- Report Date
- March 2019
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL050 Academic Blogging Service
TEL052 QMP Upgrade
TEL057 Learn Foundations
TEL058 Learn to the Cloud
TEL059 Moodle Upgrade
TEL060 Learn Upgrade
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
All agreed (Plan or In Year) projects for 2018/19 in progress.
Section Three: Projects in Progress
| Project Info |
Project Manager's Commentary |
|
TEL050
Academic Blogging Service
Discretionary
Milestones
| UAT Complete - Acceptance - Phase 2 |
05-Apr-2019 |
| Deployment to Live - Phase 2 |
30-Apr-2019 |
| Deployment Review - Phase 2 |
08-May-2019 |
| Project Closure |
17-May-2019 |
RAG Status: AMBER
|
Report by Sonali Nakhate for March 2019
Achievements in Last Period
- Phase 2 - Paperwork and approvals completed for setup of Test and Live IDM service for the Blogging service. Test IDM service setup. Testing preparation work in progress.
- Domain of One's Own contract paperwork in progress with third party supplier and Legal service.
- Blogs Search technical option (Solr) agreed, proof of concept underway.
Issues
Next Steps
- Start of Blogs Archive & Deletion testing.
- Complete Blogs Search Proof of Concept and agree its suitability.
- DOOO paperwork complete. Start setup of DOOO service.
|
|
TEL052
QMP Upgrade (17/18)
Compliance
Milestones
All subsequent milestones remain unchanged at present.
RAG Status:
RED
All subsequent milestones remain unchanged at present.
|
Report by Colin Watt for March 2019
Achievements in Last Period
- QM resolved the issues preventing the Test environment being made available for UAT. This was a major step forward given the delays through Jan and Feb.
- LTW have been through basic testing and 6 jira issues have been raised; none are showstoppers but we are waiting for a response from QM on resolution of each issue (or confirmation that the behaviour is as designed).
- However, during w/c 25/03/19 a further issue inexplicably occurred with participants unable to access scheduled assessments and authors unable to preview their content; team to push QM on resolution in order that we can have confidence in revised timelines.
Issues
- The availability of the test server reduced the immediate need for QMP to come on site, however a number of (non-showstopper) issues remain and QM are unable to indicate when they expect to resolve these; team will be pushing for a more certain response w/c 01/04/19 to avoid further disruption to timescales and milestones.
Next Steps
- TEST & Acceptance signoff
- LTW documentation tasks to complete when TEST signed off
- Deployment checklists completed
- Live install
- Configure and verify SSO on Test (to be set up on Test parallel with Live QMP install so as not to delay further)
|
|
TEL057
Learn Foundations
Discretionary
Milestones:
RAG Status:
AMBER - Project is currently being reported as AMBER due to the Template/Check List and Terminology milestones slipping as a result of the additional steps taken to support the methodology. There is also a possibility that the PgCap pilot may be impacted as a result. This work has been undertaken with the expectation that the project should return to GREEN by the beginning of April.
|
Report by Lee-Ann Simpson for March 2019
Achievements in the last period
- Template structure agreed by project team and shared with College Learning Technologists for review prior to sign off;
- Checklist content agreed by the team
- Terminology content agreed by the team;
- Continued user experience activity and engagement ongoing;
- Chalkmark Usability Testing completed;
- Communications & engagement at campus and School level with 2nd stage interviews began in March;
- Student and staff user groups held in March;
- Continued focus on training requirements for users;
- Communications Manager position offered and accepted;
- User experience and playback session for PPLS held with next user experience activity under way.
Issues
- Scheduled PgCap pilot potentially unable to be continued due to the availability of the Template within the IAD timescales. Currently being reviewed;
- Automation work stream slipped into Phase Two due to resourcing availability as a result of the Phase One deliverables which need to be delivered before automation can be undertaken. This work stream will be defined with support from the College Learning Technologists once roll over has been completed (circa. June/July);
Next Steps
- Template prototype to be signed off;
- Checklist prototype to be signed off;
- Terminology to be signed off;
- Continued user experience activity and engagement ongoing;
- Student and staff user groups to be held in April;
- Continued focus on training requirements for users;
- Automation work stream to be defined and planned for Phase Two;
- PgCap to commence if timescales allow.
|
|
TEL058
Learn to the Cloud
Discretionary
Milestones
| Data Cleansing Complete for Test Migration |
22-Mar-2019 |
| Provide Test Migration Data to Blackboard |
02-Apr-2019 |
| Start Test Migration |
05-Apr-2019 |
| Build ready for Test migration |
23-Apr-2019 |
| Handover of Production SaaS from Blackboard to UoE |
26-Apr-2019 |
| Complete Build |
20-May-2019 |
| End Test Migration |
24-May-2019 |
| Go/No-Go Decision |
31-May-2019 |
| Complete User Acceptance Testing |
14-Jun-2019 |
| Deployment to Live |
08-Jul-2019 |
| Deployment Review |
22-Jul-2019 |
| Project Closure |
08-Aug-2019 |
RAG Status:
AMBER
|
Report by Sonali Nakhate for March 2019
Achievements in Last Period
- Build work on custom UoE building blocks completed.
- Build work on Data feeds in progress.
- Data Cleansing consultation complete, work ongoing with testing of archive and deletion on Test environment.
- Test migration preparation complete - data transfer to AWS S3 completed in approximately 4.5 days.
Issues
- Awaiting allocation of software development resource for one development task.
Next Steps
- Continue development work of data feeds.
- Start MyEd channel development work.
- Continue implementation of Data Cleansing plan.
- BB to complete Test migration steps.
- UoE to start testing of SaaS environment once Test migration is complete.
Budget
Budget Review carried out on the project. See PICCL here.
|
|
TEL059
Moodle Upgrade
Compliance
Milestones
RAG Status:
GREEN
|
Report by Colin Watt for March 2019
Achievements in Last Period
- Analysis & Design milestone approved w/c 04/03/19.
- Build tasks delayed by a few days to enable the most recent release 3.4.8 to be used (released 11 March) (this was agreed by project team).
- Signoff of Build milestone expected w/c 01/04/19.
- Members of the project team met with colleagues in SW Dev and agreed on an approach to bring the code into version control; this to be implemented following signoff of Dev.
Issues
- No major issues. Project running to expected timeline.
- Initial test of Moodle Mobile functionality on Dev proved negative.
Next Steps
- Complete Build on Dev.
- Checkpoint for committing to Moodle version.
- Review estimates.
|
|
TEL060
Learn Upgrade
Compliance
Milestones
| Upgrade Dev Learn |
15-Apr-2019 |
| Test Dev Learn |
15-May-2019 |
| Upgrade Test Learn |
07-Jun-2019 |
| Complete UAT |
21-Jun-2019 |
| Deployment to Live |
08-Jul-2019 |
| Deployment Review |
22-Jul-2019 |
| Project Closure |
05-Aug-2019 |
RAG Status: GREEN
|
Report by Sonali Nakhate for March 2019
Achievements in Last Period
- Planning stage complete - signed off by WIS.
Issues
Next Steps
- Learn Dev to be upgraded to Learn Q4 2018 and Oracle database to be patched.
- Testing on Dev to commence.
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
|
TEL049
VLE Standards
|
Withdrawal Approved 24/07/18 |
|
TEL031
VLE Student Analytics
|
Closure Approved 21/12/18 |
| TEL Improvements |
Withdrawal Approved |