Report for Dec 2018

Report Date
December 2018

Report compiled by  Jamie Thin (IS Apps Programme Manager) 

for Jim McGeorge (USG), Tracey Slaven (GASP) ,Theresa Merrick (CAM) , Niall Bradley (CAM),  Steven Ross (CAM) , Paddy Corscadden (SDS),Gael Campbell (SDS) ,Ronnie Millar( SCS) ,Jane Johnston (SRA), Rebecca Gaukroger(SRA), Ailsa Vamplew (SRA), Lesley Stokes (SRA), Laura Cattell (SRA) , Clare MacKay (SRA) , Shellagh Green (Careers) , Damon Querry (RIS), Rena Gertz (Data Protection Officer), Sara Cranston (Records Management), Karsten Moerman (IAD) , Jon Turner (IAD) , Sarah Macallister (IAD) , Andrew Crossland (Student Systems) , Rena Gertz (GaSP)  and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

 

The STU programme is AMBER  as  three of the projects are AMBER.

STU contingency has been reduced for 2018-19, as 24 days contingency has been re-allocated to STU263 to cover the additional effort for the Records Management options appraisal.

Overall the burn-rate of IS Apps spend across the STU projects for 18-19 after first 5 months is 36% after 41% of elapsed time, this is slightly below expected burn rate.

 

 

Programme Risks ( RED & AMBER)

   

UG & PG Degree finder-Business Continuity Plan to be updated by Dec 2019 ( STU260 - CAM UG & PG Degree Finders) AMBER             Niall Bradley
Additional compliance work may affect scheduling and budgets of other projects during 2018-19  (STU Programme) AMBER Jim McGeorge
Existing 'Mobility Online' solution will not be decommissioned by SEP SAS0014/ SAS016 Work & Study Away project ( need to be kept for in progress Student exchanges and to continue to support Staff exchanges going forward)  AMBER Jim McGeorge

 

RAG & Forward Look to end of Dec 2018

     

STU RAG to end of Dec 2018

 

Resources to end of Dec  2018

          

STU actual spend to end Dec 2018

 

 

Section Two: Projects Not Started

 

All currently approved projects are in progress.

There will be a  follow-on project for  Records Management  in 18-19 to implement the recommendations from STU263, subject to outcome of the options appraisal , and availability of sponsor funding

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

Milestones

30-Jan 2019 Withdrawal

RAG Status

BLUE (Suspended)

Report by Jamie Thin  for December 2018

Achievements this period

  • None - project suspended
    • RIS business area are evaluating other BI Tools and reporting options incl Power BI

Issues

  • No new issues

Next steps

  • agree closure / withdrawl report
  • project expected to be withdrawn by end of Jan 

Milestones

Withdrawal - 30-Jan 2019

STU253 - PGR Opportunity Finder

Category: Discretionary

Milestones

Target Datesort descending Previous Date Title Stage Complete
31-Aug-2017  30-Jun-2017 End of Planning Plan Yes
05-Feb-2018 No date available       Unsuspend project and Kick off the development work Execute No
11-May-2018 23-Mar-2018 End of Planning (re-plan following suspension) Plan Yes
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver Yes
25-Jan-2019 No date available Design Design No
08-Feb-2019 No date available Build Build No
28-Feb-2019 No date available Project Closure Close No

RAG Status

Green

Report by Geoff Cropley for December 2018

Achievements this period

The revised design and proof on concept (POC) using the alternative products has been built. 

To deploy the demonstrator a new front end design and build are required.  Dev Services have been consulted and a revised set of requirements will be submitted in due course.

Issues

  • None

Next steps

  • Provide requirements to support revised front end design
  • Request necessary resources to complete the design and deployment of the POC

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

Currently re-planning -as procurement process has been unexpectedly elongated.  Revised milestones below now require to be approved

Target Date  Title
09-Nov-2018 Contract Award
14-Jan-2019 Complete Application Familiarisation and Setup
08-Feb-2019 Complete User Guides
15-Feb-2019 User Acceptance
18-Feb-2019 Deployment to Live
08-Mar-2019 Deployment Sign-Off
08-Mar-2019 Closure

RAG Status

AMBER

  Report by Andy Stewart for December 2018

 

Achievements

  • Procurement 
    • Discussions held between legal representatives from both UOE and the supplier to resolve contract related discrepancies. 
    • Supplier updated version of the contract received on 18th December 
  • An outline project implementation plan has been prepared on the assumption that the contract will be signed-off mid January 2019 and approved by project sponsor.  However, this has still to be discussed with the supplier 
  • Supplier presented an overview of product road map 

Issues 

  • The period to agree terms and conditions has had to be extended to resolve 
    • the incorporation of UoE tender documentation 
    • payment terms 
    • service level agreement 
  • It has not been possible to review Implementation Plan due the contract not being signed 
  • Requirement to re-plan the project to accommodate the elongated time to complete the procurement process

Next Steps

  • EQIA - to be completed
  • Contract to be signed-off
  • Implementation planned to be agreed

 

RAG Commentary
Contract delays have continued with the supplier updated version received on 18th December. A revised project plan to implement the application will finalised once the contract is signed. This is not impacting on the business at this time

 

STU258 - Careers - Student Alumni Community Networking Platform

Category - Discretionary

Milestones

18-Jun-2018 Launch of website
29-Jun-2018 Delivery sign-off
16-Nov-2018   Project closure

RAG Status

BLUE (Closed)

Report by Richard Bailey for December 2018

Achievements

Issues

  • None

Next steps

  • None

Milestones

16-Nov-2018   Project closure

 

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

Milestones:

01-Feb 2019 End of Planning

RAG Status:

AMBER

 Report by Jamie Thin for December 2018

Achievements this period

  • No progress - waiting for Dev work for STU264 to be completed first

  • The work on the security strengthening package is on hold , pending availability of IS Dev services resources after STU264 has been delivered

Issues

  • Dependency on STU264 - the urgent small enhancements to the UG & PG degree finder should be delivered first via STU264, then the security work can be delivered after STU264 goes LIVE
  • Dependency on SEP SAS PCIM analysis & SRA analysis - the future PCIM / SRA Website solution may not provide a complete end-to-end solution for CAM for all marketing data associated to Programmes.  
    • STU260 should attempt to understand the potential size of any gap , so that Service owner (CAM) can make a bid for additional funding / submit business case to SEP for another future project
    • initial response with answers to STU260 questions received from Emma Rowson (SEP), fuller details will be available from Feb 2019 once initial PCIM analysis complete.

Next Steps

  • Get resources booked  to deliver the  security strengthening dev work for both the UG & PG applications
    • initial estimates are that the work is relatively small , so it is recommended that it is delivered as a work package within STU260 rather then spinning up a separate project to do the security work
    • make bookings with the S/W dev team to start after STU264 has gone live

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING

TOOL 

Category:  Compliance

Milestones

4-June-2018 End of Planning
12-Oct-2018            BRD Document Released for Review
29-Oct-2018 Options Appraisal Signed Off
30-Nov-2018 Analysis of Requirements - Signoff Complete
14-Dec-2018 Options Appraisal Delivered
18-Jan-2019 Project Closed

Rag Status:

 AMBER

Report by Ken Miller for December 2018

Achievements

  • Meeting held with project sponsor to review project and options.
  • SharePoint response received and incorporated into options paper along with G-cloud responses.
  • Final G-Cloud responses received.
  • Initial options appraisal commenced but not yet ready for review.

Issues

  • Initial draft appraisal paper won't be available for review until early January.

Next Steps

  • Initial options appraisal document completed for initial review.
  • Feedback received and incorporated into the final options paper.

 

 

STU264 CAM UG & PG Degree Finders Small Enhancements

Category - Discretionary

Milestones

Peer testing in DEV complete 18-Jan-2019
Deploy to TEST 23-Jan-2019
Apps mgt peer testing in TEST 30-Jan-2019
CAM Complete UAT 22-Feb-2019
Build re-work after Integration test and UAT 14-Mar-2019
Deploy changes to UG Degree finder to LIVE 20-Mar-2019
Deploy changes to PG Degree finder to LIVE 20-Mar-2019
Deployment review sign-off 29-Mar-2019
Project Closure 12-Apr-2019

Rag Status:

GREEN

Report by Chris Konczak for December 2018

Achievements

  • Estimation for the three additional JIRAs complete. This is a change in scope. Three days additional funding agreed with SRA.
  • Development commenced

Issues

  • Progress in December has not been as much as anticipated due to higher priority live issues on COM036, annual leave and issues with the developer's environment / framework setup.
  • Will need additional deployment milestone for JIRA 19 as this is a compliance scope addition required for 11/02/2019

Next Steps

  • Continue with development, particularly JIRA 19, the compliance change required for 11/02/2019.
  • UAT to complete for JIRA 19
  • Review milestones with project team