Report for March 2013
- Report Date
- March 2013
Report compiled by Maurice Franceschi (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The programme budget has been reviewed by senior management and is now set as 448 days, with 284 days for Core funded projects and Programme Management, and 164 days for the projects funded by College Ring-Fence. All planned and in-year projects are in progress. The summaries below reflect the distinction in the funding of projects.
Actions from programme meeting.





Section Two: Projects Not Started
No further projects
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||
TEL001 (AP23-018) Pebblepad Upgrade Compliance Core Milestones
RAG Status GREEN | Report by Laura Bell for March 2013 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||
TEL002 (AP23-037) MVM College Ring-Fenced
Milestones
RAG Status AMBER
| Report by Maurice Franceschi for March 2013
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||
TEL003 (AP23-35) Extension of SMART to HSS with Enhancements HSS College Ring-Fenced Milestones
RAG Status AMBER | Report by Maurice Franceschi and David Watters forMarch 2013 Achievements in Last Period1.Phase 1 reporting:
2. Phase 2 enhancements:
Issues
Next Steps
| ||||||||||||||||||||||||||||||||
TEL004 (AP23-043) Compliance Core
Milestones
RAG Status GREEN | Report by Maurice Franceschi for March 2013 Due to issues, there has been a slight delay in the testing of Plugins. However, project remains on course. Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||
TEL005 (AP23-904) ODL Image Upload for Card Services Discretionary Core
Milestones
RAG Status GREEN | Report by Laura Bell for March 2013 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||||||||||||
TEL006 (AP23-907) Discretionary Core Milestones
RAG Status GREEN
| Report by Alex Wood for March 2013
Activities completed in this period
IssuesNo issues
Activities to complete in next period
|
Section Four: Projects Closed / Withdrawn
| Project Info | Project Managers Commentary | ||||
LAT010 (AP12-022) Compliance Milestones 28-09-2012 Closure
| Project completed. | ||||
| LAT011 (AP12-030) Virtual Classroom Implementation Very Important Milestones
| Report by Tim Gray for November 2012 Achievements in Last Period Phase 3:
Issues Next Steps
| ||||
AP12-044 Social Hub Enhancements Funded | Withdrawn | ||||
AP12-042 Moodle Enhancements Funded | Withdrawn | ||||
AP23-045 DEI Data Hub- Enhancements Funded (IS) | Withdrawn |
Actions from October Programme Meeting (12th November)
| Main action was the prioritisation of the Annual Planning proposals - see above. | ||
| Review how a TEL/TELS programme could be set up for SM/USD projects | Maurice | |
Actions from September Programme Meeting (5th October)
| Fix programme report so that the images fit on a screen | Maurice | Done |
| Add previous monthly programme actions onto current report | Maurice | Done |
| Ask for Registry to take on SMART project | Maurice |
Maurice talked to Karen on Monday 8th and has asked for this transfer. Karen to get back.
|
| When is the current review of programme and project structure expected to complete | Maurice to find out | Ongoing |
| Pebblepad Funding - clarify situation | Bryan to talk to Simon | Done |
| LAT010 is not showing as Closed on prject website | Maurice to action | Done |
We will focus on New MyED, given the current on schedule status of the MyED Upgrade Project. The risk of not having a working Old MyED channel to be accepted, with the three daysd Richard has w/c 22nd to be used as fallback if the upgrade is postpoened or backed out.
| Programme Owners to confirm the approach and who owns the risk,
Programe owners to decide if project board needs to be informed. | |
| Email to confirm the New My ED approach to Project Team. | Tim | Done |
Prgoramme owners of DEI and TEL agreed that the DEI projects should be moved into TEL programme, as DEI will not be funding DEI projects in 2012/13.
| Maurice to request expansion of TEL programme with transferred projects, and removal of DEI programme. Programme Owners/Simon to confirm the Funding for DEI projects. DEI Pcode effort to be transferred over to TEL programme management. | Done |
| For PebblePad v 3, we need user requirements and the dates when an upgrade can be scheduled (May-July?) confirmed. | Mark to talk to Robert C. | |
