March 2018
- Report Date
- March 2018
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL031 VLE Student Analytics
TEL049 VLE Standards
TEL050 Academic Blogging Service
TEL051 Annual Moodle Upgrade (17/18)
TEL052 QMP Upgrade
TEL053 Learn Annual Upgrade
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP78-060 TEL Improvements | Project withdrawn |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
|
VLE Student Analytics Discretionary Milestones
RAG Status: GREEN
|
Report by Colin Watt for March 2018
Issues
Next Steps
|
||||||||||||||||||||||||||||
|
VLE Standards Discretionary Milestones
RAG Status: GREEN |
Report by Colin Watt for March 2018 Achievements in Last Period
Issues
Next Steps
Project RAG status is currently GREEN due to PM resource conflict being dealt with by recruitment (new PM to start 16/04/18). No escalation required at this time. |
||||||||||||||||||||||||||||
|
Academic Blogging Service Discretionary Milestones:
RAG Status: GREEN |
Report by Sonali Nakhate for March 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
|
Annual Moodle Upgrade (17/18) Compliance Milestones
RAG Status: GREEN |
Report by Ben Armstrong for March 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
|
QMP Upgrade (17/18) Compliance Milestones
RAG Status: RED |
Report by Sue Woodger for March 2018
Achievements in Last Period
Issues
Next Steps
Project RAG status is currently RED as the domain issues have not been resolved. Project has been escalated to Mark Lang to provide the technical conduit between ITI and Questionmark to find a resolution. |
||||||||||||||||||||||||||||
|
Annual Learn Upgrade (17/18) Compliance Milestones
RAG Status: AMBER |
Report by Sue Woodger for March 2018
Achievements in Last Period
Issues
Next Steps
Current Project RAG status is AMBER (time) due to delays on Dev build. Escalated to Devtech line management for resolution. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Annual Moodle Upgrade |
Closure Approved 25/08/17 |
|
Learn Upgrade |
Closure approved 18/08/17 |
|
Learn Database Migration to Oracle 12 |
Withdrawal approved 23/02/18 |
|
TEL Improvements |
Withdrawal approved 09/03/18 |
| Attachment | Size |
|---|---|
| 168.02 KB | |
| 183.14 KB |