Report for August 2018

Report Date
August 2018

 

Report compiled by  Morna Findlay (IS Apps Programme Manager)

for Jim McGeorge (USG), Niall Bradley (CAM),  Steven Ross (CAM) , Ailsa Vamplew (CAM) , Sheila Williams (SDS), Jane Johnston (SRA),  Damon Querry (RIS), Sara Cranston (Records Management), Rena Gertz (GaSP), Isabell Majewsky Anderson (Edinburgh Global) and other interested business area owners.

 

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

Overall the STU programme is AMBER  because there are  projects  an risks which are red or amber at this time.

 

STU260 - RED - scope, budget, time unclear - escalated within IS.

 

 

RED and AMBER Programme Risks

 

   

Additional compliance work may affect scheduling and budgets of other projects during 2018-19        AMBER            Jim McGeorge
mobility online may not be decomissioned by Study Away AMBER Jim McGeorge
End of Life of Yii framework may require rewrite of multiple applications AMBER Stefan Kaempf

 

RAG & Forward Look to end of Aug 2018

     

 

Resources to end of Aug  2018

          

   

 

 

Section Two: Projects Not Started

 

All approved  projects within the STU programme are in progress.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

Milestones

RAG Status

BLUE (Suspended)

Milestones

TBC - once project status reviewed in Oct 2018

STU253 - PGR Opportunity Finder

Category: Discretionary

Milestones

Date Previous Date Title Stage Complete
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
31-Oct-2018 No date available Deployment Deliver No
16-Nov-2018 No date available Project Closure Close No
21-Dec-2018 21-Dec-2017 External Milestone: Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available" Deliver No
21-Dec-2018 11-May-2017 External Milestone: Guidance policy for use and tagging of keywords to support PGR search Deliver No

RAG Status

GREEN

Report by Geoff Cropley for August 2018

Achievements this period

Budget for the new academic year has been secured amounting to 20 days.  This is great news and allows the team to continue to develop the minimal viable product (MVP).  Technical issues with Funnelback search engine are ongoing  and have prevented real progress during August.   This was expected as securing time with the vendor had been planned for later in August. 

Following a re-plan, a change request was approved by WIS to amend a number of milestones and the revised deployment date moving to 31st October 2018.

Development Services resource have confirmed that in the event that changes are required to the search widget, these could be accommodated following Funnelback work, during September.

Student Recruitment  are continuing to drive data and standards development and also driving forward with guidance and policies to improve the quality of staff profiles to enhance the supervisor search journey and ultimately the data quality.

Issues

  • None

Next steps

  • Resolve outstanding technical issues with data retrieval from the Funnelback search collection.

 

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

Target Date  Title
26-Oct-2018 Contract Award
07-Dec-2018 Complete Application Familiarisation and Setup
21-Dec-2018 Complete User Guides
21-Dec-2018 User Acceptance
07-Jan-2018 Deployment to Live
25-Jan-2018 Deployment Sign-Off
25-Jan 2018 Closure

RAG Status

GREEN

  Report by Andy Stewart for August 2018

  Achievements in Last Period 

  • Tender Process
    • Four  bids were received in response to the tender
    • All suppliers have passed the mandatory question sets
    • Accessibility review incorporating written responses and application review have been completed
    • The written responses to the Desirable questions have all but been reviewed
    • Supplier demonstrations have been held by all four suppliers
  • The project has been re-planned to incorporate the additional 5 weeks to complete the tender process (meeting scheduled with the project sponsor scheduled for 6th September to review)

  Issues

  • One supplier has supplied two sets of different answers to the Desirable questions - and this has still to be clarified.  The Procurement lead is currently seeking clarification
  • The tender process is taking longer than initially anticipated due to the following
    • Diary congestion delaying the functional and usability review of the four potential suppliers - this was partly due to not knowing how many suppliers would require to be evaluated
    • Requirement to re-plan all the procurement consensus meetings until the functionality and usability review  
  • A delay of around 5 weeks is anticipated to complete the tender evaluation process

Next Steps

  • EQIA - to be completed
  • Determine preferred solution after
    • Completing   tender quality review
    • Completing  tender cost review

The project has been assigned a Change  status of Amber due to the projected 5 week delay in delivering the solution

 

STU258 - Careers - Student Alumni Community Networking Platform

Category - Discretionary

Milestones

18-Jun-2018 Launch of website
29-Jun-2018 Delivery sign-off
31-Aug-2018 Project closure

RAG Status

Green

Report by Richard Bailey for August 2018

Achievements

  • Project Manager reviewed and agreed closure against all remaining milestones other than closure with Business Project Manager on his return from annual leave
  • Closure report drafted, awaiting feedback from Senior Supplier

Issues

  • None

Next steps

  • Look to complete Closure report / Close Project

 

STU260 CAM  Degree Finders - Options Appraisal - PhP End of Life migration path - proof of concept

Milestones: TBC

RAG Status: RED

 Report by Jamie Thin for August 2018

Achievements this period

  • Discussion on scope and funding progressed  and escalated within IS.

Issues

  • No approved scope, budget or milestones.
  • The project is currently without a project manager since the departure from the university of the previous project manager
  • The programme manager  escalated the risk to the programme that this work could not be progressed and has arranged a meeting between the business and IS section heads in September 2018 at which a way forward is to be discussed.

Next Steps

  • Assign new project manager
  • Agree way forward with Business and Section heads in September 2018

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING

TOOL 

Category:  COMPLIANCE 

Milestones

4-Sep-2018              Analysis of Requirements - Signoff Complete
12-Oct-2018 Options Appraisal Signed Off
19-Oct-2018 Options Appraisal Reviewed
29-Oct-2018 Options Appraisal Delivered
12-Nov-2018 Project Closed

Rag Status:

 Amber

Report by Ken Miller for August 2018

Achievements

  • Meeting with business leads held to review requirements.
  • As-is process maps updated after feedback and signed off.

Issues

Next Steps

  • BRD to be updated and released for review and sign off.
  • Assess in-house redevelopment option based on BRD.
  • Review G-Cloud options based on BRD.

 

 

 

Section Four: Closed or Withdrawn Projects

None at this time.

 