Report for Oct 2019

Report Date
October 2019

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shelagh Green (Careers) ,  Rena Gertz (Data Protection Officer), Anne Grzybowski (Records Management) , Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD), Andy Shanks (Student Wellbeing)  and other stakeholders

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is AMBER , as 2 projects are AMBER

 

 

RAG & Forward Look to end of Oct 2019

 

STU RAG status as at end of Oct 2019

 

 

Resources to end of Oct 2019

 

STU actual spend to end of Oct 2019

 

 

 

 

 

Section Two: Projects Not Started

 

AP90-039 CAM- Support for Compliance

 36 days left in balance row for 2019-20, this is contingency budget for in-year compliance , if needed not expected to start until Mar 2020

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

 

Target Date  Title
22-Nov-2019 Deployment Sign-Off
22-Nov-2019 Closure

RAG Status

AMBER

  Report by Andy Stewart for October 2019

Achievements this period

  • SSO
    • Single Sign-On has now now been successfully configured via the Test EASE environment 
    • Testing to determine the impact of implementing SSO has commenced and all testing to-date has been successful
    • It has now been agreed that the two-phase login is technically acceptable, whereby;
      • the user is required to have a valid account within the application 
      • the user  is required to have an active EASE account
    • SSO has now been configured for the Live environment, and is now ready to be switched-on
  • Email Issue 
    • An issue regarding the email address being generated by the system has been resolved 
  • Project Closure 
    • The project closure report has been completed and approved by the the project sponsor and senior business user 

Issues

  • Final SSO testing regarding visitor accounts has been delayed due to a number of factors 
    • Issues with the generation of visitor accounts - now resolved 
    • Unavailability of the project team to complete testing in October through a combination of holidays and illness  
  • Email
    • the issue regarding the email address being generated by the system, after the last upgrade, has been resolved 
  • The project is currently predicting an overspend of 12 days, including 1 day to complete all remaining project activity

Next steps

  • SSO   

    • Complete technical implementation for SSO, on the live environment, if pertinent 
  • Complete project closure
RAG Commentary
The scheduled project closure in October has been delayed whilst final testing for visitor accounts is completed, whilst noting that all other SSO testing has been successfully completed. Final testing is scheduled to be completed in early November. There is currently no impact to the either the system usage nor the business.

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

Milestones

UAT sign-off complete for Security Strengthening of UG & PG Degree finder 01-Nov-2019
Deploy to LIVE - WP1 - Security Strengthening of UG & PG Degree Finders 05-Nov-2019
Project closure 22-Nov-2019

RAG Status:

AMBER

 Report by Chris Konczak for October 2019

Achievements this period

  • DEV completed tested. No issues reported.

Issues

  • Deployment of UG and PG to TEST gave "Too many authentication failures".  This was resolved before Dev Tech's annual leave, but required a bamboo deployment the following week. There was an issue raised as the developer was not sure where to deploy the code as there are a number of active pages where the code could be deployed to. This was resolved with the help of Production, but the delay reduced the time testing could be carried out by production.
  • Issue raised regarding the completion of the deployment to TEST and would affect LIVE - Production and Development recommended that the person deploying to TEST should be the person deploying to LIVE, and also requires someone from EdWeb involved. The deployment steps required Development, Production and EdWeb involvement. This was pointed out when attempting to carry out the deployment to TEST and as a result was not completed.  EdWeb contact for this was on annual leave, returning on 04/11.
  • Cost to be reviewed as 5 extra days required. Project is Amber as a result

 

Next Steps

  • Complete the deployment to TEST with the involvement of all teams
  • Integration testing sign off
  • Revise deploy to LIVE milestone
  • Deploy to LIVE
  • DSOR
  • Closure

 

STU265 - G-Cloud replacement of FOI Request planning tool

Category:  Compliance

Milestones

Milestone Date
Product Procurement 30-Aug-2019
Product Implementation tbc - from Jan 2020
User Acceptance Testing - Sign Off tbc
Go Live tbc - Expected March 2020
Deployment Sign Off tbc
Migration of Historic Data tbc
Legacy ColdFusion Decommissioned tbc

Rag Status: AMBER

 

Report by Ken Miller for October 2019

Achievements

  • Work on overall implementation plan in conjunction with Fivium to schedule resource.
  • Commence internal process regarding case migration to the replacement eCase.
  • Engage with Procurement and Legal regarding process to purchase preferred solution.
  • Continued engagement with Fivium regarding various aspects of transition process.

Issues

  • Delay in procurement process is delaying fully engaging with Fivium in the technical aspects of the transition process.  Project has now been re-assigned to our third UoE procurement contact this year.
  • Overall project delay will mean that the milestones need to be revised.

Next Steps

  • Progress with Procurement regarding process to purchase preferred solution. Aim to complete by the end of November.
  • Work on overall implementation plan in conjunction with Fivium to schedule resource.
  • Engagement with Fivium regarding case migration process to the replacement eCase.

Rescheduled milestone dates still to be approved by project , USG and ISG governance

AMBER RAG Commentary
The project as a whole has progressed more slowly that planned. This means that although the contract should be signed in November / December the initiation date will be early Jan with a go live date in early March. Having reviewed revised timescales with Records Management this will fit better with their resource availability.

STU266 - UG & PG Degree Finder Options Appraisal

Category:  Discretionary

Milestones

Milestone Due Date
Delivery (Options Appraisal) 29-Nov-2019
Closure 13-Dec-2019

Rag Status: 

AMBER

 

Report by Ben Armstrong for October 2019

Achievements this period

  • The planning stage was approved by the project team
  • An architecture diagram showing the 'as-is' system set-up was produced
  • Further discussions have taken place on preparing how to capture business requirements

Issues

  • The project budget increase was approved (from 25 days to 35 days) so the Cost RAG moves to GREEN this month.
  • The business analyst assigned to the project was re-assigned to another programme; this has prevented the business requirements work starting, which increases the risk of missing the business requirements milestone.  A new business analyst starts next week.  The increased risk means that the Time RAG remains at AMBER this month.

Next steps

  • Sign off project planning stage
  • Undertake requirements capture sessions and document requirements
  • Start market research / UCISA communication

CLOSED Projects

 

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

RAG Status

BLUE (Closed) 

Report by Jamie Thin 

STU253 - PGR Opportunity Finder

Category: Discretionary

RAG Status

BLUE (Closed)

Report by Geoff Cropley 

 

 

STU258 - Careers - Student Alumni Community Networking Platform

Category : Discretionary

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING TOOL 

Category:  Compliance

BLUE (Closed)

Report by Ken Miller

STU264 - CAM UG & PG Degree Finders Small Enhancements

Category: Discretionary

RAG Status

BLUE (Closed)

 

Report by Chris Konczak

Programme Status
Has formal escalation taken place?
No