the Completion Report for further information |
Section Five: Actions/Notes from monthly meeting on 14th March 2019
Project | Action / Notes | Responsibility | Status |
Deployment | Schedule 2h meeting to map out and discuss deployment comms. The output should be an overview of all comms actions, responsibilities and appoint a gatekeeper. | TG | Done |
DrupalCamp Scotland | Code sprint on 24th May 2019. Colleagues in Dev Services to attend and possibly Mentor. AR to speak to Bill Lee regarding training budget, if not budget is available time can be coded against the programme code. AR also to speak to Billy Wardrop about other activities to assist in preparation. | AR | Closed |