Programme Report for September 2012
- Report Date
- September 2012
Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for Mark Wetton and Anne-Marie Scott (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The programme continues, with SMART for HSS project starting w/c 8th October, and the Data Hub Enhancements project transferred from DEI to TEL, as a Funded project. This month also saw the closure of Learn.
At present, there is a shortfall of circa 100 days for the planned work for UnFunded projects and the Programme Budget for UnFunded work. The LAT010 carry over, LAT011 carry over and TEL001 PebblePad Upgrade total circa 140 days and the unfunded days in the programme only 39 days. LAT010 overrun is covered by UnFunded Budget.
IS Apps Director has authorised the overspend of 60 days for LAT011 to stay until mid-year review, when the situation will be re-assessed.
IS Apps Director has also recommended that The PebblePad Upgrade project be reviewed at mid-year, and a decision to withdraw project, postpone to 13/14, or to do the project as-is or descoped will be taken then.
WIS asked for feedback on decision and expressed no concerns.
Actions from programme meeting.



Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
AP23-018 Pebblepad Upgrade Compliance Milestones Feb-12 Planning Jun-13 Delivery RAG Status Amber | Plan Programme Owners agree with schedule. Due to carry over from 2011/2 impacting on the programme budget, there is insufficient budget to complete the work - this is a programme governance issue to be escalated. IS Apps Director has recommended that The PebblePad Upgrade project be reviewed at mid-year, and a decision to withdraw project, postpone to 13/14, or to do the project as-is or descoped will be taken then.
Dependencies None |
AP23-035 Extension of SMART to HSS HSS College Ring-Fenced Milestones Oct-12 Planning May-13 Delivery RAG Status Green | Plan Franck Bergeret has been assigned as Project Manager, with Dave Watters as Business Analyst also providing continuity with recent SMART projects. Franck will set up new project send week of October. Proposal and Estimates, also list of enhancements
Dependencies none |
AP23-045 DEI Data Hub- Enhancements Funded (IS) Milestones TBC Planning TBC Delivery RAG Status Red
| The project has been transferred from DEI programme, and wil be funded by IS. At present, there is a hard dependency on completion of projects to enhance SOA and IDM, so start date is unknown. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||
TEL002 (AP23-037) MVM College Ring-Feanced
Milestones
RAG Status GREEN
| Report by Franck Bergeret for September 2012 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||||||
LAT011 (AP12-030) Virtual Classroom Implementation Very Important Milestones
RAG Status GREEN | Report by Maurice Franceschi for September 2012 IS Apps Director has authorised the overspend of 60 days for LAT011 to stay until mid-year review, when the situation will be re-assessed. Achievements in Last Period
Issues The build of MyED was not signed-off, due to contraints on time and the testing already done that anticipates UAT, PM felt confident in taking the risk and deploying MyEd to TEST so that project coudl keep on track for UAT. Next Steps
| ||||||||||||||||||||||
Section Four: Projects Closed / Withdrawn
| Project Info | Project Managers Commentary |
LAT010 (AP12-022) Compliance Milestones 28-09-2012 Closure
| Project completed. |
Actions from September Programme Meeting (5th October)
| Fix programme report so that the images fit on a screen | Maurice | Done |
| Add previous monthly programme actions onto current report | Maurice | Done |
| Ask for Registry to take on SMART project | Maurice |
Maurice talked to Karen on Monday 8th and has asked for this transfer. Karen to get back.
|
| When is the current review of programme and prject structure expected to complete | Maurice to find out | |
| Pebblepad Funding - clarify situation | Bryan to talk to Simon | |
| LAT010 is not showing as Closed on prject website | Maurice to action | Done |
We will focus on New MyED, given the current on schedule status of the MyED Upgrade Project. The risk of not having a working Old MyED channel to be accepted, with the three daysd Richard has w/c 22nd to be used as fallback if the upgrade is postpoened or backed out.
| Programme Owners to confirm the approach and who owns the risk,
Programe owners to decide if project board needs to be informed. | |
| Email to confirm the New My ED approach to Project Team. | Tim | |
Prgoramme owners of DEI and TEL agreed that the DEI projects should be moved into TEL programme, as DEI will not be funding DEI projects in 2012/13.
| Maurice to request expansion of TEL programme with transferred projects, and removal of DEI programme. Programme Owners/Simon to confirm the Funding for DEI projects. DEI Pcode effort to be transferred over to TEL programme management. | |
| For PebblePad v 3, we need user requirements and the dates when an upgrade can be scheduled (May-July?) confirmed. | Mark to talk to Robert C. | |
Actions from August Programme Meeting (13th Sept)
| SMART to be moved out of TEL to Registry | Maurice | SMART still in TEL - Sheila to talk to Karen Action re-iterated in September No further action |
| Review how projects such as Speedwell are placed in programmes without programme owner consent | Maurice Shiela | Programme structure is under review just now No further action |
| See up meeting to dicuss options for TEL budget, with Simon | Maurice | Completed |
| Review ETC for TEL011 with Tim | Maurice | Completed |
