December 2019

Report Date
December 2019

(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Karen Howie

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL052 QMP Upgrade

TEL057 Learn Foundations

TEL058 Learn to the Cloud

TEL063 Lynda.com upgrade to Linkedin Learning

TEL064 Moodle Annual Upgrade 19/20

 

 

Forward Look and RAG

Resource Summary

Section Two: Projects Not Started

None

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

RAG Status:

Report by Colin Watt for Dec 2019

Achievements in Last Period

Issues

Next Steps

TEL057

Learn Foundations

Discretionary

Milestones

RAG Status:

Report by Lee-Ann Simpson for Dec 2019

Achievements in the last period

Issues

Next Steps

TEL058

Learn to the Cloud

Discretionary

Milestones

Deployment to Live - Phase 2 31-Jan-2020
Project Closure 14-Feb-2020

 

RAG Status: GREEN

Report by Karen Beggs for Dec 2019

Achievements in Last Period

  • Learn MyEd channel deployed to live. 
  • BI data feed deployed but still pointing to 2018/19 data. 
  • Setup of SaaS staging environment ongoing.
  • 'Implementation of Data Retention Policy' work has been deployed to Dev environment.
  • Further preparation for testing of new bb_stats schema.
  • Project Sponsor has changed from Anne-Marie Scott to Karen Howie.
  • Project Manager has changed from Sonali Nakhate to Karen Beggs.

Issues

  • None

Next Steps

  • SaaS Staging environment to be completed - BBL feeds schema to be exported from Dev to Test, then Live to Test.
  • DevTech to investigate / resolve BI feed issue (unable to connect to Learn remote database) to enable final testing and handover.
  • 'Implementation of Data Retention Policy' to be tested.
  • Learn MyEd channel caching to be looked at by DevTech team.

TEL063

Lynda.com upgrade to Linkedin Learning

Compliance

Milestones:

Workstream 5 Reporting  31-Oct-2019
Closure 14-Nov-2019

 

RAG Status: RED

Report by Kevin Hone for Dec 2019

Achievements in Last Period

  • A contract developer has investigated alternative CSV and API solutions and has quoted an indicative development cost of 6-8 weeks effort.
  • Greater clarity has been brought to discussions on the future solution with that of the existing BI suite being favoured over Power BI.

Issues

  • There has been no known progress on the following issue:
    • Engagement with LinkedIn Learning - a reporting API was to have been available to users (outside of the former pilot offering) in November. 
  • Internal resource with the necessary skill-set will not be available to undertake any development until the beginning of March.
  • The Project Manager is presently working to a contract that finishes at the end of January.

Next Steps

  • It is with a change of personnel, specifically Project Sponsor and Software Development Manager  that meetings are scheduled in the diary for early January introductions.
  • It is hoped that the new staff joining the project team will give clear direction on how best to bring the project to conclusion, once options have been openly discussed. 

The project currently remains at Red but with a meeting in diaries for early January to bring together resource from both the business and technology in an effort to plan next steps to a resolution. Questions need to be resolved over (1) which data feed solution best fits the needs of the university and (2) who is to do the work and when? Answers to the latter, affecting time and possibly cost.

 

TEL064

Moodle Upgrade

Compliance

Milestones:

(to be agreed in planning stage)

Planning 07-Feb-2020
Delivery 10-Jul-2020
Closure 31-Jul-2020

RAG Status: GREEN

Report by Colin Watt for Dec 2019

Achievements in Last Period

  • Project Website updated
  • Project initiated (TR Code requested at WIS 20/12/19).
  • Project Manager assigned (Mark Downey).

Issues

  • No major issues.

Next Steps

  • Project Planning & Estimates.

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL059

Moodle Upgrade

Closure Approved 16/08/19

TEL060

Learn Upgrade

Closure Approved 16/08/19

TEL050

Academic Blogging Service

Closure Approved 08/11/19

 

 

Programme Status
Has formal escalation taken place?
No