Report for May 2018
- Report Date
- May 2018
Report compiled by Morna Findlay (IS Apps Programme Manager)
for Jim McGeorge (USG), Niall Bradley (CAM), Steven Ross (CAM) , Ailsa Vamplew (CAM) , Sheila Williams (SDS), Jane Johnston (SRA), Damon Querry (RIS), Sara Cranston (Records Management), Rena Gertz (GaSP), Isabell Majewsky Anderson (Edinburgh Global) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
Overall the STU Programme is RED because it is now confirmed that several projects will not complete within 17/18. . Several projects are RED or AMBER at this time.
STU252 - RED - need to agree change of scope and investigate workaround with IS Service Management
STU253 - AMBER - risk that the work cannot be completed in 17/18 hence AMBER.
STU257 - RED - change to milestones due to change in procurement approach. To complete in 18/19
STU258 - AMBER - milestones to be revised after consultations with vendor
STU260 - AMBER - milestones likely to change during planning process
STU262- RED - Delivery milestone delayed as testing not yet completed
STU263 - GREEN - Likely to complete in 18/19
It was hoped that the proposed project to provide free WIFI for Open Days would be superseded by a new JISC service. IS is now participating in the JISC pilot but finding this unsuitable, was unable to find an alternative solution in time to provide free WIFI for the June Open Day and that the 10 days earmarked as funding may not be sufficient to supply an alternative service. The portfolio manager has escalated within IS in order to find a way forward.
RED and AMBER Programme Risks
RAG & Forward Look May 2018
Resources to end of May 2018
The resources table below below 65d has been nominally allocated to STU263, (50 d in 17/18) and the budget overall for 17/18 is is 691d.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
SRA - Free WiFi at University Open DaysDiscretionary Planning: TBC Delivery:TBC RAG StatusRED |
PlanThis project is to undertake the work noted in this proposal. The proposal estimated 10d of work, but it is now clear that this budget is insufficient enough to deliver a standalone solution for open wifi during open days, ITI planned to deliver open wifi using the JISC pilot service but this has not been achieved. Alternative solutions have been estimated to be of significant cost and there is no identified source of funding to deliver these, hence the project's status as RED. The issue has been escalated to senior management. DependenciesSolution not identified. Funding not identified. Status of and cost of JISC-solution unclear. |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary |
||||||||||||||||||||||||||||||||||||||||||||||||||
STU252 - Worktribe BI Suite Universe - Research Management BI MI EnhancementsCategory: DiscretionaryMilestonesProvisional milestones updated on Projects website, will need updated and approved after re-plan, once scope change approved RAG StatusRED |
Report by Jamie Thin for May 2018Achievements in Last Period
Issues
Next Steps
RAG CommentaryRED -Issue - Scope change not agreed with business - can't deliver the full scope in current capped budget , must either cut scope or suspend project until budget issue resolved |
||||||||||||||||||||||||||||||||||||||||||||||||||
STU253 - PGR Opportunity FinderCategory: DiscretionaryMilestones
RAG StatusAMBER |
Report by Geoff Cropley for May 2018Achievements this period
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU256 - CAM Degree Finders - Compliance with Legislation & GuidanceCategory: ComplianceMilestonesNow Closed RAG StatusBLUE |
Report by Chris Konczak for May 2018Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU257 Privacy Impact Assessment ToolCategory: ComplianceMilestones
RAG StatusRED |
Report by Andy Stewart for April 2018Achievements in Last Period
Issues
Next Steps
RAG CommentaryChange : Project delivery date extended by 6 weeks as a result of changing to a full OJEU procurement |
||||||||||||||||||||||||||||||||||||||||||||||||||
STU258 - Careers - Student Alumni Community Networking PlatformCategory - DiscretionaryMilestones
RAG StatusAMBERIssue: The current milestones need to be revised in light of the changes to delivery that need to be made after consultation with the vendor. |
Report by David Watters for May 2018Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU259 FREEDOM OF INFORMATION GDPR UPDATESCategory: COMPLIANCEMilestones
Rag StatusGREEN |
Report by Megan Graham for May 2018Achievements This Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU260 CAM Degree Finders - Options Appraisal - PhP End of Life migration path - proof of conceptEnd of planning to be proposed to 29th June. RAG Status Amber |
Report by Jamie Thin for May 2018Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU262 Electronic Sharing of Responses for GDPRCategory: COMPLIANCEMILESTONES
Rag Status:AMBER |
Report for May 2018 by Megan Graham and Morna FindlayAchievements This Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||||||||||||
STU263 - REPLACE INFORMATION REQUEST PLANNING MONITOR TOOL - PROCUREMENTCategory: COMPLIANCEMilestones
Rag Status:Green |
Report for May 2018 by Alison KellasAchievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
STU256 |
Closed 01/06/2018 |