Report for March 2018
- Report Date
- March 2018
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
In this reporting period, the new Search Engine has successfully deployed to LIVE. The project remains RED as some additional development is required, pushing out the remaining milestones. A critical Drupal update was successfully deployed to LIVE, with the turn around between release through Drupla.org and deployment less that one hour. The work on GDPR for EdWeb has progressed beyond planning and is now in the design phase, securing resources has had an impact on Drupal 8 Implementation Planning, resulting on this project's milestones moving out by two months. The project RAG is red to reflect this change.
RAG Status and Forward Look
Resources
Other UWP Activities
Section Two: Projects Not Started
All planned projects are now in flight
Section Three: Projects in Progress
|
Project Managers Commentary |
||||||||||||||||
UWP016-Implementation of University Search Engine Compliance Milestones
RAG RED |
Report by Emma McNab for March 2018 Achievements in Last Period
Issues
Next Steps
RED: The search engine is now live however a challenging issue arose in January in relation to the quality and security linked to current student email and telephone data. It was agreed two APIs were required to enable a robust solution and it was not possible to develop these prior to go live. The budget, resource, and milestones have been reviewed and outlined in Change 8. |
||||||||||||||||
UWP017 Drupal 8 Implementation Planning Compliance Milestones
RAG RED |
Report by Tim Gray for March 2018 Achievements in Last Period
Issues
Next Steps
RED Change: Activity and milestones moved out two months due to a resource conflict. resources have been prioritised to work on Implement GPDR Compliance Requirements for EdWeb |
||||||||||||||||
UWP020 EdWeb Events Enhancements Discretionary Milestones
RAG GREEN |
Report by Tim Gray for March 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
UWP019 Deliver Talks@Ed as a University-wide Service
Discretionary Milestones
RAG RED |
Report by Sonali Nakhate for March 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
EdWeb and EdGEL - Powering collaborative development Discretionary RAG GREEN |
Report by Bruce Darby for March 2018 Completed actions
Ongoing actions
Planned actions
|
||||||||||||||||
UWP021 Implement GPDR Compliance Requirements
Compliance Milestones
RAG GREEN |
Report by Tim Gray for March 2018 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
EdWeb Collaboration and Feature Development Discretionary
|
Report by Tim Gray This project was closed on 15/09/17 (WIS Notes 15/09/17) Please see the Completion Report for further information |
New University Search Engine: Requirements Gathering and Procurement Compliance |
Report by Emma McNab This project was closed on 22/09/17 (WIS Notes 22/09/17) Please see the Completion Report for further information |
Drupal 8 Implementation Planning Compliance |
Report by David Gibbons This project was closed on 17/11/17 (WIS Notes 17/11/17) Please see the Completion Report for further information |
Section Five: Actions/Notes from monthly meeting on 14th December 2018
Project | Action / Notes | Responsibility | Status |
---|---|---|---|
UWP017 | Discuss 3rd developer options for implementation project with Bill Lee | TG | Done |