Report for March 2018

Report Date
March 2018

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

In this reporting period, the new Search Engine has successfully deployed to LIVE. The project remains RED as some additional development is required, pushing out the remaining milestones. A critical Drupal update was successfully deployed to LIVE, with the turn around between release through Drupla.org and deployment less that one hour.  The work on GDPR for EdWeb has progressed beyond planning and is now in the design phase, securing resources has had an impact on Drupal 8 Implementation Planning, resulting on this project's milestones moving out by two months.  The project RAG is red to reflect this change. 

RAG Status and Forward Look

Resources

Other UWP Activities

 

Section Two: Projects Not Started

All planned projects are now in flight

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

UWP016-Implementation of University Search Engine

Compliance

Milestones

 

  Title
22-March-2018 Go Live
29-Mar-2018 Project Completion Acceptance signed off
20-April-2018 Closure

 

RAG

RED

 

 

Report by Emma McNab for March 2018

Achievements in Last Period

  • Special Cab Approval
  • UAT complete
  • Pre Live Communications
  • Sign Off / Approval
  • Go Live - 22nd March

Issues

  • Telephone and Student email data - Resolution of how this data will be gathered has been been challenging.  Two API solutions are now being progressed however it was not possible to make the data available for Go Live. See Change 8.

Next Steps 

  • Additional resource and budget secured
  • API development and Go Live
  • Project Closure

RED: The search engine is now live however a challenging issue arose in January in relation to the quality and security linked to current student email and telephone data. It was agreed two APIs were required to enable a robust solution and it was not possible to develop these prior to go live. The budget, resource, and milestones have been reviewed and outlined in Change 8.

 

UWP017 Drupal 8 Implementation Planning

Compliance

Milestones

27-Apr-2018 Analysis and Design Review
21-May-2018 Deliver Implementation Strategy
22-Jun-2018 Closure

RAG

RED

Report by Tim Gray for March 2018

Achievements in Last Period

  • Workshop to identify and prioritise the areas of activity successfully held - workshop notes

Issues

  • The infrastructure issue raised last month is being discussed in detail with ITI. At this time we are quietly confident that a solution will be possible. 
  • Resource conflict has resulted in the milestones being moved out 2 months

Next Steps 

  • Limited activity over the next reporting period. 

RED Change: Activity and milestones moved out two months due to a resource conflict. resources have been prioritised to work on Implement GPDR Compliance Requirements for EdWeb

UWP020 EdWeb Events Enhancements

Discretionary

Milestones

Target Datesort descending Title
05-April-2018 Deployment Review
19-April-2018 Closure Review

RAG

GREEN

Report by Tim Gray for March 2018

Achievements in Last Period

  • Second deployment slightly delayed due to industrial action

Issues

  • One content type was missed from the deployment, this will be deployed on Monday 2nd April 2018

Next Steps 

  • Deployment review
  • Project closure
UWP019 Deliver Talks@Ed as a University-wide Service

Discretionary

Milestones

Target Datesort descending Title
26-01-2017 Planning Review
28-02-2018 Analysis Complete
29-05-2018 Build Complete
15-06-2018 UAT Complete
29-06-2018 Deployment to Live
13-07-2018 Deployment Sign off
20-07-2018 Closure

RAG

RED

Report by Sonali Nakhate for March 2018

Achievements in Last Period

  • No work carried out on the project in the last period.

Issues

  • Issue raised that project cannot be closed till final decision received from senior management. 

Next Steps  

  • Final decision from senior management regarding the future of the project.
  • Closure report
  • Decision on future of the current Talks system.

EdWeb and EdGEL - Powering collaborative development

Discretionary

RAG

GREEN

Report by Bruce Darby for March 2018

Completed actions

  • University Website vision finalised.
  • Team workshop to share vision and how this fits with D8 planning completed.
  • EdWeb code sprint 12 Feb 2018.
  • Drupal (rather than EdWeb focussed) code sprint planned for May 18 in Argyle House.
  • DrupalCamp planned for May 19. LTW to sponsor event.
  • Regular meetings of the EdWeb/EdGEL Task Force (15/1/2018 and 26/02/2018).
  • Business School meetings to discuss D8 and Pattern Lab progress (15/01/2018, 19/02/2018, 20/03/2018).

Ongoing actions

  • Mapping of development process against wider developer groups, e.g. LTW DLAM developers contributing to EdWeb issue resolution.
  • Continue having transparent communication between the task force members, having responsibility to share with other stakeholders when relevant.
  • Meeting with the Business School web team to reflect on the School's progress in adopting EdGEL and use of Drupal 8.
  • Liaison with CSE regarding local code sprint organisation.
  • Technical reps from the task force to meet with technical reps from the community to provide feedback and guidance on best practices to adopt EdWeb/EdGEL.

Planned actions

  • Disseminate the long-term University Website vision to key stakeholders.
  • Revisit roles & responsibilities in view of creating web service team(s).
  • Future meeting planning.
UWP021 Implement GPDR Compliance Requirements

Compliance

Milestones

Target Datesort descending Title
06-Apr-2018 Design Review
11-May-2018 Build Review
14-May-2018 Acceptance Review
24-May-2018 Delivery
05-Jun-2018 Deployment Review
26-Jun-2018 Closure

RAG

GREEN

Report by Tim Gray for March 2018

Achievements in Last Period

  • Planning completed
  • Resources for Development completed
  • Requirements gathered
  • project priority changed from NORMAL to HIGHER

Issues

  • No issues to report

Next Steps

  • Sign off Design Review
  • Commence Build Phase

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

UWP015

EdWeb Collaboration and Feature Development  

Discretionary

 

Report by Tim Gray

This project was closed on 15/09/17  (WIS Notes 15/09/17)

Please see the Completion Report for further information

UWP014

New University Search Engine: Requirements Gathering and Procurement

Compliance

Report by Emma McNab

This project was closed on 22/09/17  (WIS Notes 22/09/17)

Please see the Completion Report for further information

UWP017

Drupal 8 Implementation Planning

Compliance

Report by David Gibbons

This project was closed on 17/11/17  (WIS Notes 17/11/17)

Please see the Completion Report for further information

 

 

Section Five: Actions/Notes from monthly meeting on 14th December 2018

Project  Action / Notes  Responsibility  Status
UWP017  Discuss 3rd developer options for implementation project with Bill Lee  TG  Done

Documentation

Not available.