Report for November 2017
- Report Date
- November 2017
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
This reporting period has continued to see progress on all projects. The TSL Implementation work has been completed and closed off. The Search Engine Implementation project is quickly gathering pace towards MVP next year. A sponsor funded project to update the core software and expand the talks@ed service has started; planning should be completed prior to the break.
In other news, Stratos Filalithis and Tim Gray presented the CMS and community building work at Burda Media's Thunder Day in Hamburg. The presentation was very well received with discussion about possibly hosting an event with Burda in the future ongoing.
RAG Status and Forward Look
Resources
Other UWP Activities
To give a more complete picture, this section captures other project activity in UWP which is not directly part of the programme but does have some impact, cross over or dependancies on Apps driven projects.
Section Two: Projects Not Started
Project Info | Programme Managers Commentary |
---|---|
Section Three: Projects in Progress
|
Project Managers Commentary |
||||||||||||||||||||
UWP016-Implementation of University Search Engine Compliance Milestones
RAG GREEN |
Report by Emma McNab for November 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||
UWP017 Drupal 8 Implementation Planning Compliance Milestones
RAG GREEN |
Report by Tim Gray for November 2017
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||
UWP020 EdWeb Events Enhancements Discretionary Milestones
RAG GREEN |
Report by Tim Gray for November 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||
UWP019 Deliver Talks@Ed as a University-wide Service
Discretionary Milestones
RAG GREEN |
Report by David Gibbons for November 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||
EdWeb and EdGEL - Powering collaborative development Discretionary RAG GREEN |
Completed actions
Ongoing actions
Planned actions
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
EdWeb Collaboration and Feature Development Discretionary
|
Report by Tim Gray This project was closed on 15/09/17 (WIS Notes 15/09/17) Please see the Completion Report for further information |
New University Search Engine: Requirements Gathering and Procurement Compliance |
Report by Emma McNab This project was closed on 22/09/17 (WIS Notes 22/09/17) Please see the Completion Report for further information |
Drupal 8 Implementation Planning Compliance |
Report by David Gibbons This project was closed on 17/11/17 (WIS Notes 17/11/17) Please see the Completion Report for further information |
Section Five: Actions/Notes from monthly meeting on 16th November 2017
Project | Action / Notes | Responsibility | Status |
Programme report | Need to improve how activity directly impacting on the programme is reflected in the above graphic. In the meeting we decided to include the project UWP099 in the programme report. SF will add content to the report, including estimates of time spent. TG will add this to the Programme Report. | TG/SF | Complete |
3 Year planning | In progress | All | On going |