August 2018

Report Date
August 2018

(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL050 Academic Blogging Service

TEL052 QMP Upgrade

TEL057 Learn Foundations

 

 

Forward Look and RAG

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP89-030 Moodle Upgrade  
AP89-031 Learn Upgrade  
AP89-915 TEL Improvements Funding tbc
AP89-916 Learn Migration to Managed Hosting Funding tbc

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

RAG Status: BLUE

 

Project currently suspended

 

TEL050

Academic Blogging Service

Discretionary

Milestones

Planning Review 02-Mar-2018
Design/Build Complete - Phase 1 13-Jul-2018
UAT Complete - Acceptance - Phase 1 24-Aug-2018
Deployment to Live - Phase 1 04-Oct-2018
Deployment Review - Phase 1 18-Oct-2018
UAT Complete - Acceptance - Phase 2 (to be reviewed) 16-Nov-2018
Deployment to Live - Phase 2 (to be reviewed) 30-Nov-2018
Deployment Review - Phase 2 (to be reviewed) 14-Dec-2018

Project Closure

(to be reviewed)

21-Dec-2018

RAG Status: 

AMBER

Report by Sonali Nakhate for August 2018

Achievements in Last Period

  • System testing complete.
  • UAT complete.
  • Accessibility testing and EQIA complete.
  • Policies development in progress.
  • Online help and guidance creation in progress.
  • Planning and creation of training workshops.

Issues

  • None

Next Steps

  • Complete bug fixing and sign off release for go-live.
  • Continue development of policies, support and guidance material.
  • Carry out pilot training workshops
  • Carry out comms activities as per the published Communications Plan.
  • Implementation Checklist and Handover to Production Management.
  • Phase 2 project planning

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

03-Aug-2018- to be reviewed

Upgrade to v6 in TEST

10-Aug-2018- to be reviewed

Test migration

10-Aug-2018- to be reviewed

Full migration of data and settings into v6

31-Aug-2018 - to be reviewed

TEST signoff

12-Sep-2018- to be reviewed

UAT complete

14-Sep-2018- to be reviewed

Acceptance signoff

14-Sep-2018- to be reviewed

Training completed

23-Nov-2018

Live infrastructure built

13-Dec-2018

Deploy to Live

11-Jan-2019

Decommissioning of old servers

25-Jan-2019

Delivery review

31-Jan-2019

Close

 

RAG Status: RED

Report by Sue Woodger for August 2018

Achievements in Last Period

  • The secondary load balancer was completed by 24 August 18
  • PM confirmed with QMP when they would be able to pick up the test install again and they agreed 27 August

Issues

The revised dates for the Test install have been missed due to waiting on getting the secondary load balancer up and running. ITI have cited start of term issues and infrastructure team holidays as causing the delay. We got the secondary load balancer by 24 August 18. PM will revise the milestones again. It was emphasised at last revision of milestones that they were just an estimate and these ones will be too until we are sure Test has been completed. We are drawing up an implementation checklist for Live to mitigate the issues found during the Test install.   

  • Mark Dobbing has been off sick and PM was not aware - only when prompting for an update was this discovered. Mark Lang asked 30/8 that he be included if any issues

    • Colin, Programme manager, informed DevTech that LTW are paying for the work (not just Apps time, but also QMP as 3rd party supplier) and due to misunderstandings with ITI there has been disagreement on some of the work; the outcome is that there is potential for QMP to be charging twice for work that has to be redone; understandably LTW are not happy with this at all so it is crucial that          PM knows exactly what is happening.
  • Christian from QMP informed 30/8 that he did not have the missing IPs yet. Mark L supplied addresses on 31 August.
  • On 31 August Christian reported that that he could not get VPN access to continue the install – this continues into 3 September with Mark L and Alistair Webb trying to resolve

Next Steps

PM to update milestones

  • DevTech to resolve VPN issues for QMP
  • QMP to complete TEST install and complete migrations
  • TEST signoff
  • LTW documentation tasks to start when TEST signed off

RAG Commentary

We estimated Test to be completed in August but did not receive the secondary load balancer until 24 August (due to start of term de-risking issues and infrastructure team holidays causing the delay). QMP were due to re-start 27 August but DevTech developer was off sick so QMP had not received the IP addresses. DevTech team manager has now supplied these but there is now an issue with QMP access to the servers which DevTech are currently working on. Because of all the issues surrounding the Test install the project remains at RED until we are sure TEST can be completed plus the continued delays are eating into the projects budget and there is potential for QMP to be charging twice for work that has to be redone.  We are drawing up an implementation checklist for Live to mitigate the issues found during the Test install.   

Project sponsor, programme manager, DevTech team lead are all aware of the issues with the Test install.

TEL057

VLE Standards

Discretionary

Milestones

 

Project strategy brief outlining recommendations for solution(s) & 2 year plan 31-Aug-2018
Agree Plan 02-Nov-2018
End of Planning 02-Nov-2018
Go/no go for testing 04-Jan-2019
High-level benefits baselined and success criteria created 04-Jan-2019
Testing complete & test results documented 28-Feb-2019
Go/no go for pilots 01-Mar-2019
Go/no go for roll out 03-May-2019
Delivery/Implementation 06-May-2019
Report on measurement against success criteria 10-Jan-2020
Terms of reference for additional roll out 24-Jan-2020
Project Closure 31-Jan-2020

RAG Status: GREEN

Report by Laura Woods-Dunlop for August 2018

Achievements in Last Period

  • Old project (VLE Standards, TEL049) closed & new project (Learn Foundations, TEL057) opened due to significant scope & milestone changes.

  • Planning workshops scheduled

  • First staff user group held

  • Communications hub drafted 

  • Work on measurements baseline begun 

  • Detailed costings drafted

Issues

Next Steps

  • Secure sign off for detailed costings & begin recruitment
  • Commence planning workshops
  • Submit project brief

  • Source baseline measurements

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL049

VLE Standards

Withdrawal Approved 24/07/18

 

 

AttachmentSize
Image icon tel-resource-aug2018.jpg169.16 KB
Image icon tel-fl-aug2018.jpg181.9 KB