April 2013

Report Date
April 2013

 

Report compiled by Maurice Franceschi (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott (Programme Owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects under Core Funding remain within budget, however there are potential problems for PebblePad, Moodle and ODL Image Upload that could all require further effort.

As there is no contingency in the budget, then these need to be assessed and we may need to descope accordingly by the end of May.

 

For Ring-Fenced projects, TEL003 SMART is significantly over budget already and this is going to increase as the issues for deployed code and the work packages stil being developed are resolved.

 

 

Actions from programme meeting.

 

 

 

 

 

 Section Two: Projects Not Started  

No further projects

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

TEL001 (AP23-018)

Pebblepad Upgrade Compliance

Core

Milestones

 

Target dateTitle
31-May-2013User Acceptance (ASOR)
14-Jun-2013Delivery
21-Jun-2013Deployment Sign-Off
28-Jun-2013Closure

 

RAG Status

AMBER

Report by Laura Bell for April 2013

Achievements in Last Period

  • Integration testing has commenced
  • Impact assessment with Specialist Users completed
  • Training material in development

Issues

  • Testing has identified that the "accessible" version of Pebblepad is missing functionality. Issue is being escalated with Pebble Learning.
  • Risk that accessibility issue is not resolved in time for deployment of new version; contingency is to seek agreement from Pebble Learning to continue support for existing version.

Next Period

  • Confirm Turnitin functionality will be on target for delivery on 1/7
  • Sign off User Acceptance Testing 

TEL002 (AP23-037)

Speedwell Database Hosting

MVM College Ring-Fenced

 

Milestones

10-May-2013Deployment sign off DSOR
17-May-2013Closure
 

RAG Status

AMBER

 

Report by Franck Bergeret for April 2013

 

Achievements in Last Period

  • Delivery to Live completed

Issues

  • There is one remaining test to be completed for DSOR: test that the supplier Speedwell has access to the database for future maintenance. Delayed due to ITI work priority.
  • Exact number of days for annual maintenance to be agreed between IS Apps Production and MVM Business Lead Set status as Amber as this needs to be completed before closure.

Next Steps

  • Complete DSOR and Closure

TEL003 (AP23-35)

Extension of SMART to HSS with Enhancements

HSS College Ring-Fenced

Milestones

need to be restated for all phases

 

RAG Status

RED

Report by Maurice Franceschi for April 2013

New Project Manager Maurice Franceschi from 1st May

 

Achievements in Last Period

2. Phase 2 enhancements:

  • Pass/Fail: Delivered
  • Null Values: Delivered

Issues

  • Phase1: Boxi Report. Outstanding issues remain, some critical. All issues now in JIRA.  
  • Phase1: STREAM/SMARTMI. TEST Memory issue still unresolved. Critical issue, now in Jira.  
  • Phase 2: A number of critical issues reported in the LIVE environment after the deployment of NULL and PASS/FAIL. Issues recorded in Jira.  
  • Phase 2: PGT Pass/Fail UAT delayed until live problems resolved. We may have to drop PGT from deployment in May/June  

Next Steps

  • Phase 1 reporting:
    • Resolve issues for BOXI - issues prioritised in BOXI  
    • Resolve STREAM/SMARTMI memory issue - meeting arranged for 9th May  
  • Phase 2 enhancements:
    • Pass/Fail and Null values - Greg back on 8th May. LIve data copied to TEST to increase testing capability. Meeting 10th May with Sponsor and Operation manager for registry to assess what has been fixed, remain  
    • Meeting 12th May with stakeholders to discuss if we can avoid deploying PGT Pass/Fail

 

  • budget is overrunning both for Apps. Project Sponsor has been given an estimate of 35 days overspend (Apps) - but this may rise further. SM budget is ok.

 

TEL004 (AP23-043)

Moodle Upgrade

Compliance

Core

 

Milestones

 

Target dateTitle
06-May-2013Build Review PPBR
31-May-2013Deploy to Test
21-Jun-2013Acceptance ASOR
08-Jul-2013Deploy to Live

 

RAG Status

AMBER

Report by Laura Bell for April 2013

 

Achievements in Last Period

  • Review, deployed and tested plugins
  • Continued fixing new Theme bugs

Issues

  • The project is Amber as we continue to experience a number of bugs with the new Theme, and this is delaying sign off of the Build.
  • The issues above should not delay the overall implementation date.

Next Steps

  • Complete fixing new Theme bugs

 

TEL005 (AP23-904)

ODL Image Upload for Card Services

Discretionary

Core

 

Milestones

 

Target dateTitle
03-May-2013PPIR Phase 2 (Peer Project Integration Review)
10-May-2013ASOR Phase 2 (Acceptance Sign Off Review)
05-Jun-2013Deploy to Live
21-Jun-2013DSOR Phase 2 Sign off (Deployment Sign off review)
05-Jul-2013Project Closure

RAG Status

RED

 

Report by Laura Bell for April 2013

 

Achievements in Last Period

  • The project was due to complete Integration and acceptance testing in the last period.
  • Due to issues with the feed of test data from EUCLID, through IDM to MyEd, the test accounts were not able to be used
  • Test account issues look resolved; testing will now commence
  • Revised deployment schedule agreed with Sponsor

Issues

  • Test account issues may still arise as testing commences
  • New issue with the capacity of the servers has been identified, leading to lack of stability; ODL applications likely to need to move to a new environment
  • Project costs have increased to investigate and resolve Test account issues; costs will also be associated with environment review

 

Next Period

  • Complete Integration and Acceptance Testing

 

TEL006 (AP23-907)

Learn Enhancements

Discretionary

Core  

Milestones

 

20-May-2013Build Signed Off
11-Jun-2013User Documentation Complete
24-Jun-2013Acceptance Signed Off
27-Jun-2013Deployed in LIVE
17-Jul-2013Deployment Signed Off
23-Jul-2013Project Closed

 

 

RAG Status

GREEN

 

Report by Alex Wood for April 2013

 

 

Achievements in Last Period

  • BRD Signed Off
  • SDS Signed Off
  • TAD updates made
  • Merged Course Enrolments functionality deployed into TEST
  • Secondary Insitutional role functionality deployed into TEST

 

Issues 

  •  No issues

Next Period 

  •  Integration testing to be undertaken on 13th and 14th May
  • Plan user engagement
  • Plan UAT

Section Four: Projects Closed / Withdrawn

 

Project InfoProject Managers Commentary

LAT010 (AP12-022)

VLE upgrade to Learn 9.1

Compliance

Milestones 28-09-2012 Closure

 

Project completed.  

Closure Report

LAT011 (AP12-030)

Virtual Classroom Implementation

Very Important

Milestones

Target dateTitle
07-Dec-2012Closure

Report by Tim Gray for November 2012

Achievements in Last Period

Phase 3:

  • Delivery milestone achieved
  • Deployment Sign Off milestone achieved

Issues

  •  

Next Steps

  • Closure

AP12-044

Social Hub Enhancements Funded

Withdrawn

AP12-042

Moodle Enhancements Funded

Withdrawn

AP23-045 DEI Data Hub- Enhancements

Funded (IS)

Withdrawn

 

Actions from October Programme Meeting (12th November)

 

Main action was the prioritisation of the Annual Planning proposals - see above.  
Review how a TEL/TELS programme could be set up for SM/USD projectsMaurice 
   

Actions from September Programme Meeting (5th October)

Fix programme report so that the images fit on a screenMauriceDone
Add previous monthly programme actions onto current reportMauriceDone
Ask for Registry to take on SMART projectMaurice

Maurice talked to Karen on Monday 8th and has asked for this transfer. Karen to get back.

 

When is the current review of programme and project structure expected to completeMaurice to find outOngoing
Pebblepad Funding - clarify situationBryan to talk to SimonDone
LAT010 is not showing as Closed on prject websiteMaurice to actionDone

We will focus on New MyED, given the current on schedule status of the MyED Upgrade Project. The risk of not having a working Old MyED channel to be accepted, with the three daysd Richard has w/c 22nd to be used as fallback if the upgrade is postpoened or backed out.

 

Programme Owners to confirm the approach and who owns the risk,

 

Programe owners to decide if project board needs to be informed.

 
Email to confirm the New My ED approach to Project Team.TimDone
   

Prgoramme owners of DEI and TEL agreed that the DEI projects should be moved into TEL programme, as DEI will not be funding DEI projects in 2012/13.

 

Maurice to request expansion of TEL programme with transferred projects, and removal of DEI programme.

Programme Owners/Simon to confirm the Funding for DEI projects.

DEI Pcode effort to be transferred over to TEL programme management.

Done
   
For PebblePad v 3, we need user requirements and the dates when an upgrade can be scheduled (May-July?) confirmed.Mark to talk to Robert C.