November 2018

Report Date
November 2018

(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL050 Academic Blogging Service

TEL052 QMP Upgrade

TEL057 Learn Foundations

TEL058 Learn to the Cloud

 

 

Forward Look and RAG

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP89-030 Moodle Upgrade  
AP89-031 Learn Upgrade  
AP89-915 TEL Improvements Confirmed in TEL Project meeting 06/11/18 that not required this session.

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

RAG Status: BLUE

 

Project currently suspended

Project to  close

 

TEL050

Academic Blogging Service

Discretionary

Milestones

UAT Complete - Acceptance - Phase 2 (to be reviewed) 15-Jan-2019
Deployment to Live - Phase 2 (to be reviewed) 31-Jan-2019
Deployment Review - Phase 2 (to be reviewed) 08-Feb-2019

Project Closure

(to be reviewed)

15-Feb-2019

RAG Status: 

AMBER

Report by Sonali Nakhate for November 2018

Achievements in Last Period

  • Phase 2 Sprint 1 was made live - new plugins, themes and bug fixes.
  • Phase 2 Sprint 2 development work in progress.
  • Phase 2 - Blogs Archive & Deletion development and policy work in progress.
  • Changes to Website Search - new 'Blogs' tab - development and testing complete.

Issues

  • None

Next Steps

  • Phase 2 sprint 2 to go live.
  • Changes to Website Search - new 'Blogs' tab to go live.
  • Continue Blogs Archive & Deletion development work.
  • Finalise first draft of Blogs Archive and Deletion Policy
  • Continue search investigation with Funnelback
RAG Commentary
No change from last reporting period. Phase two of the project includes bespoke development work such as change to WordPress search engine, blogs archiving and deletion etc. There is some uncertainty on how the search requirements can be technically met and hence there is medium confidence in Phase 2 being completed in time. So the RAG status of Amber has been selected for Phase 2 of the project in this reporting period.

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

Accept

Acceptance signoff

23-Nov-2018 missed

Deliver

Training completed

30-Nov-2018 missed

Deliver

Live infrastructure built

07-Dec-2018

Deliver

Deploy to Live

08-Jan-2019

Deliver

Decommissioning of old servers

28-Jan-2019

Deliver

Delivery review

31-Jan-2019

Close

Close

08-Feb-2019

RAG Status: AMBER

Report by Sue Woodger for November 2018

Achievements in Last Period

  • Budget reviewed and approved as 88d (was 63d) – wis approval 9/11/18
  • LTW confirmed Live deployment date to be wb 7/1/ 18
  • Revised milestones agreed and updated – wis approval 9/11/18
  • QMP completed Test install and migrations and UAT commenced 7/11/18
  • Call submitted to ITI for Live configuration

 Issues

  • UAT not yet signed off ads there are still issues with managed access and load balancer settings

Next Steps

  • LTW to complete testing
  • TEST signoff
  • LTW documentation tasks to start when TEST signed off
  • Live infrastructure to be completed

Rag commentary:

As indicted last month once verified by QMP that TEST is fully upgraded and migrations are complete we can move the project to AMBER. We now have a Test system and it is in UAT so we can move the project to AMBER. There are issues in UAT to do with managed access and load balancer firewall rules and these are being investigated by QMP with support from DevTech and ITI.

Work has started on the LIVE configuration as ITI do not have the resource to wait until UAT is signed but are doing so with the caveat that some rework may be required

TEL057

Learn Foundations

Discretionary

Milestones

 

Stage Milestone Due Date Previous Date Complete
Plan Project strategy brief outlining recommendations for solution(s) & 2 year plan (Major) 31-Aug-2018 No date available Yes
Plan End of Planning 05-Oct-2018 28-Sep-2018 Yes
Plan Agree Detailed Plan 30-Nov-2018 23-Nov-2018 Yes
Plan End of Detailed Planning 30-Nov-2018 23-Nov-2018 Yes
Design Go/no go for testing 04-Jan-2019 No date available No
Analyse High-level benefits baselined and success criteria created 04-Jan-2019 No date available No
Design Testing complete & test results documented 28-Feb-2019 No date available No
Build Go/no go for pilots 01-Mar-2019 No date available No
Accept Go/no go for roll out 03-May-2019 No date available No
Deliver Delivery/Implementation 06-May-2019 No date available No
Deliver Report on measurement against success criteria 10-Jan-2020 No date available No
Deliver Evaluation of Phase 1 complete 28-Feb-2020 No date available No
Deliver Scoping of Phase 2 - Terms of reference produced 27-Mar-2020 No date available No
Deliver Strategy Plan Document for Phase 2 29-May-2020 No date available No
Deliver Go/no go checkpoint for Semester 1 31-Jul-2020 No date available No
Deliver Go/no go checkpoint for Semester 2 27-Nov-2020 No date available No
Close Project Closure 29-Jan-2021 No date available No

RAG Status: AMBER

Report by Laura Woods-Dunlop for November 2018

Achievements in Last Period

  • Project plan finalised & activities prioritised
  • Design underway - user experience activity supporting design
  • Engagement strategy developed
  • Student UX activity playbacks complete
  • Decision on rollover date for Learn made
  • Support from LTC Senate secured
  • Project priority moved to highest
  • Dependencies on Learn to the Cloud identified
  • Communications plan signed off at Project Board
  • Festival of Creative Learning planned & submission entered
  • Abstract approved by LTW for application to present at Durham Blackboard User Conference
  • Piloting opportunities identified

Issues

  • No current issues however decision made to re-plan automation workstream due to resource constraints

Next Steps

  • Submission for Learning & Teaching Conference
  • Sign off engagement strategy & begin implementation
  • Sign off evaluation activities with board
  • Continue design work for templates & terminology - launch staff & student surveys to identify top tasks and student mental model of categorising tasks
  • Presentation to LISC
RAG Commentary
AMBER - discussions between LTW and Apps are ongoing about assigning a replacement PM however nothing secured yet.
In addition resource from DLAM has constraints due to loss of resource within the team putting additional pressure on key
resource for the project. Re-plan has taken place to alleviate this pressure. Path to GREEN, replacement PM resource needs to be secured. Expected that DLAM resource issue will be addressed through re-plan so no further steps necessary.

TEL058

Learn to the Cloud

Discretionary

Milestones:

Complete R&D phase 31-Jan-2019
Deployment to Live  08-July-2019
Deployment Review  22-July-2019

Project Closure

08-Aug-2019

 

RAG Status: 

AMBER

Report by Sonali Nakhate for November 2018

Achievements in Last Period

  • Project planning in progress.
  • Scope of R&D phase of the project agreed.
  • Project Brief completed and in review by the team.
  • Contract paperwork started with Blackboard

Issues

  • None

Next Steps

  • Project Brief to be signed off by WIS.
  • Start R&D stage of the project.
  • Sign off contract paperwork
  • Blackboard start build of Test SaaS environment.

RAG Commentary

Contract for PM on the project is due to end beginning of January and the paperwork for contract extension has not been completed. Hence the project status has been moved to Amber. Path to Green - Pursue contract paperwork and get it in place before Christmas break.

 