Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL043 Learn Upgrade

TEL044 Pebblepad Upgrade

TEL045 Annual Moodle Upgrade

 

Forward Look and RAG

 

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP67-012 QMP Upgrade 16/17 Agreed to withdraw project
AP67-063 Learning Analytics Funded days have been transferred to TEL031 and this year's project withdrawn

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

30-Jun-2017

Check point End June

29-Sep-2017

Check point End September

15-Dec-2017

Check point End December

31-Jan-2018

Close

 

RAG Status: 

GREEN

 

Report by Colin Watt for May 2017

Achievements in Last Period

  • Outcome of recommendations to Project Board and discussion at Project Board meeting 27/04/17 was that current work with Civitas on ODL students be ceased and that we use the remaining time of the Civitas contract to work with them on a set of lessons learned and recommendations for taking analytics forwards at UoE in the future. 
  • The Project Team met with Civitas in Edinburgh early May to provide feedback on the Project Board discussions and discuss practical options that could be actioned over the remaining months of the current contract.
  • Due to overlapping leave (PM and Project Sponsor), not possible to hold joint catch up call in June, so this now booked for 07/07/17; dates for Civitas on site visit pencilled in for early August.
  • Due to resource availability, it is unlikely that effort can be focussed over Jun/Jul/Aug so the recommendations are likely to be developed Sep/Oct then a decision made on timing of project closure. For the moment, the monthly checkpoint milestones will be kept in place.

Issues

  • No major issues.

Next Steps

  • Work with Civitas on lessons learned and recommendations.
  • Agree date for final Project Board.
  • Close Project.

 

TEL033

Learn and Student Record Grade Exchange

Discretionary

Milestones

 

RAG Status: BLUE

 

 

Report by Colin Watt for May 2017

Project currently suspended.

Agreement with Programme Owner at May programme meeting that project be withdrawn due to unavailable resource in SSP.

 

TEL043

Learn Upgrade

Compliance

Milestones

23-Jun-2017

Acceptance

04-Jul-2017

Deploy

20-Jul-2017

Deployment review

26-Jul-2017

Close

 

RAG Status: GREEN

 

Report by Anne Mathison for May 2017

Achievements in Last Period

  • Completed integration testing in Test
  • Completed UAT before 23 June. This has been completed earlier, however as there has been some budget left some more work has been planned to be completed in June.
  • Issues 2 and 5 with Learn completed in May
  • Cumulative Patch number 3 has been completed and passed UAT
  • Rubic grades BB student preview has been developed
  • Course menu text issue completed
  • Issue with resourcing on July 4 solved by agreeing with Partners and Programme Manger to complete the Go-live on 5 July

Issues

  • No Issues

Next Steps

  • ECA BB Downloads (Unidesk call) to be fixed and tested in June
  • Rubic grades BB student preview to be tested
  • Complete integration testing in Test
  • Complete further UAT testing(changes completed after CU3 testing work) by 23 June
  • Check all is well in the Upgrade and Building Blocks before golive
  • Go-live on 5 July. Hannah is booked and downtime is planned from 0900-1700 on 5th July which involves testing and tweaking the environment prior to users accessing @ 1700

TEL044

Pebblepad Upgrade

Compliance

Milestones

16-Jun-2017 Integration and Acceptance
20-Jun-2017 Deployment
30-Jun-2017 Training plan in place for rollover of courses
14-Jul-2017 Closure

 

RAG Status: 

GREEN

Report by Karen Beggs for May 2017

Achievements in the last period

Issues

  • MyEd Integration awaiting updated test connection from supplier before final integration test can be signed off. Integration & Acceptance milestone delayed from 2 Jun to 16 Jun

Next steps

  • Equality impact assessment to be completed
  • MyEd team to confirm plans for taking the channel offline on 20th
  • Digital Signage will be displayed 1 week before launch
  • Engagement with course leads/administrators ongoing

 

TEL045

Annual Moodle Upgrade

Compliance

Milestones

09-Jun-2017 Integration
23-Jun-2017 Acceptance
14-Jul-2017 Deployment
21-Jul-2017 Deployment Sign Off (DSOR)
04-Aug-2017 Close

RAG Status: 

GREEN

Report by Karen Stirling for May 2017

Achievements in the last period

  • PHP 5.6.5 has been installed on Dev.
  • Data refresh from Live into Dev. completed
  • Moodle Dev. upgrade and configuration completed
  • Service Team have confirmed they are happy with Dev. Testing
  • Boost Theme frame work design agreed and Dev. homepage completed on-going work for other page in progress
  • PHP 5.6.5 has now been installed on Test

Issues

  • PHP installation was behind scheduled in Dev. environment but there was contingency within the project plan and agreed testing timescales can be reduced, looking at the week commence 10th / 17th July for live deployment. It is looking likely that this will need to deploy week commencing 10th July due to availability of Dev. Tech resource. Reviewing resource options with resource team.
  • Service team also wanted to retest Moodle feed prior to upgrade - completed 5th June

Next steps

  • Refresh data in test environment
  • Upgrade Moodle in Test and complete configuration
  • Update TAD and sign off documentation
  • Complete Boost Theme
  • Commence User acceptance testing
  • Preparation for Live upgrade - Service Alert / Deployment Checklist

The project status is currently GREEN

 

TEL046

STACK Scalable Connection to Learn

Discretionary

Milestones

 

30-May-2017 Delivery Date
30-Jun-2017 Project Closure

RAG Status: 

GREEN

Report by  Karen Beggs for May 2017

Achievements in Last Period

  • The new LTI tool was tested in Moodle 3.2
  • The STACK/Learn integration was successfully launched and UAT completed   
  • A link to technical documentation in github has been added to wiki
  • Delivery milestone completed

Issues

None

Next activities

  • The current LTI link will be deprecated
  • Note, Learn upgrade on 5July (changed from 4 July) - UAT will be scheduled to ensure LTI connection not impacted (after project closure)
  • Complete user documentation (after full cycle on Test Learn)
  • Review server access permissions in School of Maths to ensure no single point of failure
  • Begin comms to school/college
  • Project closure activities

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL029 (AP56-080)

Adaptive Learning Pilot

Closure Approved 12/08/16

TEL030 (AP56-013)

Annual Moodle Upgrade

Closure Approved 12/08/16

TEL025 

Moodle Course Enrolment Management

 

Closure Approved 02/09/16

TEL032

BlackBoard Collaborate MyEd Channel Refresh

Closure Approved 09/09/16

TEL039

WebPA Migration

Closure Approved 09/12/16

TEL042

Virtual Classroom Options Appraisal & Procurement

Closure Approved 05/05/17

TEL034

Lynda.com Implementation

Closure Approved 19/05/17