August 2016
- Report Date
- August 2016
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The contingency has already been applied to a number of 15/16 projects to balance budgets and enable their completion asap.
Projects in Progress:
TEL031 VLE Student Analytics
TEL032 BlackBoard Collaborate MyEd Channel Refresh
TEL033 Learn and Student Record Grade Exchange Feasibility Study
TEL034 Lynda.com Implementation
TEL039 WEBPA Migration
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP67-043 Annual Moodle Upgrade | Scheduled start: February 2017 |
| AP67-012 QMP Upgrade 16/17 | Scheduled start: January 2017 |
| AP67-013 End of Collaborate License | Scheduled start: October 2016 |
| AP67-014 Pebblepad upgrade | Scheduled start: February 2017 |
| AP67-063 Learning Analytics | Funded days have been transferred to TEL031 and this year's project withdrawn |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||
VLE Student Analytics Discretionary
Milestones
RAG Status RED | Report by Sue Woodger for August 2016 Achievements
Issues
Next steps
Milestones: are dependent on the scope being finalised. Interim milestones have been taken out and will be revisited once scope of the project is resolved. RAG – will continue as RED until we can resolve the PII issue as we cannot plan until it is resolved | ||||||||||||
BlackBoard Collaborate MyEd Channel Refresh Compliance
Milestones
RAG Status AMBER | Report by Chris Konczak for August 2016 Achievements in Last Period
Issues
Next Steps
| ||||||||||||
Learn and Student Record Grade Exchange Discretionary Milestones
RAG Status Green | Report by Iain McLaughlin for August 2016 Achievements in Last Period
Issues
Next Steps
| ||||||||||||
Lynda.com Implementation Discretionary
Milestones
RAG Status RED | Report by Nikki Hackett Reed for August 2016 Achievements this period Data Archiving process agreed and drafted Presentation to SMT LEARN andMoodle integration showcased POC SDS reviewed and signed off Issues Delays in decision making to scope and sign off of BRD https://www.projects.ed.ac.uk/project/tel034/issues/27 Project Re-Plan - Remaining Deliverables https://www.projects.ed.ac.uk/project/tel034/issues/30 Business Lead Annual Leave https://www.projects.ed.ac.uk/project/tel034/issues/31
Next Steps Agree revised milestones for remaining deliverables Agree resource requirements to deliver remaining milestones | ||||||||||||
WEBPA Migration Discretionary
Milestones
RAG Status AMBER | Report by Sue Woodger for August 2016 Achievements
Issues
Next Steps
Project is Amber as revised milestones will only be submitted to WIS this week. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Adaptive Learning Pilot | Closure Approved 12/08/16 |
Annual Moodle Upgrade | Closure Approved 12/08/16 |
Moodle Course Enrolment Management
| Closure Approved 02/09/16 |