Report for July 2018

Report Date
July 2018

DRAFT

 

Report compiled by  Morna Findlay (IS Apps Programme Manager)

for Jim McGeorge (USG), Niall Bradley (CAM),  Steven Ross (CAM) , Ailsa Vamplew (CAM) , Sheila Williams (SDS), Jane Johnston (SRA),  Damon Querry (RIS), Sara Cranston (Records Management), Rena Gertz (GaSP), Isabell Majewsky Anderson (Edinburgh Global) and other interested business area owners.

 

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

Overall the STU Programme is RED   because it is now confirmed that  several projects did  not complete  within 17/18 and several projects are RED or AMBER at this time.

STU252 - BLUE  - suspended

STU260 - RED - scope, budget, time unclear - escalated within IS.

 

 

RED and AMBER Programme Risks

   

Additional compliance work may affect scheduling and budgets of other projects during 2018-19        AMBER            Jim McGeorge
mobility online may not be decomissioned by Study Away AMBER Jim McGeorge
End of Life of Yii framework may require rewrite of multiple applications AMBER Stefan Kaempf

 

RAG & Forward Look July 2018

   

     

 

Resources to end of July 2018

          

 

 

Section Two: Projects Not Started

 

All projects within the STU programme are in progress.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

Milestones

Provisional  milestones updated on Projects website, will need updated and approved after re-plan, once scope change approved

31-Oct 2018 Decision point to re-start or withdraw project
   
   

 

      

RAG Status

BLUE (Suspended)

Report by Jamie Thin for July 2018

Achievements in Last Period

  • Project suspended
  • Business lead has agreed Project should be formally suspended while the RIS team evaluate the use of Power BI against the raw BI Data extract as alternative to the STU252 Star schema and BI Suite Universe
  • Alternative technical solutions to apply org unit permissions to the BI Suite universe reviewed - none are operationally attractive
  • Other project tasks on hold , pending outcome of discussion on scope and priorities
  • Business lead has discusses priorities with the key business users at the operational group

Issues

  • Open - No agreement on Scope change re. Org unit permissions
    • Initial proposal of providing no org unit data restrictions have been rejected by Business lead
    • Workaround explored with IS Service Management of applying row level permissions, but doesn't look like it would work for  IGMM and Roslin, and complex data structures with collaborative projects with multiple budgets for each Org unit

Next Steps 

  • Agree suspension period and criteria for either withdrawing the project or reducing scope and completing the revised scope.
  • Propose review within 3-months time by  end of Oct 2018 - Decision point for Business lead and Project sponsor

Milestones

TBC - once project status reviewed in Oct 2018

STU253 - PGR Opportunity Finder

Category: Discretionary

Milestones

Date Previous Date Title Stage Complete
25-May-2018 No date available System Design - Research PURE API Design Yes
19-Jun-2018 No date available Build Complete Build Yes
03-Jul-2018 No date available Integration Complete Integrate No
18-Jul-2018 No date available Acceptance Complete Accept No
26-Jul-2018 No date available Deployment Deliver No
14-Aug-2018 No date available Project Closure Close No
21-Dec-2018 21-Dec-2017 External Milestone: Guidance policy for use of "Willingness to take Ph.D. students" and "Ph.D. research projects available" Deliver No
21-Dec-2018 11-May-2017 External Milestone: Guidance policy for use and tagging of keywords to support PGR search Deliver No

RAG Status

RED

Report by Geoff Cropley for July 2018

Achievements this period

Good progress was achieved in terms of the technical deliverables of  the the project.  The search widget was designed and built and is capable of being incorporated onto any of the universities web pages.  This proof concept (POC)  is capable of being further developed and implemented as a minimum viable product (MVP) when the underlying data is of suitable quality. 

There are technical issues with getting the right data in the right format from the Funnelback collection.   Rectifying this problem will delay the the delivery of the application and the impact of this means that it will not be possible to deliver the project to the agreed plan.  The Funnelback issues are being supported by the vendor.  At the same time,  the data quality of staff profiles held within Pure are inconsistent and some of the key data is missing.  This means that data being delivered to the search results page is not at the level that could enable the application to be deployed in production.  Both these issues prevent the search application from going live at this time.  Risks and issues are raised to cover these problems.

Notwithstanding this, development work is ongoing with Funnelback by the LTW team and Student Recruitment  are continuing to drive data and standards development beyond the end of the project as both of theae areas are of strategic interest to the teams.   Aditionally, further funding is being sought b Student Recruitment, through a number of channels, to complete any remaining search result page development.

Student Recruitment are also driving forward with standards guidance and policies to improve the quality of staff profiles to enhance the supervisor search journey and ultimately the data quality.  

Issues

  • None

Next steps

As this is a core funded project it is not possible to move funding into the new academic year the project will be closed.

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

Target DateFor security reasons, images aren't duplicated during cloning. Please re-add or replace the image as required. Title
21-Sep-2018 Contract Award
02-Nov-2018 Complete Application Familiarisation and Setup
16-Nov-2018 Complete User Guides
23-Nov-2018 User Acceptance
26-Nov-2018 Deployment to Live
14-Dec-2018 Deployment Sign-Off
14-Dec-2018 Closure

RAG Status

GREEN

  Report by Andy Stewart for July 2018

  Achievements in Last Period 

  • Procurement Activity
    • DPIA presentation produced by the project sponsor and the Accessibility officer for the Bidders Conference.   However, having arranged for the Bidders conference to be held on 11th July, no interest was shown by any of the potential suppliers in the Bidders conference
    • The ITT process closed on 20th July resulting in 4 tenders being submitted
  • Tender Review Process
    • Review of mandatory questions commenced
    • review of accessibility questions  commenced

  Issues

  • Noted that the Desirable Questions had been duplicated in the mandatory Qualifications envelope.  Subsequently removed by Procurement
  • Requirement to clarify submission details with 3 of the 4 bids

Next Steps

  • EQIA - to be completed
  • Continue tender reviews

 

STU258 - Careers - Student Alumni Community Networking Platform

Category - Discretionary

Milestones

18-Jun-2018 Launch of website
29-Jun-2018 Delivery sign-off
31-Aug-2018 Project closure

RAG Status

Green

Report by Richard Bailey for July 2018

Achievements

  • Project closure milestones have had to be reset as a result of the Business Project Manager being on annual leave and the IS Project Manager leaving the University
  • A new IS Project Manager is in place for closure activities and is coming up to speed 
  • Draft closure report written

Issues

  • None

Next steps

  • Achieve sign off against both delivery and closure milestones.  Note it is believed that the delivery milestones were achieved and that they were not signed off.  Project Manager to review with Business Project Manager as soon as they are available.
  • Complete Closure report / Close Project

 

STU260 CAM  Degree Finders - Options Appraisal - PhP End of Life migration path - proof of concept

Milestones: TBC

RAG Status: RED

Achievements this period

  • Discussion on scope and funding progressed  and escalated within IS.

Issues

  • No approved scope, budget or milestones.
  • The project is currently without a project manager since the departure from the university of the previous project manager
  • The programme manager  escalated the risk to the programme that this work could not be progressed and has arranged a meeting between the business and IS section heads in September 2018 at which a way forward is to be discussed.

Next Steps

  • Assign new project manager
  • Agree way forward with Business and Section heads in September 2018

STU262 Electronic Sharing of Responses for GDPR

Category:  COMPLIANCE 

Rag Status:

 BLUE

Report for July by Morna Findlay

Achievements This Period

  • Deployment sign-off milestone  approved
  • Service handed over to support
  • Closure report circulated and signed off
  • Project closed

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING

TOOL 

Category:  COMPLIANCE 

Milestones

4-Sep-2018              Analysis of Requirements - Signoff Complete
12-Oct-2018 Options Appraisal Signed Off
19-Oct-2018 Options Appraisal Reviewed
29-Oct-2018 Options Appraisal Delivered
12-Nov-2018 Project Closed

Rag Status:

 Amber

Report for July 2018 by Morna Findlay

Achievements

  • As-is process maps drafted and sent to business for review
  • New delivery and closure milestones approved

Issues

Next Steps

  • Business leads invited to meetings to review requirements
  • Sign-off of as-is process maps
  • Conduct gap analysis and gap analysis workshop
  • Conduct data mapping exercise

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

STU256

CAM Degree Finders - Compliance with Legislation & Guidance

Closed 01/06/2018

Closure Report

Closure Milestone

STU259

FREEDOM OF INFORMATION GDPR UPDATES

 

 

Closed 12/6/18

Closure report

Closure milestone

STU262

Electronic Sharing of Responses for GDPR

 

Closed 20/7/18

Closure Report

Closure Milestone

STU261

SRA- Feree WiFi at Open Days

 

Withdrawn 3/8/18

PICCL

 