October 2018
- Report Date
- October 2018
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL031 VLE Student Analytics
TEL050 Academic Blogging Service
TEL052 QMP Upgrade
TEL057 Learn Foundations
TEL058 Learn to the Cloud
Forward Look and RAG




Resource Summary



Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP89-030 Moodle Upgrade | |
| AP89-031 Learn Upgrade | |
| AP89-915 TEL Improvements | Confirmed in TEL Project meeting 06/11/18 that not required this session. |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||
|
VLE Student Analytics Discretionary Milestones RAG Status: BLUE
|
Project currently suspended Project to close
|
||||||||||||||||||||||||||||||
|
Academic Blogging Service Discretionary Milestones
RAG Status: AMBER |
Report by Sonali Nakhate for October 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
|
QMP Upgrade (17/18) Compliance Milestones A piccl is being submitted 8 November to update these milestones
RAG Status: RED |
Report by Sue Woodger for October 2018 Achievements in Last Period
Issues The Test install continues with the following issues
Next Steps
Rag commentary: The project remains at RED because although we are expecting Test to be ready this week (week ending 9 November) we don’t have QMPs validation on this yet. Once verified by QMP that TEST is fully upgraded and migrations are complete we can move the project to AMBER. LTW have confirmed that an early January date is best for Live deployment which leaves us with only 5 weeks to get the Live environment created by ITI and for QMP to do the upgrade. We absolutely must have full commitment from everyone in UoE and have it from DevTech, Project Services and LTW. The biggest risk to not meeting the dates is ITI as they cannot commit to dates up front.
Impact: The primary impact to this upgrade not happening is to students as they will be on an unsupported system for summative assessment which could break at any point. End of support for the current version of QMP, which is v5.7 (but commonly referred to as v5), will be July 2019, however according to their website and confirmation from Mark Findlay issues will only be fixed at the vendor's discretion. QMP also state the resolution to most issues will require an upgrade - which we are currently trying to do. Any deployment requires university wide agreement plus their time for testing so LTW attempt wherever possible to avoid deploying changes to their services during teaching time and have advised that week beginning 7 January will be best for the live deployment. |
||||||||||||||||||||||||||||||
|
Learn Foundations Discretionary Milestones
RAG Status: AMBER |
Report by Laura Woods-Dunlop for October 2018 Achievements in Last Period
Issues
Next Steps
Rag Commentary AMBER - discussions between LTW and Apps are ongoing about assigning a replacement PM however nothing secured yet. |
||||||||||||||||||||||||||||||
|
Learn to the Cloud Discretionary Milestones: In Planning stage, yet to be agreed. RAG Status: GREEN |
Report by Sonali Nakhate for October 2018 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
VLE Standards |
Withdrawal Approved 24/07/18 |
| Attachment | Size |
|---|---|
| 169.16 KB | |
| 181.9 KB | |
| 171.57 KB | |
| 144.04 KB | |
| 171.57 KB | |
| 144.04 KB | |
| 163.55 KB | |
| 153.49 KB |