April 2018

Report Date
April 2018

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL049 VLE Standards

TEL050 Academic Blogging Service

TEL051 Annual Moodle Upgrade (17/18)

TEL052 QMP Upgrade

TEL053 Learn Annual Upgrade

 

Forward Look and RAG

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP78-060 TEL Improvements Project withdrawn

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

13-Apr-2018

Close

 

RAG Status: AMBER

 

Report by Colin Watt for April 2018

  • Final report is currently with LTW Business Lead for finalisation before circulation to Project Board.
  • Project Board to complete approval of report by email before project closure.

Issues

  • No major issues.
  • Project Closure delayed due to resource conflict (Business Lead, LTW).

Next Steps

  • Complete final report and circulate to Project Board members.
  • Close Project.

The project current status is AMBER;  the project closure date is being pushed back further due to Business Lead availability. Business Lead availability subject to  competing higher priority work.

TEL049

VLE Standards

Discretionary

Milestones

18-May-2018 Complete Consultation exercise
25-May-2018 Produce New Templates
22-Jun-2018 Agree Terms of Reference for Pilot(s)
13-Jul-2018 Recommendations Report
14-Dec-2018 Complete Pilot(s)
25-Jan-2019 Review Pilot(s) and Agree plan for Rollout
25-Jan-2019 Agree Communications Plan
25-Jan-2019 Agree Support & Training Plan
24-May-2019 Institutional Templates Available
28-Jun-2019 Complete Rollout
30-Aug-2019 Post Rollout Support
13-Sep-2019 Delivery Sign Off Review
27-Sep-2019 Project Closure

 

RAG Status: AMBER

Report by Colin Watt for April 2018

Achievements in Last Period

  • Consultation process continuing with individual schools.
  • Learn template to be used for pilot on track for completion w/c 30/04/18 ahead of scheduled course rollover.
  • Replacement PM scheduled to start 14/05/18.

Issues

  • No major issues.
  • Potential changes in project scope upcoming.

Next Steps

  • Handover to replacement PM.
  • Handover of Service Manager.
  • Review of actions for Project Board.
  • Agreement on scope changes.

 

Project RAG status is currently AMBER due to PM resource conflict still ongoing and the need to repeat PM recruitment (new PM now confirmed to start 14/05/18). No escalation required at this time.

TEL050

Academic Blogging Service

Discretionary

Milestones:

29-Jun-2018 Build Complete
27-Jul-2018 Deployment to Live
13-Aug-2018 Deployment Review
27-Aug-2018 Project Closure

RAG Status: GREEN

Report by Sonali Nakhate for April 2018

Achievements in Last Period

  • External user consultation events completed.
  • Analysis stage in progress
  • First Project Board meeting, ToR signed off.
  • TAD complete, Infrastructure build started.
  • Student intern recruited, starting 4th June.
  • Some development started.

Issues

  • No major issues.

Next Steps

  • Analysis stage to be completed and BRD signed off.
  • Infrastructure build for blogs.ed.ac.uk to complete.
  • Continue Development.
  • Content Plan to be agreed.

TEL051

Annual Moodle Upgrade (17/18)

Compliance

Milestones

Target Datesort descending Title
29-Jun-2018 Acceptance
12-Jul-2018 Deploy to LIVE
26-Jul-2018 Deployment Sign Off Review (DSOR)
02-Aug-2018 Close

RAG Status: 

GREEN

Report by Ben Armstrong for April 2018

Achievements in Last Period

  • Completed Moodle TEST application upgrade
  • Set up user accounts and courses in TEST
  • Commenced "Internal UAT" of TEST

Issues

  • The Behat feasibility, now completed, incurred a couple more days of effort than expected; however, this can be absorbed within the project's contingency budget

Next Steps

  • Finalise 'internal' UAT
  • Complete 'external' UAT
  • Compile feedback from UAT
  • Implement fixes (where required)

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

09-May-2018

Statement of works approved

11-May-2018

VM environments set up on TEST & LIVE

14-May-2018

Upgrade to v6 in TEST

16-May-2018

Test migration

18-May-2018

Full migration of data and settings into v6

21-May-2018

TEST signoff

18-Jun-2018

UAT complete

28-Jun-2018

Acceptance signoff

28-Jun-2018

Training completed

11-Jul-2018

Deploy to Live

27-Jul-2018

Decommissioning of old servers

30-Jul-2018

Delivery review

31-Jul-2018

Close

RAG Status: AMBER

Report by Sue Woodger for April 2018

 

Achievements in Last Period

Domain investigations are now completed: We escalated the domain issue to Mark Lang on 21 March. On 9 April a conference call was held between the technical staff from ITI, Dev Tech and QMP and all were happy that we could progress with an installation which fits with UoE infrastructure requirements (the AD issues were discussed and resolved and no further technical blockers were noted). 

  • On 11 April it was confirmed that there will be a single set of infrastructure required (QMP’s option B), with test and live environments both running on the same infrastructure.
  • DevTech have ordered the VM machines from ITI – we confirmed that TEST and LIVE environments should be set up at the same time (LIVE should be a clone of TEST)
  • Can confirm that we expect TEST will be ready in the first half of May and on LIVE first half of July. Deploy Is 11 July.

Issues

Possible issue with load balancer re the url requests and this is being pursued –developers have said that there is an option for testing should there be delays

  • Statement of works– was running late as the domain investigations took longer than anticipated but are now underway
  • There was a week’s delay in the escalation of the domain issues being actioned  
  • We have not been able to get ITI to commit to any timescales so the latest milestone changes have been completed on a most likely basis. Any delay from ITI  will cause the milestones to be seriously stretched  

Next Steps

Statement of works to be approved

  • VM machines to be set up on TEST and LIVE
  • QMP to upgrade to v6 with DevTech support
  • TEST signoff

 

Rag commentary: Project is AMBER as confidence in milestones is dependent on ITI work being completed and we cannot get ITI to commit to timescales

TEL053

Annual Learn Upgrade (17/18)

Compliance

Milestones

18-Jun-2018

Acceptance

03-Jul-2018

Deploy to Live

17-Jul-2018

Delivery review

24-Jul-2018

Close

 

RAG Status: GREEN

Report by Sue Woodger for April 2018

 

Achievements in Last Period

  • Build signed off on 18 April
  • UAT scripts created by LTW
  • Due to change freeze on TEST for Learn course rollover we agreed to move into TEST week beginning 30 April – Actual date agreed as 2 May as rollover will continue into 30 April
  • Chris C has fixed the mobility bug and upped memory on DEV. TEST and LIVE currently sitting at 8gb so should not be an issue. (Last years upgrade issue was with the update overriding JMB settings)

Issues

  • No issues

Next Steps

  • Move into TEST on 2 May
  • Integration testing and UAT to be completed

Rag commentary: None – project GREEN

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL045

Annual Moodle Upgrade

Closure Approved 25/08/17

TEL043

Learn Upgrade

Closure approved 18/08/17

TEL048

Learn Database Migration to Oracle 12

Withdrawal approved 23/02/18

AP78-060

TEL Improvements

Withdrawal approved 09/03/18

 

 

 

 

 

 

AttachmentSize
Image icon tel-flook-apr2018.jpg163.53 KB
Image icon tel-resource-apr2018.jpg184.48 KB