February 2018

Report Date
February 2018

(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL049 VLE Standards

TEL050 Academic Blogging Service

TEL051 Annual Moodle Upgrade (17/18)

TEL052 QMP Upgrade

TEL053 Learn Annual Upgrade

 

Forward Look and RAG

For security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required.

 

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP78-060 TEL Improvements Agreed with Programme Owner 26/02/18 that this project be withdrawn

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

13-Apr-2018

Close

 

RAG Status: AMBER

 

Report by Colin Watt for February 2018

Achievements in Last Period

  • Final report feedback from SSP Business Lead now included - report is currently with LTW Business Lead for finalisation before circulation to Project Board.
  • Project Board to complete approval of report by email before project closure.

Issues

  • No major issues.
  • Project Closure needs to be pushed back again due to an additional resource conflict (Business Lead, LTW).

Next Steps

  • Complete final report and circulate to Project Board members.
  • Close Project.

The project current status is AMBER due to moving the project closure date back one month (agreed with Project Sponsor at monthly TEL Programme meeting); this is due to resource conflict (SSP conflict now resolved, new conflict is LTW Business Lead).

TEL049

VLE Standards

Discretionary

Milestones

18-May-2018 Complete Consultation exercise
25-May-2018 Produce New Templates
22-Jun-2018 Agree Terms of Reference for Pilot(s)
13-Jul-2018 Recommendations Report
14-Dec-2018 Complete Pilot(s)
25-Jan-2019 Review Pilot(s) and Agree plan for Rollout
25-Jan-2019 Agree Communications Plan
25-Jan-2019 Agree Support & Training Plan
24-May-2019 Institutional Templates Available
28-Jun-2019 Complete Rollout
30-Aug-2019 Post Rollout Support
13-Sep-2019 Delivery Sign Off Review
27-Sep-2019 Project Closure

RAG Status: AMBER

Report by Colin Watt for January 2018

Achievements in Last Period

  • Initial comms to all stakeholder groups completed.
  • Consultation process continuing with individual schools.
  • Events now set up for open consultation sessions with staff and students throughout March.

Issues

  • No major issues.
  • Conflict on PM resource remains due to commitments on MVM509. Recruitment underway w/c 12/03/18.

Next Steps

  • Progress consultation process and report initial feedback to first Project Board meeting.

 

Project RAG status is currently AMBER due to PM resource conflict. Recruitment underway and no escalation required at this time.

TEL050

Academic Blogging Service

Discretionary

Milestones:

Planning Review - 23/02/18

Build Complete - 29/06/18

RAG Status: GREEN

Report by Sonali Nakhate for February 2018

Achievements in Last Period

  • Project Brief and Planning milestone approved by WIS
  • First draft of DPIA completed and sent to team and Data Protection Officer for review
  • High level market research for Domain of One's Own complete.
  • Project Board in the process of being setup - Dr. Jen Ross will chair it.
  • Requirements gathering preparation

Issues

  • No major issues.

Next Steps

  • Conduct Requirements gathering session - internal and some external
  • Produce BRD
  • Produce Use Cases
  • Sign off PIA.
  • Project Board members agreed and setup.

TEL051

Annual Moodle Upgrade (17/18)

Compliance

Milestones

Target Datesort descending Title
23-Feb-2018 Analysis and Design
02-Mar-2018 Deploy to DEV
30-Mar-2018 Build
06-Apr-2018 Deploy to TEST (Integration)
29-Jun-2018 Acceptance
12-Jul-2018 Deploy to LIVE
26-Jul-2018 Deployment Sign Off Review (DSOR)
02-Aug-2018 Close
RAG Status: GREEN

Report by Ben Armstrong for February 2018

Achievements in Last Period

  • Signed off Planning Stage
  • Business Requirements Document and Review completed
  • Communication Plan completed
  • System Design Specification and Implementation Plan completed
  • Technical Architecture Document and Review completed
  • Moodle data refreshed from DEV
  • PHP v7.1 installed

Issues

  • The Behat and O365 feasibility studies are continuing as part of the analysis stage but the milestone date has passed; as the essential analysis and design for the upgrade has been completed, the feasibility studies will be assigned a new target milestone date
  • A project team member is taking part in the UCU strike action with potential impact to the date for the DEV upgrade; arrangements are being made to cover this absence

Next Steps

  • Complete Moodle DEV application upgrade
  • Install Moodle plugins in DEV
  • Review Disaster Recovery Plan
  • Sign off Build stage
  • Review Moodle DEV upgrade and resolve any snagging issues
  • Collate UAT documentation including benchmark tests

TEL052

QMP Upgrade (17/18)

Compliance

Milestones

09-Mar-2018

Statement of works approved

23-Mar-2018

VM environments set up on TEST & LIVE

20-Apr-2018

Upgrade to v6 in TEST

01-May-2018

Test migration

11-May-2018

Full migration of data and settings into v6

16-May-2018

TEST signoff

18-Jun-2018

UAT complete

28-Jun-2018

Acceptance signoff

28-Jun-2018

Training completed

04-Jul-2018

Delivery

11-Jul-2018

Deploy to Live

27-Jul-2018

Decommissioning of old servers

30-Jul-2018

Delivery review

31-Jul-2018

Close

RAG Status: AMBER

Report by Sue Woodger for February 2018

Achievements in Last Period

  • Discovery meeting with Questionmark
  • Project Brief, plan and estimates signed off as End of planning 15 February. IS Apps approved at 63 days.

Issues

  • Query has arisen over the domain setup. Discussions are ongoing with Questionmark, DevTech and the Windows team to resolve
  • Statement of works– this is now running late as the domain investigations are taking longer than anticipated

Next Steps

  • To reconcile the domain query
  • Statement of works to be approved

 

RAG commentary: Project is AMBER as domain discussions ongoing - if these are not resolved this could be a showstopper

TEL053

Annual Learn Upgrade (17/18)

Compliance

Milestones

2-Mar-2018 End of planning
3-Jul-2018 Delivery
03-Aug-2018 Close
RAG Status: GREEN

Report by Sue Woodger for February 2018

 

Achievements in Last Period

  • Project brief circulated and comments and amendments made
  • TEL048 project no longer progressing so dependency on this project has been dropped
  • Priority of project raised to High priority. Approved at WIS 2 March 18.

Issues

  • Team were to discuss the plan before sending to wis for approval as it is very tight to hit the hard deadline. Meeting was delayed due to the snowstorm

Next Steps

  • To get project plan agreed between all teams
  • End of planning sign off

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL045

Annual Moodle Upgrade

Closure Approved 25/08/17

TEL043

Learn Upgrade

Closure approved 18/08/17

TEL048

Learn Database Migration to Oracle 12

Withdrawal approved 23/02/18

 

 

 

 

 

 

AttachmentSize
Image icon tel-effort-feb2018.jpg195.18 KB