January 2019

Report Date
January 2019

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL050 Academic Blogging Service

TEL052 QMP Upgrade

TEL057 Learn Foundations

TEL058 Learn to the Cloud

TEL059 Moodle Upgrade

 

 

Forward Look and RAG

Resource Summary

 

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP89-031 Learn Upgrade Keep on books as contingency until TEL058 R&D complete.
AP89-915 TEL Improvements Confirmed in TEL Project meeting 06/11/18 that not required this session.

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL050

Academic Blogging Service

Discretionary

Milestones

UAT Complete - Acceptance - Phase 2 5-Mar-2019
Deployment to Live - Phase 2  29-Mar-2019
Deployment Review - Phase 2 08-Apr-2019

Project Closure

15-Apr-2019

RAG Status: AMBER

 

Report by Sonali Nakhate for January 2019

Achievements in Last Period

  • Phase 2 Sprint 2 went live.
  • Phase 2 - Blogs Retention policy completed and published.
  • Phase 2 - Blogs Archive and deletion development and testing preparation work in progress.
  • Domain of One's Own contract paperwork in progress with third party supplier.

Issues

  • None

Next Steps

  • Complete Blogs Archive & Deletion development and commence UAT testing.
  • Blogs Search investigation and options and agree a solution and plan.

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

TEST signoff (by QMP)

31-Jan-2019

Acceptance signoff

28-Feb-2019

Training completed

08-Mar-2019

Soft deploy to live - live install (ring-fenced)

22-Mar-2019

Deploy to Live- opened to user base

11-Jul-2019

Decommissioning of old servers

26-Jul-2019

Delivery review

27-Jul-2019

Close

31-Jul-2019

Rag commentary:

Project is RED as the 'Manage Access' page error is a showstopper because we can't give users access to their content without that functionality working. QMP are working on this at present. LTW cannot go back to the community to discuss revised Live dates until the managed access showstopper issue is resolved

RAG Status: RED

 

Report by Sue Woodger for January 2019

Achievements in Last Period

  • A new QMP project manager has been appointed
  • Weekly meetings have been set up with QMP
  • LTW has agreed that deployment as follows
    • Complete Test by resolving the external user access issue and allow UAT to complete and thereby sign Test off
    • Resolve high availability groups and reinstall test with these in place first (high availability groups need to be in place before an install)
    • Move directly to Installing high availability groups on Live then completing the live install in March so not to lose momentum with QMP -  but we do not intend to make v6 live to users until July when exams are completed (as advised by LTW, DevTech). V6 will be ring-fenced to LTW only and they will continue with the current v5.7, open to their user base, in Live until July when it will be replaced with v6 (they are on separate VMs).  We expect to suspend the project from the end of March until July assuming there are no further delays.

Issues

  • QMP continuing to investigate and resolve issues

    • Managed access (external access for university wide user base is not working therefore delaying UAT): still with QMP development team – no sign off a resolution date and PM following up with QMP PM
  • High availability groups: QMP are in the position of installing the HA groups on Test and will then re-install v6 (as high availability groups have to go in first). The issue is with the database ODBC connection string. QMP have asked for a description of the current setup on the forwarding rules on the balancer to do with the SSL offloading, and the forwarding rules on internal and public facing IP before they can complete this.

 

Next Steps

  • Managed access issue resolved by QMP so LTW can complete external UAT
  • Load testing and DR testing – Mark F has said that if Mark D decides the dates he will be able to set up from LTW end
  • TEST & Acceptance signoff
  • LTW documentation tasks to start when TEST signed off
  • Deployment checklists completed
  • Handover
  • Live install

 

 

TEL057

Learn Foundations

Discretionary

Milestones

 

Go/no go for testing 05-Feb-2019
Testing complete & test results documented 28-Feb-2019
Go/no go for pilots 01-Mar-2019
High-level benefits baselined and success criteria created 26-Apr-2019
Go/no go for roll out 03-May-2019
Delivery/Implementation 06-May-2019
Report on measurement against success criteria 10-Jan-2020
Evaluation of Phase 1 complete 28-Feb-2020
Scoping of Phase 2 - Terms of reference produced 27-Mar-2020
Strategy Plan Document for Phase 2 29-May-2020
Go/no go checkpoint for Semester 1 31-Jul-2020
Go/no go checkpoint for Semester 2 27-Nov-2020

RAG Status: GREEN - Training Contractor now appointed and in place.

 

Report by Laura Woods-Dunlop for January 2019

Achievements in Last Period

  • Handover to replacement PM continued throughout January with replacement PM joining the project full time on 28th January 2019;
  • Learning Technology Advisor and Learning Technologist Training Contractor appointed and in situ by end of January;
  • User experience Card Sort and Categorisation Analysis completed and shared with relevant stakeholders;
  • Design workshop for template, terminology and checklist underway with template/terminology skeleton complete and ready for next user experience testing;
  • Staff and student user group session held with successful outputs received which fed into both the ‘tree jack’ survey and training package;
  • Project user experience activities continued with a ‘tree jack’ survey being launched with students to test the initial phase of the skeleton.  The survey was live for 2 weeks and more than 1200 student responses received;
  • First campus based roadshow undertaken at the Vet School with good engagement from staff in attendance;
  • User experience and playback session for HCA held with next user experience activity underway.

Issues

Next Steps

  • Finalised design workshops for template, terminology & checklists to produce prototypes for testing;
  • Continued user experience activity and engagement;
  • Communications & engagement at campus and School level (KB, Central and Holyrood booked);
  • Usability test cases to be written and testing to be undertaken throughout February to allow for the current May training Milestone to be achieved;
  • Continued focus on training requirements for users;
  • ‘Tree Jack’ Analysis to be completed;
  • Communications Manager recruitment to be undertaken.

 

TEL058

Learn to the Cloud

Discretionary

Milestones

Complete R&D Phase 31-Jan-2019
Deployment to Live 08-Jul-2019
Deployment Review 22-Jul-2019
Project Closure 08-Aug-2019

RAG Status: AMBER

 

Report by Sonali Nakhate for January 2019

Achievements in Last Period

  • Test SaaS environment received from Blackboard.
  • R&D phase of the project complete, planning in progress.
  • Service Delivery manager from Blackboard assigned to the project and initial discussions about migration plan have taken place.
  • Contingency planning discussions ongoing.

Issues

  • Resourcing Issue - 

    There is an issue with resourcing on the project where the number of required development resources are not available. Two development resources are needed to be able to deliver the project on time and only one resource is available currently.

Next Steps

  • Acquire resources and complete detailed planning and submit to WIS.
  • Start design and build work
  • Establish Project Board.
  • Contingency - agree an option and plan.

 

TEL059

Moodle Upgrade

Compliance

Milestones

To be confirmed during planning

End of Planning 15-Feb-2019
Analysis & Design 01-Mar-2019
Build 29-Mar-2019
Integration 12-Apr-2019
Acceptance 28-Jun-2019
Deployment 12-Jul-2019
Deployment Sign Off Review (DSOR) 02-Aug-2019
Close 16-Aug-2019

 

RAG Status: GREEN

Report by Colin Watt for January 2019

Achievements in Last Period

  • Project Initiated.
  • Project Sponsor and Team kickoff meeting held 25/01/19.
  • Project Team confirmed.
  • Weekly Team meetings in place starting 31/01/19.
  • Draft Project Brief available.
  • Draft BRD available.

Issues

  • No issues. Awaiting DevTech assessment of latest stable Moodle release documentation to determine any version dependencies with supporting software.

Next Steps

  • Scope to be confirmed.
  • Agree scope and work with TechMan, DevTech, SWDev on planning and estimates.

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL049

VLE Standards

Withdrawal Approved 24/07/18

TEL031

VLE Student Analytics

Closure Approved 21/12/18
TEL Improvements Withdrawal Approved