Programme Report for September 2012

Report Date
September 2012

 

Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for Mark Wetton and Anne-Marie Scott (Programme Owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

The programme continues, with SMART for HSS project starting w/c 8th October, and the Data Hub Enhancements project transferred from DEI to TEL, as a Funded project. This month also saw the closure of Learn.  

At present, there is a shortfall of circa 100 days for the planned work for UnFunded projects and the Programme Budget for UnFunded work. The LAT010 carry over, LAT011 carry over and TEL001 PebblePad Upgrade total circa 140 days and the unfunded days in the programme only 39 days. LAT010 overrun is covered by UnFunded Budget.

IS Apps Director has authorised the overspend of 60 days for LAT011 to stay until mid-year review, when the situation will be re-assessed.

IS Apps Director has also recommended that The PebblePad Upgrade project be reviewed at mid-year, and a decision to withdraw project, postpone to 13/14, or to do the project as-is or descoped will be taken then.

WIS asked for feedback on decision and expressed no concerns.

Actions from programme meeting.

 

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary

AP23-018

Pebblepad Upgrade Compliance

Milestones

Feb-12   Planning

Jun-13   Delivery  

RAG Status Amber  

Plan Programme Owners agree with schedule.

Proposal and Estimates

Due to carry over from 2011/2 impacting on the programme budget, there is insufficient budget to complete the work - this is a programme governance issue to be escalated.

IS Apps Director has recommended that The PebblePad Upgrade project be reviewed at mid-year, and a decision to withdraw project, postpone to 13/14, or to do the project as-is or descoped will be taken then.

 

 

Dependencies None

AP23-035

Extension of SMART to HSS HSS College Ring-Fenced

Milestones

Oct-12   Planning

May-13   Delivery  

RAG Status Green

Plan Franck Bergeret has been assigned as Project Manager, with Dave Watters as Business Analyst also providing continuity with recent SMART projects.

Franck will set up new project send week of October.

Proposal and Estimates, also list of enhancements

 

Dependencies none

  

AP23-045 DEI Data Hub- Enhancements

Funded (IS)

Milestones

TBC  Planning

TBC   Delivery  

RAG Status Red

 

The project has been transferred from DEI programme, and wil be funded by IS.

At present, there is a hard dependency on completion of projects to enhance SOA and IDM, so start date is unknown.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

TEL002 (AP23-037)

Speedwell Database Hosting

MVM College Ring-Feanced

 

Milestones

 

Target dateTitle
26-Sep-2012Convert and migrate data into 3 Test databases
26-Oct-2012Check data migrated/software in Test
02-Nov-2012ASOR sign off test
12-Nov-2012Convert and Migrate data in the 3 Live databases
19-Nov-2012Package and deploy Live to desktop
26-Nov-2012Deployment sign off DSOR
12-Dec-2012Closure
 

RAG Status

GREEN

 

Report by Franck Bergeret for September 2012

Achievements in Last Period

  •  Brief signed off
  • TAD reviewed
  • First two Speedwell softwares installed and linked OK with the Test database on the new shared server 

 

Issues

  • N/A

Next Steps  

  • Data conversion and migration may not be required as there is an import facility in the new version of the third software due end Oct. Business Lead to confirm and PM to update project scope accordingly.
  • A new version of the third software will be released end Oct 12. The UAT can only start after that date. 
  • To agree new dates once new project scope confirmed by Business Lead.

 

 

LAT011 (AP12-030)

Virtual Classroom Implementation

Very Important  

Milestones  

Target dateTitle
08-Aug-2012Phase 3: MyEd Integration - Analysis/Design Review
10-Aug-2012Phase 2: Learn Integration - Deployment Review
25-Aug-2012Phase 4: MVM Integration - Development Review
07-Sep-2012Phase 4: MVM Integration - Acceptance Review
03-Oct-2012Phase 3: MyEd Integration - Build Review NOT ACHIEVED - needs rescheduled
10-Oct-2012Phase 3: MyEd Integration - Integration Review
30-Oct-2012Phase 3: MyEd Integration - Acceptance Review
05-Nov-2012Phase 3: MyEd Integration - Delivery
21-Nov-2012Phase 3: MyEd Integration - Deployment Review
07-Dec-2012Closure

RAG Status

GREEN

Report by Maurice Franceschi for September 2012

IS Apps Director has authorised the overspend of 60 days for LAT011 to stay until mid-year review, when the situation will be re-assessed.

Achievements in Last Period

  • Phase 3: MyED implemented in TEST.
  • Phase 4: MVM launched the new service.  

Issues

The build of MyED was not signed-off, due to contraints on time and the testing already done that anticipates UAT, PM felt confident in taking the risk and deploying MyEd to TEST so that project coudl keep on track for UAT.

Next Steps

  • Phase 3: Build Review needs completed. UAT to proceed. List of JIRAs need reviewed and prioritised to see what can be fixed within budget remanining.
  • Phase 4: Check on issues raised after deployment - sign-off phase if ok.

 

  

 

Section Four: Projects Closed / Withdrawn

 

Project InfoProject Managers Commentary

LAT010 (AP12-022)

VLE upgrade to Learn 9.1

Compliance

Milestones 28-09-2012 Closure

 

Project completed.  

Closure Report

 

Actions from September Programme Meeting (5th October)

Fix programme report so that the images fit on a screenMauriceDone
Add previous monthly programme actions onto current reportMauriceDone
Ask for Registry to take on SMART projectMaurice

Maurice talked to Karen on Monday 8th and has asked for this transfer. Karen to get back.

 

When is the current review of programme and prject structure expected to completeMaurice to find out 
Pebblepad Funding - clarify situationBryan to talk to Simon 
LAT010 is not showing as Closed on prject websiteMaurice to actionDone

We will focus on New MyED, given the current on schedule status of the MyED Upgrade Project. The risk of not having a working Old MyED channel to be accepted, with the three daysd Richard has w/c 22nd to be used as fallback if the upgrade is postpoened or backed out.

 

Programme Owners to confirm the approach and who owns the risk,

 

Programe owners to decide if project board needs to be informed.

 
Email to confirm the New My ED approach to Project Team.Tim 
   

Prgoramme owners of DEI and TEL agreed that the DEI projects should be moved into TEL programme, as DEI will not be funding DEI projects in 2012/13.

 

Maurice to request expansion of TEL programme with transferred projects, and removal of DEI programme.

Programme Owners/Simon to confirm the Funding for DEI projects.

DEI Pcode effort to be transferred over to TEL programme management.

 
   
For PebblePad v 3, we need user requirements and the dates when an upgrade can be scheduled (May-July?) confirmed.Mark to talk to Robert C. 
   
   

 

Actions from August Programme Meeting (13th Sept)

SMART to be moved out of TEL to RegistryMaurice

SMART still in TEL - Sheila to talk to Karen

Action re-iterated in September

No further action

Review how projects such as Speedwell are placed in programmes without programme owner consentMaurice Shiela

Programme structure is under review just now

No further action

See up meeting to dicuss options for TEL budget, with SimonMauriceCompleted
Review ETC for TEL011 with TimMauriceCompleted