TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL050 Academic Blogging Service
TEL052 QMP Upgrade
TEL057 Learn Foundations
TEL058 Learn to the Cloud
Forward Look and RAG



Not produced for Dec 2018.
Resource Summary


Not produced for Dec 2018.
Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP89-030 Moodle Upgrade | To be initiated Jan 2019. |
| AP89-031 Learn Upgrade | Keep on books as contingency until TEL058 R&D complete. |
| AP89-915 TEL Improvements | Confirmed in TEL Project meeting 06/11/18 that not required this session. |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||
|
Academic Blogging Service Discretionary Milestones
RAG Status: AMBER |
Report by Sonali Nakhate for December 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||
|
QMP Upgrade (17/18) Compliance Milestones
RAG Status: RED |
Report by Sue Woodger for December 2018 Achievements in Last Period
Issues
Next Steps
Rag commentary:Project is RED as the 'Manage Access' page error is a showstopper because we can't give users access to their content without that functionality working. This issue means that we will miss the deployment date for week beginning 7 January. LTW cannot go back to the community to discuss revised Live dates until the managed access showstopper issue is resolved |
||||||||||||||||||||||||||
|
Learn Foundations Discretionary Milestones
RAG Status: RED |
Report by Laura Woods-Dunlop for December 2018 Achievements in Last Period
Issues
Next Steps
Rag commentary: RAG Status is currently RED - Replacement PM secured however training contractor not yet appointed. Training is critical to project's success & timeline for this workstream was planned based on trainer being available to start in January therefore move to red until successful recruitment. Path to GREEN, recruitment of trainer & re-plan of activity to allow deadline of training commencement in May to happen. |
||||||||||||||||||||||||||
|
Learn to the Cloud Discretionary Milestones
RAG Status: AMBER |
Report by Sonali Nakhate for December 2018 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
VLE Standards |
Withdrawal Approved 24/07/18 |
|
VLE Student Analytics |
Closure Approved 21/12/18 |