August 2019

Report Date
August 2019

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL050 Academic Blogging Service

TEL052 QMP Upgrade

TEL057 Learn Foundations

TEL058 Learn to the Cloud

TEL063 Lynda.com upgrade to Linkedin Learning

 

 

Forward Look and RAG

 

Resource Summary

 

Section Two: Projects Not Started

TEL064 Moodle Annual Upgrade 19/20

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL050

Academic Blogging Service

Discretionary

Milestones

Deployment to Live - Phase 2 03-Oct-2019
Deployment Review - Phase 2 11-Oct-2019
Project Closure 18-Oct-2019

RAG Status: GREEN

 

Report by Sonali Nakhate for Aug 2019

Achievements in Last Period

  • Phase 2 - Testing completed of Blogs Archive & Deletion (IDM Integration) functionality. Not deployed to Live, will now be done post change freeze period.
  • Blogs Solr Search - Infrastructure work and testing completed. Deployed to Live.

Issues 

  • None

Next Steps

  • Deploy IDM Integration  functionality to Live post change freeze period.
  • Close project

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

Decommissioning of old servers

05-Oct-2019

Close

31-Oct-2019

 

RAG Status:

AMBER

Report by Colin Watt for Aug 2019

Achievements in Last Period

  • Short term workarounds were required to enable exams to be completed.
  • One area which is not going to use QMP after the end of September - this has required the legacy platform to remain rather than migrating this community; decommissioning to take place following the change freeze.
  • DSOR meeting held 29/08/19. It was agreed that the project cannot yet close due to issues which have come up in the period post deployment.

Issues

  • There are two issues preventing project closure and it was agreed to push the closure back to the end of October to allow the issues to be addressed (with consideration to the UoE Change Freeze):
    • emails from assessments
    • user experience when running QMP on kiosks

Next Steps

  • Agree obstacles to project closure removed.
  • Deployment checklists completed.
  • Decommissioning of legacy QMP platform.

TEL057

Learn Foundations

Discretionary

Milestones

 

Milestones are in the process of being amended - Project team are reviewing these prior to sign off.

Phase One: Evaluation Framework Sign Off 31-Jul-2019
Phase One: Training Material Sign Off 31-Jul-2019
Report on measurement against success criteria 10-Jan-2020
Evaluation of Phase 1 complete 28-Feb-2020
Scoping of Phase 2 - Terms of reference produced 27-Mar-2020
Strategy Plan Document for Phase 2 29-May-2020
Go/no go checkpoint for Semester 1 31-Jul-2020
Go/no go checkpoint for Semester 2 27-Nov-2020
Project Closure 29-Jan-2021

RAG Status: GREEN

Report by Lee-Ann Simpson for Aug 2019

Achievements in the last period

  • Complete the Phase One School migrations and began preparing the School reports;
  • Complete Phase Two planning;
  • Complete replacement for lost FTE;
  • Refined the new Learn Foundations SharePoint;
  • Continued focus on training requirements for users;
  • Created web pages for the Learn Foundations Terminology and Checklist work streams;
  • Completed accessibility mapping for 1 x non phase one School;

 

Issues

  • Automation work stream slipped into Phase Two due to resourcing availability as a result of the Phase One deliverables which need to be delivered before automation can be undertaken.  This work stream will be defined with support from the School Learning Technologists once roll over has been completed (Phase Two);

 

Next Steps

 

  • Complete the Phase One School School reports;
  • Begin Phase Two
  • Schedule Lessons Learned for Phase One.
  • Re-plan milestones for Phase Two based on Phase Two project plan

TEL058

Learn to the Cloud

Discretionary

Milestones

Planning Complete 06-Dec-2018
Complete R&D Phase 31-Jan-2019
Data Cleansing Complete for Test Migration 22-Mar-2019
Provide Test Migration Data to Blackboard 02-Apr-2019
Start Test Migration 05-Apr-2019
Build ready for Test migration 23-Apr-2019
Handover of Production Saas from Blackboard to UoE 26-Apr-2019
Complete Build 20-May-2019
End Test Migration 24-May-2019
Go/No-Go Decision 31-May-2019
Complete User Acceptance Testing 14-Jun-2019
Deployment to Live - Phase 1 17-Jul-2019
Deployment Review - Phase 1 22-Jul-2019
Deployment to Live - Phase 2 18-Oct-2019
Project Closure 31-Oct-2019

RAG Status: GREEN

Report by Sonali Nakhate for Aug 2019

Achievements in Last Period

  • Post migration to the Cloud, some snagging issues found with Data feeds and timetabling feed. These have now been fixed and all feeds are running satisfactorily for Start to Term.
  • Some changes made to Learn MyEd channel and deployed to Live to make it more resilient for Start of Term
  • Interim and longer term solutions agreed for BI data feed. Work ongoing on the interim solution.
  • Data Retention Policy presented to the board, minor changes, ready to be published soon.
  • Phase 2 scope agreed with relevant stakeholders, estimates and planning in progress.

Issues

  • None

Next Steps

  • Complete testing of interim solution of BI feed
  • Publish Data Retention policy.
  • Phase 2 - Finish planning and start development work.

TEL063

Lynda.com upgrade to Linkedin Learning

Compliance

Milestones

Workstream 5: Reporting function available 30-Sep-2019
Workstream 4: VLE Integration complete 31-Oct-2019
Closure 14-Nov-2019

RAG Status: AMBER

Report by Kevin Hone for Aug 2019

Achievements in Last Period

  • Project went live for the following work-streams:

    • W/S 1 - Data and Security
    • W/S 2 - Single Sign-on
    • W/S 3 - Discover Ed Integration (one month ahead of plan)
    • W/S 6 - Account Archiving
    • W/S 7 - User Access, Guidance and Support
    • W/S 8 - Communications and Marketing
  • Post implementation review meeting held with project team members and the 3rd party.

Issues

  • Lack of timely and accurate communication from the 3rd party in the lead-up to go-live and on the day of implementation required unplanned management.      
  • No clear date as to when the Reporting API and a final specification will be available from the 3rd party. Best guidance is that the pre-requisites to allow for an internal build will be shared Mid-Sept. 
  • eMail delays experienced in answering questions to aid the VLE Integration work. Escalation and feedback on the issues has been passed to the 3rd party Relationship Manager.

Next Steps

  • Work-stream 5 - Reporting. To be re-planned.
  • Work-stream 4 - VLE Integration. Further planning

 

 

 

 

 

 

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL059

Moodle Upgrade

Closure Approved 16/08/19

TEL060

Learn Upgrade

Closure Approved 16/08/19

 

 

AttachmentSize
Image icon tel-flook-aug2019.jpg174.2 KB
Image icon tel-effort-aug2019.jpg160.28 KB
Programme Status
Has formal escalation taken place?
No