- Report Date
- March 2016
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Budget:
Completion of planning has been delayed on the following projects; budgets to be reviewed during estimation with considering to other demands on the programme and the feasibility of using all the remaining days by the end of July.
TEL031 VLE Student Analytics
TEL032 BlackBoard Collaborate MyEd Channel Refresh
TEL033 Learn and Student Record Grade Exchange Feasibility Study
A proposal for the Online Assessment Evaluations (years 2 and 3) days will be discussed at the next Programme meeting.
Additionally, a proposal for using TEL days for the Lynda.com delivery / integration will be discussed at the next Programme meeting.
Programme Balance row stands at 24d
Issues:
TEL029 Adaptive Learning Pilot - PM concerned about feasibility of delivering iteration 3, which is now late. PM organising meeting w/c 11/04/16 to discuss and make decision.
Projects in Progress:
TEL025 Moodle Course Enrolment Management - UAT not complete or signed off. Meeting 07/04/16 to review approach and agree options to resolve barriers to progress.
TEL029 Adaptive Learning Pilot - Deployment of iteration 2 coursework materials completed, but iteration 3 delivery delayed.
TEL030 Annual Moodle Upgrade - Analysis in progress.
TEL031 VLE Student Analytics - End of Planning moved to 15 April.
TEL032 BlackBoard Collaborate MyEd Channel Refresh - End of Planning moved to 15 April.
TEL033 Learn and Student Record Grade Exchange Feasibility Study - End of Planning moved to 15 April.
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP56-080 Online Assessment Evaluations (years 2 and 3) | Scheduled start: TEL029 Adaptive Learning Pilot started using 20d from umbrella project. outstanding budget reduced to 40d in mid-year review. |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary |
TEL025 TEL025 Moodle Course Enrolment Management Discretionary Milestones RAG Status RED | Report by Karen Stirling for March 2016 Achievements in Last Period - UAT commenced and being tested by Moodle Service team
- A number of JIRAS have been raised and resolved / retested
Issues - UAT start was delayed as there was issue with MOODLE Test environment this was investigated by Moodle Service team and resolved by Application Management by completing a database restore
- A number of JIRAS have been raised due to quality of data in IDM Test and impacted by LDAP sync job not having been run on Test environment by ITI for a number of months this has caused further delays to testing also Business lead also on annual leave
- Grouper Permissions issue highlighted that test users all require Sys Admin access to view folders and will impact users in Live environment. A workaround has been proposed by Service Management. A problem record has been raised for investigations into the upgraded version of Grouper to understand permissions issue.
- Review completed for impacts of delays on project budget additional 13 days required to complete project
- Revised milestones proposed to Project Sponsor, Programme Manager and Business Lead however due to concerns around data quality and progress out with projects for changes to Course code and Grouper concerns Project Sponor has placed a halt to UAT and proposed milestones not approved. Meeting being held with Enterprise Architect, Service Management and project team including Project Sponsor on 7th April to discuss way forward.
- A further issue has been encountered with the MOODLE Test environment which is being investigated by the Service team, therefore the testing team have had to use a workaround to continue testing
Next Steps - UAT to recommence, complete and sign off Acceptance
- Deployment Checklist
- Preparation for deployment – checklist, service alert etc.
- Deployment to Live
The project status is RED due to the UAT being placed on hold and action plan agreed and in place. |
TEL029 Adaptive Learning Pilot Discretionary Milestones RAG Status AMBER | Report by Sue Woodger for March 2016 Achievements- Iteration 2 materials have been delivered
- The milestones for Analytics configuration and Deploy analytics were withdrawn as the SME and Lead Editor believed that the current analytics delivered what they required. They did mention that it was difficult to evaluate without student data and they will have better feedback once more data comes through students' use. However any updates would come under future improvements (no development within this project) and will be captured in the closure report.
- Lead editor was able to finally confirm that technical issues were all ironed out and the milestone closed (technical issues milestone)
- Lead editor has confirmed that iteration 3 has started but approach has changed from lectures to topics
Issues- There were delays to iteration 3 starting as there was no decision on which materials were going into iteration 3
- Although an initial topic 'Carbon in Oceans' has been started there is still no decision on what other topics are to be included in iteration 3.
- Tom Challands is creating the materials for iteration 3 and his contract was expected to finish at the end of April but this has been extended to the end of July and he will be developing iteration 3 materials within this time. This means that the iteration 3 delivery will be delayed which will impact on the closure date. PM has submitted a request for extending the project and will discuss with project sponsor when she returns from leave. However this discussion will opened up to discuss the confidence is realising iteration 3. Until the discussions have taken place and a decision reached milestones have been temporarily moved out within this year without extending timescales.
- Feedback survey has been delayed as author (Amy Woodgate) is waiting on SME’S supplying feedback to update the forms. Milestone has been delayed until 18 April
Next steps- Feedback on updates to the existing surveys to be sent to Amy so she can update the surveys
- Agreement reached on iteration3
Project is AMBER as current milestones are at risk as current projections from iteration 3 means we will have to extend the project. Discussions to be held with project sponsor on her return from leave |
TEL030 Annual Moodle Upgrade Compliance Milestones RAG Status GREEN | Report by Colin Forrest for March 2016 Achievements in the last period - The BRD has been drafted and circulated for sign off.
- Although slightly out of sync Software Development have started the analysis of the new version and the SDS is being updated. This is helping to keep us on track as we get the BRD signed off.
Issues - Other than a delay in getting the BRD signed off due to Annual Leave and illness we are on track. We do not anticipate this will delay the plan as a whole.
Next steps - We will sign off the Analysis and Design phases of the project.
- We will refresh DEV and install the updated version of Moodle.
|
TEL031 VLE Student Analytics Discretionary Milestones RAG Status AMBER | Report by Sue Woodger for March 2016 Achievements- Civitas supplied a summary of their finds – this is t be discussed with Anne-Marie Scott and Lisa Dawson
Issues- Project brief delayed due to late replies and PM sick leave – to be re-issued and approved
Next steps- Project brief signed off by 15 April 16
- Meetings set up to allocate tasks and take project forward
Programme Manager: The project status is AMBER due to delay in planning (time). |
TEL032 BlackBoard Collaborate MyEd Channel Refresh Compliance Milestones RAG Status AMBER | Report by David Watters for March 2016 Achievements in Last Period - Project Brief completed
- Business requirements prepared for review
- Design template received from Blackboard
Issues - Sign-offs delayed because of leave and sickness
- Issues round resourcing to be pursued
Next Steps - Sign-off planning stage
- Sign-off business requirements
- Commence work on system design
Programme Manager: The project status is AMBER due to delay in planning (time). |
TEL033 Learn and Student Record Grade Exchange Discretionary Milestones RAG Status AMBER | Report by Jason Fiddes for March 2016 Achievements in Last Period - Project Brief and plan agreed in principle
- Phase 1 (15/16) to focus on solution design, planning and feasibility.
- Phase 2 (16/17) to focus on delivery
Issues - Planning milestone of 18/03 - not achieved - due to issues securing resources.
Next Steps - Complete planning
- Sign off brief
Programme Manager: The project status is AMBER due to delay in planning (time). |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
TEL017 (AP45-038) VLE Student Analytics | Closure Approved 04 September 2015 |
TEL018 (AP45-037) QMP Upgrade | Closure Approved 25 September 2015 |
TEL022 (AP45-058) Moodle Upgrade | Closure Approved 11 September 2015 |
TEL023 (AP34-049) Next Generation Voting System Implementation | Closure Approved 11 September 2015 |
TEL024 TEL024 Migration of MVM UG to PebblePad | Closure Approved 02 October 2015 |
TEL021 (AP45-039) TELS Management Information | Closure Approved 04 December 2015 |
TEL015 (AP45-039) Online Assessment/Feedback Evaluations – FACS | Withdrawal Approved 24 November 2015 |
(AP56-012) Coldfusion Upgrade of Learn Services MyEd Channel | Withdrawn |