Report for July 2019

Report Date
July 2019

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Ailsa Vamplew (SRA), Lesley Stokes (SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shellagh Green (Careers) , Damon Querry (RIS), Rena Gertz (Data Protection Officer), Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD) , Sarah Macallister (IAD) , Andrew Crossland (Student Systems) , Rena Gertz (GaSP)  and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is AMBER, as 2 projects are AMBER

 

--

Programme Risks ( RED & AMBER)

   

UG & PG Degree finder-Business Continuity Plan to be updated by Dec 2019( STU260 - CAM UG & PG Degree Finders) AMBER             Niall Bradley
     
Existing 'Mobility Online' solution will not be decommissioned by SEP SAS0014/ SAS016 Work & Study Away project ( need to be kept for in progress Student exchanges and to continue to support Staff exchanges going forward)  AMBER Jim McGeorge

 

RAG & Forward Look to end of July 2019

 

STU RAG to end of July 2019

 

 

Resources to end of July 2019

 

STU actual spend to end of July 2019

 

 

 

 

Section Two: Projects Not Started

 

AP90-039 CAM- Support for Compliance 50 days core for potential compliance work, 10 days to be set aside to complete STU260 security work

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

The revised (projected) milestones still require to be confirmed with the project sponsor.

Target Date  Title
03-Jul-2019 Deployment to Live
22-Jul-2019 Deployment Sign-Off
16-Aug-2019 Closure

RAG Status

GREEN

  Report by Andy Stewart for July 2019

Achievements this period

  • Go-Live
    • Application is now live and being used across the University
  • DPIA
    • Completed actual DPIA for the actual Assessment Automation application
  • Accessibility
    • eQIA completed and published
    • Details of Accessibility report forwarded to the supplier for consideration
  • SSO
    • Investigations towards implementing SSO are on-going
    • Completed Regular Data Feed request form and forwarded to golden copy owners for approval
  • SMTP
    • Investigations towards implementing SMTP are on-going

Issues

  • Whilst investigations are on-going regarding SSO and SMTP, this has been hampered by the lack of technical resource availability

Next steps

  • Accessibility 
    • Review supplier response to Accessibility Report
  • System Configuration  
    • Confirm Regular Data Feed approval regarding SSO 
    • Complete technical implementation for SSO and SMTP
    • Complete Email configuration
  • Service Management to clarify service arrangements and SLA with the business 
  • Complete project closure

 

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

End of Planning 02-Jul-2019
Complete Build in DEV for Security Strengthening of the UG & PG Degree finders 05-Jul-2019
Complete Integration Testing in TEST for Security Strengthening of the UG & PG Degree finders 10-Jul-2019
UAT sign-off complete for Security Strengthening of UG & PG Degree finder 18-Jul-2019
WP1 - Deploy to LIVE - WP1 - Security Strengthening of UG & PG Degree Finders 23-Jul-2019
Project closure 02-Aug-2019

RAG Status:

AMBER

 Report by Chris Konczak for July 2019

Achievements this period

  • Development work for security strengthening completed, needs Dev Tech to also complete their part

Issues

  • Dev Tech availability - there was no availability in July 2019 to complete this work, so the project has moved into 2019/20
  • No budget for 2019/20, therefore project will have to complete using support days

Next Steps

  • Milestone replan required
  • Accurate estimate of days required to finish the project in 2019/20
  • Dev Tech to complete security strengthening work
  • Deploy and complete testing in TEST, then deployment to LIVE
  • DSOR

Milestones

To be replanned.

 

STU265 - G-Cloud replacement of FOI Request planning tool

Category:  Compliance

Milestones

To Be Agreed as part of End of Planning

Rag Status: 

AMBER

Report by Ken Miller for July 2019

Achievements this period

  • Project funding has been agreed with USG to fund the software purchase and ISG to fund the effort.
  • Milestones rescheduled in response to delay caused by lack of funding agreement.
  • Project Brief raised at WIS but not approved.
  • Product evaluation completed and preferred solution identified as eCase from Fivium.
  • Access to preferred solution provided for equality access assessment and report produced.

Issues

Next steps

  • Project Brief raised and approved.
  • Assist with with the production and sign off of DPIA
  • Assist with with the production and sign off of EqIA assessment and liaise with eCase regarding access recommendations.
  • Engage with Procurement regarding process to purchase preferred solution.

 

CLOSED Projects

 

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

RAG Status

BLUE (Closed) 

Report by Jamie Thin 

STU253 - PGR Opportunity Finder

Category: Discretionary

RAG Status

BLUE (Closed)

Report by Geoff Cropley 

 

 

STU258 - Careers - Student Alumni Community Networking Platform

Category : Discretionary

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING TOOL 

Category:  Compliance

BLUE (Closed)

Report by Ken Miller

STU264 - CAM UG & PG Degree Finders Small Enhancements

Category: Discretionary

RAG Status

BLUE (Closed)

 

Report by Chris Konczak