May 2013
- Report Date
- May 2013
Report compiled by Maurice Franceschi (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects under Core Funding remain within budget as although there is an overspend of 6 days showing, there are 14 days still to be added to the programme budget as agreed increase for TEL005. However there are potential problems for PebblePad, Moodle and ODL Image Upload that could all require further effort.
As there is no contingency in the budget, then these need to be assessed and we may need to descope accordingly.
For CollegeRing-Fenced projects, TEL003 SMART is significantly over budget.
TEL001 PebblePad continues to have significant issues around Accessibility of the upgraded product, and the TurnItIn Plugin, although progress has been made with schools and supplier on the best approach forward.
TEL004 has some issues which may cause a delay, but not expected to develop to become serious for the project.
TEL005 continues to be impacted by problems with TEST infrastructure.
TEL003 has failed to deliver on several pieces, and has overrun significantly, and PM has informed the Sponsor of this who has asked for work to continue. The threat to exam boards from SMART bugs was removed, but the PGT Pass/Fail work was not made available to exam boards and had been wanted, the BOXI reports did not prove reliable enough for use by exam boards, and the real-time update stream process had to be stopped from further development due to infrastructure isssues with TEST environment.
Actions from programme meeting.


Section Two: Projects Not Started
All planned projects have started
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||
TEL001 (AP23-018) Pebblepad Upgrade Compliance Core Milestones
RAG Status AMBER | Report by Laura Bell for May 2013 Achievements in Last Period
Issues
Next Period
| ||||||||||||
TEL002 (AP23-037) MVM College Ring-Fenced
Milestones
RAG Status BLUE
| Report by Franck Bergeret for May 2013
Achievements in Last Period
Issues
Next Steps
| ||||||||||||
TEL003 (AP23-35) Extension of SMART to HSS with Enhancements HSS College Ring-Fenced Milestones
RAG Status RED | Report by Maurice Franceschi for May 2013
Achievements in Last PeriodNone Issues
Next Steps
| ||||||||||||
TEL004 (AP23-043) Compliance Core
Milestones
RAG Status GREEN | Report by Laura Bell for May 2013
Achievements in Last Period
Issues
Next Steps
| ||||||||||||
TEL005 (AP23-904) ODL Image Upload for Card Services Discretionary Core
Milestones
RAG Status RED
| Report by Laura Bell for May 2013 Achievements in Last Period
Issues
Next Period
| ||||||||||||
TEL006 (AP23-907) Discretionary Core Milestones
RAG Status GREEN
| Report by Alex Wood for May 2013
Achievements this Reporting Period
Issues
Next Steps
|
Section Four: Projects Closed / Withdrawn
| Project Info | Project Managers Commentary | ||||
LAT010 (AP12-022) Compliance Milestones 28-09-2012 Closure
| Project completed. | ||||
| LAT011 (AP12-030) Virtual Classroom Implementation Very Important Milestones
| Report by Tim Gray for November 2012 Achievements in Last Period Phase 3:
Issues Next Steps
| ||||
AP12-044 Social Hub Enhancements Funded | Withdrawn | ||||
AP12-042 Moodle Enhancements Funded | Withdrawn | ||||
AP23-045 DEI Data Hub- Enhancements Funded (IS) | Withdrawn |
Actions from May Programme Meeting (17thJune)
Actions from October Programme Meeting (12th November)
| Main action was the prioritisation of the Annual Planning proposals - see above. | ||
| Review how a TEL/TELS programme could be set up for SM/USD projects | Maurice | |
Actions from September Programme Meeting (5th October)
| Fix programme report so that the images fit on a screen | Maurice | Done |
| Add previous monthly programme actions onto current report | Maurice | Done |
| Ask for Registry to take on SMART project | Maurice |
Maurice talked to Karen on Monday 8th and has asked for this transfer. Karen to get back.
|
| When is the current review of programme and project structure expected to complete | Maurice to find out | Ongoing |
| Pebblepad Funding - clarify situation | Bryan to talk to Simon | Done |
| LAT010 is not showing as Closed on prject website | Maurice to action | Done |
We will focus on New MyED, given the current on schedule status of the MyED Upgrade Project. The risk of not having a working Old MyED channel to be accepted, with the three daysd Richard has w/c 22nd to be used as fallback if the upgrade is postpoened or backed out.
| Programme Owners to confirm the approach and who owns the risk,
Programe owners to decide if project board needs to be informed. | |
| Email to confirm the New My ED approach to Project Team. | Tim | Done |
Prgoramme owners of DEI and TEL agreed that the DEI projects should be moved into TEL programme, as DEI will not be funding DEI projects in 2012/13.
| Maurice to request expansion of TEL programme with transferred projects, and removal of DEI programme. Programme Owners/Simon to confirm the Funding for DEI projects. DEI Pcode effort to be transferred over to TEL programme management. | Done |
| For PebblePad v 3, we need user requirements and the dates when an upgrade can be scheduled (May-July?) confirmed. | Mark to talk to Robert C. | |