Report for Dec 2019

Report Date
December 2019

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shelagh Green (Careers) ,  Rena Gertz (Data Protection Officer), Anne Grzybowski (Records Management) , Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD), Andy Shanks (Student Wellbeing)  and other stakeholders

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is AMBER , as 2 projects are AMBER.

The STU programme should move back to GREEN next month, as progress is being made with both STU265 and STU266.

For STU265 , the contract discussions with supplier Fivium are expected to conclude in Jan , and then the implementation is being re-planned for the March to July period working round availability of business resources in the USG Records Management team

STU266 should move to GREEN next month as the draft Options appraisal for UG & PG Degree finder has now been published to the project stakeholders ahead of the end of Jan deadline for funding bids to the next 3-year planning round 

 

 

RAG & Forward Look to end of Dec 2019

 

STU RAG status as at end of Dec 2019

 

Resources to end of Dec 2019

 

STU actual spend to end of Dec 2019

 

 

 

 

 

 

Section Two: Projects Not Started

 

AP90-039 CAM- Support for Compliance

 19 days left in balance row for 2019-20, this is contingency budget for in-year compliance , if not needed by  Mar 2020, the days will go back into the ISG Core compliance funding pot for another urgent core work to be completed by July 2020 

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

 

Target Date  Title
22-Nov-2019 Deployment Sign-Off
Dec-2019 Closure

RAG Status

CLOSED (BLUE)

  Report by Andy Stewart for December 2019

Achievements this period

  • Project Closed

Issues

  • n/a

Next steps

  • n/a

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

Project closure 20-Dec-2019

RAG Status:

GREEN

 Report by Chris Konczak for December 2019

Achievements this period

  • Fix for PG search deployed to LIVE in January to avoid the risk of deploying before the Christmas break and no one available to fix any issues.
  • Closure report has been circulated, those who have replied have approved the closure.

Issues

  • None.

Next Steps

  • Project closure is to be submitted to WIS on 17/01/2020

 

STU265 - G-Cloud replacement of FOI Request planning tool

Category:  Compliance

Milestones

Revised milestone dates tbc

Target Datesort descending Title
14-Feb-2020 Purchase and contract sign off.
01-May-2020 Product Implementation
15-May-2020 User Acceptance Testing - Sign Off
29-May-2020 Go Live
12-June-2020 Migration of Historic Data
19-June-2020 Legacy ColdFusion Decommissioned   
19-June-2020 Deployment Sign Off
26-June-2020    Project Closure

Rag Status: AMBER

 

Report by Ken Miller for December 2019

Achievements

  • Progress with Procurement and Fivium regarding contract review and sign off.
  • Work on overall implementation plan in conjunction with Fivium to schedule resource.
  • Fivium drafting service order form to detail their updates to the standard eCase product.

Issues

  • Delay in procurement process is delaying fully engaging with Fivium in the technical aspects of the transition process.  Project has now been re-assigned to our third UoE procurement contact this year.
  • Overall project delay will mean that the milestones need to be revised once implementation plan has been agreed.
  • Key Records Management contact is moving on from UoE.  Project replacement has been identified but will not be available until mid-March at the earliest. 

Next Steps

  • Review Fivium service order form and confirm required updates to align eCase with Scottish regulations.
  • Progress with Procurement and Fivium regarding contract review and sign off.
  • Work on overall implementation plan in conjunction with Fivium to schedule resource.
  • Engagement with Fivium regarding case migration process to the replacement eCase.
  • Reschedule project milestones.
AMBER RAG Commentary
tbc

 

STU266 - UG & PG Degree Finder Options Appraisal

Category:  Discretionary

Milestones

Milestone Due Date
Delivery (Options Appraisal) 30-Jan-2020
Closure 17-Feb-2020

Rag Status: 

AMBER

 

Report by Kevin Hone for December 2019

Achievements this period

  • A workshop was held in which answers were provided by the business that brought clarity to what is expected when it comes to the costing of future work.
  • Access to a 3rd party Content Management System, Gather Content has been provided to the Lead Architect. Availability of this tool was not previously known and is presently being considered as more favourable to that of sole use of Django or Drupal.
  • Early assessment is that future work could make use of APIs to join with the golden source of data with Django as a tool supporting the back-end repository and front-end presentation layer. 

Issues

  • The Lead Architect has an extended period of holiday following the Christmas break which could put the delivery time-line at risk. 

  • No forward planning to compensate for loss of the Project Manager in January should project extend beyond this period.

Next steps

  • Contractor extension is being progressed and agreement to prioritise technical work to support the project and planning timeline.

  • Options appraisal paper to be produced for review.

CLOSED Projects

 

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

RAG Status

BLUE (Closed) 

Report by Jamie Thin 

STU253 - PGR Opportunity Finder

Category: Discretionary

RAG Status

BLUE (Closed)

Report by Geoff Cropley 

 

 

STU258 - Careers - Student Alumni Community Networking Platform

Category : Discretionary

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING TOOL 

Category:  Compliance

BLUE (Closed)

Report by Ken Miller

STU264 - CAM UG & PG Degree Finders Small Enhancements

Category: Discretionary

RAG Status

BLUE (Closed)

 

Report by Chris Konczak

Programme Status
Has formal escalation taken place?
No