January 2017

Report Date
January 2017

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

TEL044 (Pebblepad Upgrade) and TEL045  (Annual Moodle Upgrade) have been started.

 

Projects in Progress:

 

TEL031 VLE Student Analytics

TEL033 Learn and Student Record Grade Exchange Feasibility Study

TEL034 Lynda.com Implementation

TEL042 Virtual Classroom - Options Appraisal and Procurement

TEL043 Learn Upgrade

TEL044 Pebblepad Upgrade

TEL045 Annual Moodle Upgrade

 

Forward Look and RAG

 

 

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP67-012 QMP Upgrade 16/17 Scheduled start: January 2017
AP67-063 Learning Analytics Funded days have been transferred to TEL031 and this year's project withdrawn

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL031

VLE Student Analytics

Discretionary

Milestones

31-Mar-2017

Check point End March

30-Jun-2017

Check point End June

29-Sep-2017

Check point End September

15-Dec-2017

Check point End December

31-Jan-2018

Close

 

RAG Status: GREEN

 

Report by Sue Woodger for January 2017

Achievements

  • Civitas onsite 2-3 February
  • Introduced more flexible planning: Due to the style of this project the scope of the project was constantly changing.  To relieve pressure on the effort expended by continually re-planning it was been agreed by the project team to change how planning is recorded within the project. We now follow a Kanban style of recording the major tasks in the project with milestones being check-in points.
  • Revision to project close date: Now 31 Jan 2018 - Agreed at the September Project Board was a change to the closure of the project with the Board wanting the project to run until the Civitas contract has ended which is 31 Jan 2018. We kept the closure milestone at 31 July until decisions came out of the December project Board and we now confirm that closure should be at the end of the Civitas contract.
  • The learning analytics opt-in survey has been issued to the student panel c.400 students to gauge views on the questions and the use of learning analytics within the institution. The survey will be open for 2 weeks then the data will be passed to Yi-Shan Tsai for factor analysis before the survey goes forward to ethics for approval. 

 

Issues

  • Still issues with the data model. Civitas are investigating the issues this month and will be producing data validation this month along with a definition around Active Student. There will be 2 check-ins with Civitas in Feb – 10th and 22nd.  They will also be producing an interruption filter and VLE filter. Data validation is now expected by 22 February
  • Lesley and Steph found issues with the new visuals and are following up with Civitas.
  • There is still reticence to move on including the UG data so Dragan and Sian will look at the data after validation and make their recommendations on how to continue. To include UG we need to take it back to KSE as a change of scope. This is too tight for the 24 March meeting so the recommendations will go to the meeting on the 2 June. For the meeting in March Anne-Marie and Lisa will submit an interim paper outlining where we are and likely possibilities going forward.

Next steps

  • Data Validation complete by 22 February
  • Next Civitas visit due 27 February
  • Civitas doing deep dive into Digital education data 28 February
  • Recommendations from Dragan and Sian
  • Paper for the next KSE meeting on 24 March produced by Anne-Marie and Lisa

 

 

TEL033

Learn and Student Record Grade Exchange

Discretionary

Milestones

 

07-Oct-2016 Phase 2 Planning Complete
07-Jul-2017 Solution Deployed
14-Jul-2017 Project Complete

RAG Status

 

 

Report by Colin Watt (for Iain Moore-McLaughlin) for January 2017

Achievements in Last Period

  • Sponsor has advised that there is likely to be no further progress on this initiative until a decision is made on direction.

Issues

  • Project may be subsumed into Service Excellence programme and may cease to exist from an IS perspective (See recent issue statements).
  • Responses from Service Excellence Programme are delayed. Sponsor is discussing the situation with Director of Learning and Teaching to establish best way forward.

Next Steps​

  • Await feedback on the above.

NB updated by Programme Manager for Project Manager

Current Project RAG Status is AMBER due to awaiting decision on direction of project.

TEL034

Lynda.com Implementation

Discretionary

Milestones

Target date

Title

Complete

11/01/17 

Delivery

NO

31/01/17 

Closure

NO

 

RAG Status: AMBER

 

Report by Nikki Hackett Reed for January 2017

Achievements in Last Period

Integration completed

Peer testing completed

Implemented to TEST

First iteration of UAT completed 

Issues

https://www.projects.ed.ac.uk/unpublished/project/tel034/risks/29

https://www.projects.ed.ac.uk/unpublished/project/tel034/issues/41

Next Steps

UAT completed and signed off

Deployment Checklist completed

Handover/Deploy

Closure report completed/signed off

Project closed

TEL042

Virtual Classroom - Options Appraisal and Procurement

Compliance

Milestones

RAG Status: AMBER

 

 

Report by Colin Watt for January 2017

Achievements in Last Period

  • Handover meetings scheduled with Project Sponsor and new PM.
  • Project Brief ready for review.

Issues

  • Delay to end of planning due to resource conflict (mainly due to PM working on MVM009 and MVM314). This issue is being resolved by a change to PM and the approach has been agreed with the Project Sponsor.

Next Steps

  • Agree project brief, high level timeline, and milestones.
  • Review risks with Project Team.
  • Review budget and resourcing.

 

The project current status is AMBER (time) due to delay to planning tasks however this is expected to return to GREEN next month.

TEL043

Learn Upgrade

Compliance

Milestones

10-Apr-2017 Build
05-May-2017 Integration
23-Jun-2017 Acceptance
04-Jul-2017 Deploy
20-Jul-2017 Deployment review
26-Jul-2017 Close

RAG Status: GREEN

 

Report by Sue Woodger for January 2017

Achievements in Last Period

  • Change of project manager wef 18 January. Sue Woodger took over from Colin Watt
  • Project Brief and plans were approved by project team on 3 February and End of Planning submitted to WIS week beginning 6 February

Issues

  • Project Sponsor believed the project should have a priority 1 status and a change of priority has been lodged with Mark Ritchie

Next Steps

  • Risk meeting to be arranged
  • Confirmation of Timetabling timescales from Timetabling project
  • Build work to commence week beginning 6 February

 

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL029 (AP56-080)

Adaptive Learning Pilot

Closure Approved 12/08/16

TEL030 (AP56-013)

Annual Moodle Upgrade

Closure Approved 12/08/16

TEL025 

Moodle Course Enrolment Management

 

Closure Approved 02/09/16

TEL032

BlackBoard Collaborate MyEd Channel Refresh

Closure Approved 09/09/16

TEL039

WebPA Migration

Closure Approved 09/12/16