September 2018

Report Date
September 2018

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL050 Academic Blogging Service

TEL052 QMP Upgrade

TEL057 Learn Foundations

 

 

Forward Look and RAG

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP89-030 Moodle Upgrade  
AP89-031 Learn Upgrade  
AP89-915 TEL Improvements Funding tbc
AP89-916 Learn Migration to Managed Hosting Funding tbc

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

RAG Status: BLUE

 

Project currently suspended

 

TEL050

Academic Blogging Service

Discretionary

Milestones

Deployment to Live - Phase 1 02-Oct-2018
Deployment Review - Phase 1 18-Oct-2018
UAT Complete - Acceptance - Phase 2 (to be reviewed) 16-Nov-2018
Deployment to Live - Phase 2 (to be reviewed) 30-Nov-2018
Deployment Review - Phase 2 (to be reviewed) 14-Dec-2018

Project Closure

(to be reviewed)

21-Dec-2018

RAG Status: 

AMBER

Report by Sonali Nakhate for September 2018

Achievements in Last Period

  • Phase 1 Build complete.
  • EQIA signed off.
  • Terms of Use and Take Down Policy for the service completed and signed off.
  • Online help and guidance creation in progress, some pages published.
  • Planning and creation of training workshops.
  • First pilot training workshop delivered.
  • Implementation Checklist and Handover to Production Management.
  • Communications issued about go-live as per Comms Plan.
  • Phase 2 Project planning in progress

Issues

  • None

Next Steps

  • Phase 1 Go-live
  • Carry out comms activities as per the published Communications Plan.
  • Phase 2 project planning - updated budget and timescales submit to WIS
  • Start Phase 2 Business Analysis activities

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

 

Upgrade to v6 in TEST - under way 03-Aug-2018
Test migration 10-Aug-2018
Full migration of data and settings into v6 10-Aug-2018
TEST signoff 24-Sep-2018
UAT complete 28-Sep-2018
Acceptance signoff 28-Sep-2018
Training completed 12-Oct-2018
Live infrastructure built 23-Nov-2018
Deploy to Live 13-Dec-2018
Decommissioning of old servers 11-Jan-2019
Delivery review 25-Jan-2019
Close

31-Jan-2019

 

RAG Status: RED

Report by Colin Watt for Sue Woodger for September 2018

Achievements in Last Period

  • Limited progress in September due to clarifications on the rules to be set up on Load balancers and the Start of Session change freeze.
  • VPN access issues resolved. allowing QMP to remotely connect.
  • Project overall priority raised to HIGHER: see item 13
  • PM and Programme Manager have escalated delays with ITI Enterprise Services (Unix Platforms) but this has again resulted in more elapsed time; it proved more difficult than expected to organise a face to face meeting to make sure we are working collaboratively towards a solution (see issues).
  • DevTech have received further detail from QMP to help determine the health of servers, required to help implement more graceful handling or errors.

Issues

  • The request made by QMP for implementation of load balancer rules to handle incoming traffic were rejected and because of the delays confirming information between all parties unfortunately the request itself became subject to the restrictions of the Start of Session change freeze. In order to make progress the PM and Programme Manager requested ITI (Enterprise Services - Unix Platforms) meet face to face with IS Apps DevTech and the project team, in order that agreement be reached on the detail of what was being requested to be implemented; the intention being to have a common objective internally and then follow up again with the supplier for further clarification on detail or relay back to them any issues with their request. A meeting was attended 25/09/18 following which there was further clarification on the outstanding UniDesk calls between Unix Platforms and DevTech teams. DevTech have also been in contact with QMP to determine a method for establishing health checks on the servers; information has now been received and passed on to ITI via the UniDesk call.  
  • PM and Programme Manager have emphasised the need for the work on the infrastructure to be prioritised in order that QMP be able to complete the TEST install and verify it is functioning. To date, Unix Platforms team are unable to commit to have staff available on hand at the time of testing in case minor changes are required. Unless this happens, the likelihood is that the dates for delivery to the LIVE platform would need to be pushed back further. At this stage meeting the previously agreed date of December is very optimistic.  
  • The project team would like to formally escalate that there is a commitment of ITI Unix Platforms staff availability to be on hand at the time of testing to work with DevTech and  QMP (via DevTech) to ensure the solution in place functions correctly, and reduce the chance of further delays should further minor changes be required. 

Next Steps

  • PM to update milestones
  • DevTech to work closely with Unix Platforms on load balancer config and testing
  • QMP to complete TEST install and complete migrations
  • TEST signoff
  • LTW documentation tasks to start when TEST signed off

TEL057

VLE Standards

Discretionary

Milestones

End of Planning 05-Oct-2018
Agree Detailed Plan 02-Nov-2018
End of Detailed Planning 02-Nov-2018
Go/no go for testing 04-Jan-2019
High-level benefits baselined and success criteria created 04-Jan-2019
Testing complete & test results documented 28-Feb-2019
Go/no go for pilots 01-Mar-2019
Go/no go for roll out 03-May-2019
Delivery/Implementation 06-May-2019
Report on measurement against success criteria 10-Jan-2020
Evaluation of Phase 1 complete 28-Feb-2020
Scoping of Phase 2 - Terms of reference produced 27-Mar-2020
Project Closure 29-Jan-2021

 

RAG Status: GREEN

Report by Laura Woods-Dunlop for September 2018

Achievements in Last Period

  • Sign off for detailed costings secured & recruitment underway
  • Detailed planning workshops underway
  • Project brief due for submission 05.10.18

  • Baseline measurement gathering underway

  • Communications & engagement plan drafted

Issues

Next Steps

  • Finalise communications & engagement plan
  • Produce detailed project plan
  • Schedule design workshops
  • Issue initial communication

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL049

VLE Standards

Withdrawal Approved 24/07/18