Report for February 2013

Report Date
February 2013

 

Report compiled by Jamie Thin (IS Apps Programme Manager) for Jim McGeorge (SASG), Shelagh Green (Careers), Steve Norman (Careers), John Cavani (C&M) , Ronnie Millar (Counselling) , Richard Bizley (ELTC), Con Gillen (OLL) , Sheila Williams (Student Disability Service), Scott Rosie (Timetabling unit in the Academic Registry) , Susan Graham (Records Management) (and other business area owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

***

 

Section One: Programme Commentary, RAG and Resources Update

 

The Student services programme has 8 projects in progress (some of these with  multiple work packages / phases).

The  STU programme  budget for 2012-13 was  set at 1460 days at the mid-year review

 

 

 

Current STU out-turn for 2012-13 is estimated as 1680 days  ( of which 1005 days (delivered) and 675 (estimate to complete this year))

 

 

 Section Two: Projects Not Started

 

 

Project InfoProgramme Manager's Commentary

AP23-041

Replace OLLIE and CUPID

 

Funded 

Planning Month Year Apr 2013

Delivery Month Year  tbc ( in  2015)

RAG Status

GREEN

Plan

This is the vehicle to deliver replacements for OLLIE and CUPID, an initial 93 days have  been assigned to STU229 for the options appraisal and IS Apps work associated with enabling OLL credit students to be keyed into EUCLID.

The shape of this future work is dependant on the outcome of the STU229 Options Appraisal,  the requirements for OLLIE and CUPID could be dealt with separately and met via a procurement for a 3rd party system or via inhouse development or modification to existing systems. This project will need to deliver future procurements and implementations as required - this activity is likely to be spread over 2 years.

Subject to the outcome of the options appraisal, the 2013-14 annual planning round and available funding from the project sponsor, the future profile of effort has been re-estimated as a multi-year project with place-holders for the potential spend over the next 3 years:

94 days in remainder of 12-13,

then 400 days in 13-14 and 300 days in 14-15

(these estimates are just to aid resource planning in 2013-14 , and will be updated as a result of the decision from the options appraisal)

 

Dependencies

STU229 OLLIE and CUPID Options appraisal

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

STU224

 

Category: C

Milestones

TBC

 

 

 

 

 

 

 

RAG Status

 

 

AMBER

Achievements in this period

A new Project Sponsor has been appointed. The Project Manager, Programme Manager, Project Manager and the University Records Manager met. The meeting  reviewed what progress had been made to date  and discussed  how this project should make progress. It was agreed that if possible, the project should review the testing carried out in October, carry out BOXI testing and proceed to a live deployment before the end of March, The Project Sponsor will investigate whether this preferred  timescale is feasible and agree milestones with the Sponsor

Outstanding Issues
  1. The BOXI reports were not tested before the departure of the previous project sponsor.
  2. Project milestones have not yet been agreed.
Next Steps
  1. Agree new project milestones with project sponsor
  2. Project manager to secure IS Applications resources 
  3. Project sponsor to carry out limited re-testing on TEST
  4. Project Sponsor to carry our tests of BOXI reports on TEST
  5. Live deployment date to be agreed (Records management cannot agree to a date more than three weeks in advance)

The project RAG status has been set to AMBER as the project manager has not yet set new Milestones but anticipates that this will be done shortly.

STU226  

Timetabling Extended Implementation

 

Category: Funded

Milestones

 

Target date

Title

15-Mar-2013

Student Allocator (1) Design Sign-off

26-Mar-2013

Student Allocator (2) Build Sign-off

29-Mar-2013

MyEd Integration - Build Signed Off

15-Apr-2013

Student Allocator (3) Integration Sign-off

26-Apr-2013

Calendar Services Build (for Office365 integration) - Signed Off

29-May-2013

Student Allocator (4) Acceptance Sign off review (ASOR)

31-May-2013

LEARN VLE - 1-way outgoing feed of Group data - Build

17-Jun-2013

Student Allocator (5) Deployment (go Live)

27-Sep-2013

Student Allocator (6) Deployment Sign off Review (DSOR)

25-Oct-2013

Closure

 

 

 

 

 

RAG Status

 

RED

 

Project is at RED  until project board reviews priorities

Report by Jamie Thin for Feb 2013

This project has multiple work packages.

Student Allocator is in build stage, the other work packages are at analysis / design stage.

STU226 will deliver the critical elements required to enable personalised timetables to be available for Students for the Start of Semester 1 2013, including the Scientia Student Allocator module and integration to MyEd.

3 work packages have been split-out of STU226 to provide clarity to milestones :

These are:

STU226 - WP1 Timetabling : MyEd Personalised Web Timetables (budget 20 days)

STU226 - WP2 Timetabling : Feed to Learn VLE (budget 80 days)

STU226 - WP3 Timetabling : XML Data Feed for Schools ( budget 30 days)

The overall budget for STU226 (incl. these work packages above) is now set to 445 days

Estimates for this future work will be refined as analysis and design work progresses.

This increase in estimate is not yet agreed / approved.

The scope may need to trimmed to fit available resources in 12-13.

 

Achievements in Last Period

Student Allocator

  • Additional demo / training to Timetabling Unit
  • Web interface design prepared
  • Schools comms plan prepared.

MyEd Integration

  • Estimates to feed into options appraisal Issues
  • How to manage roll-out of SAM client application to School users.
  • Large comms effort will be required to explain the impact of Student Allocator on local school business processes.
  • Project is at RED  until project board reviews priorities
Next Steps  

Student Allocator

  • First meeting of the Student Allocator Implementation Group (13-March)
  • Document business requirements and UAT approach
  • Deploy into test.
  • Prepare training materials and training session content.

 

MyEd Integration

  • Complete options appraisal - SWS / iCal / Office365

STU227 

TED Scientia Enterprise Upgrade to v3.2 

 

Category: Funded

Milestones

 

Mar 2013Reporting M7 : Closure

RAG Status

GREEN

Report by Alex Wood for Feb 2013

 

Achievements in Last Period

 

Reporting

Completed and deployed to LIVE

Issues

none

Next Steps

Project Closure

 

STU228 

Timetabling Interfaces- Extended

 

Category: Funded

Milestones

 

Target dateTitle
21-Nov-2012

Incoming Interfaces from EUCLID - Business Analysis Review

- Complete

12-Dec-2012Incoming Interfaces from EUCLID - Design Review - Complete
10-Jan-2013Build Review Phase 2a - Complete
11-Jan-2013Roll Forward Requirements Sign off Review - Complete
31-Jan-2013Design Sign Off Phase 2b - Complete
22-Feb-2013CCAM - Acceptance Test Sign Off
22-Feb-2013Roll Forward - Process Overview Review - Complete
26-Feb-2013Phase 2b Build Review
04-Mar-2013Build Review Roll Forward Web Apps - Complete
08-Mar-2013Roll Forward Web Apps - Acceptance Test Sign Off
08-Mar-2013Syncronisation - Build Review
11-Mar-2013Roll Forward Web Apps - Go Live
18-Mar-2013Roll Forward Web Apps - Deployment Sign Off Review
19-Mar-2013VS and DRPS - Design Review
19-Mar-2013EUCLID Core - Design Sign Off
01-Apr-2013VS and DPRS - Build Review
01-Apr-2013CCAM - Deploy to Live
01-Apr-2013EUCLID Core - Build Review
01-Apr-2013Phase 2a - Go Live
08-Apr-2013CCAM - Deployment Sign Off Review
 

 

22-Apr-2013VS and DRPS - Acceptance Test Sign Off
29-Apr-2013VS and DRPS - Go Live
13-May-2013VS and DRPS - Deployment Sign Off Review
16-May-2013Syncronisation - Acceptance Test Sign Off
16-May-2013Phase 2b - Acceptance Sign Off Review
20-May-2013EUCLID Core - Acceptance Test Sign Off
30-May-2013Syncronisation - Go Live
30-May-2013Phase 2b - Deploy to Live
03-Jun-2013EUCLID Core - Go Live
07-Jun-2013Phase 2b - Deployment Sign Off Review
07-Jun-2013Syncronisation - Deployment Sign Off Review
19-Jun-2013EUCLID Core - Deployment Sign Off Review
26-Aug-2013Switchover - Go Live
02-Sep-2013Switchover - Deployment Review
16-Sep-2013Project Closure

RAG Status

 

RED

Project is at RED  until project budget has been agreed

Report by Craig Middlemass for Febraury 2013

Achievements in Last Period

  • Rollforward of the SDB was completed in Dev, Test and Deployed to live in advance of the go live (4 March 2012)
  • Rollforward of the Web Applications was completed in Dev
  • Design agreed for Roll Forward overview (including the new phases to complete Syncronisation work)
  • Build completed for Phase 2a
  • Build started for Phase 2b and Syncronisation

Issues

  • Project reported as red given budget has not been approved.
  • Ilness in the configuration team has lead to delays in completing the first part of the EUCLID CCAM build and testing
  • Lots of unplanned work has surfaced in light of needing to reprioritise elements of the project
  • Conflicts with other timetabling projects for key Dev Technology resources
  • Issue with Kx linking to 2 timetablings SDBs raised, potential impact on ability to start Kx link with 2012/13 data

Next Steps

  • Replan CCAM/EUCLID changes based on available resource and prioritisation with SACS
  • Replan future phases now that timeline for go lives have been established
  • Deploy Rollforward Web Applications (11 March)
  • Test Kx link remaining issues
  • Increased budget to be agreed with WIS

 

STU229

Replace OLLIE & CUPID - options Appraisal

Category: Funded

Milestones

 

 

RAG Status

AMBER

Report by Maurice Franceschi for Feb 2013

Achievements in Last Period

Phase 1b - Requirements sign-off

Phase 2

A draft document outlining the options has been prepared, to be reviewed and discussed by Apps and SACS.

The aim is to make a recommendation to OLL by w/c 11th Feb, so we can come to a final decision that week, by senior OLL management and IS amnagement.

 

Issues

Cost of options are all high, and resourcing of them in a single year unlikely.

Next Steps

 

Phase 1b -  start of build

Phase 2 Meeting with IS and SACS colleagues Present recommendation to OLL Decide

Milestones

 

Phase 1b - Acceptance sign-off and deploy to LIVE - March-2013 (after SITS upgrade)

Phase 2                 Decision w/c 21-March 2013

List of Tasks

Options Appraisal Phase of the project may overrun its budget by 3-4 days.

STU230

Bookable Rooms Replacement Website

Category: Funded

Milestones

 

 

 

RAG Status

GREEN

Report by Alex Wood for Feb 2013

Achievements in Last Period
  • Project brief documented
  • Business requirements understood
  • Approach to providing XML feed confirmed
  • Meetings held with Service Management and resource identified
  • Proposal document outlining scope of works completed.
Issues
  • N/A
Next Steps  
  • Estimates to be provided by Service Management
  • Estimates, Milestones and Project Brief to be signed off
  • XML Presentation Layer to be installed

SSG002

Student Marketing Services Infrastructure Migration

Category: Compliance

Milestones

04-Mar-2013UAT Sign-off of A-Z and Maps
07-Mar-2013PPBR of PG Port and PG Admin
15-Mar-2013UAT Sign-off of UG Port and Admin
22-Mar-2013UAT Sign-off of PG Port and Admin
10-Apr-2013ASOR of Maps and A-Z Port and Admin
10-Apr-2013ASOR of UG Port and UG Admin
10-Apr-2013ASOR of PG Port and PG Admin
18-Apr-2013Delivery of Maps and A-Z Port and Admin
18-Apr-2013Delivery of PG Port and PG Admin

 

RAG Status

AMBER

Report by Maurice Franceschi  for Feb 2013

Achievements in Last Period

A-Z and Maps UAT begun and expected to complete by 8th March.

UG Prospectus UAT started 5th March.

PG Prospectus Analysis and Design signed-off. Build expected to complete 8th March.

Project re-planned to complete all UAT before Load Testing and DR.

Issues The additional applications on Praline have been identified and will be dealt with by Support, probably as a small -scale project. The project is project to be over budget by 34 days. However, this includes effort that is part of SSG003 Enhancements so this correction wil be made once the effort is confirmed.  

Next Steps Complete UG UAT by time of next report. Complete PG UAT by time of next report. Complete Load Testing by time of next report.

 

 

 

SSG003

Student Marketing Services Enhancements (CAM)

Category: Funded

Milestones

18-Mar-2013

Business Requirements (BRD) for UG Prospectus Enhancements

- PPAR

22-Mar-2013SDS for UG Prospectus Enhancements (PPDR)
05-Apr-2013Build of UG Prospectus Enhancements (PPBR)
08-Apr-2013

Business Requirements (BRD) for PG Prospectus Enhancements

- PPAR

12-Apr-2013SDS for PG Prospectus Enhancements (PPDR)
23-Apr-2013User Acceptance of UG prospects Enhrancements (ASOR)
25-Apr-2013Delivery of UG Prospectus Enhancements - Back End
03-May-2013Build of PG Prospectus Enhancements (PPBR)
17-May-2013User Acceptance of PG prospects Enhrancements (ASOR)
22-May-2013Delivery of PG Prospectus Enhancements
29-May-2013Delivery of UG Prospectus Enhancements - Front End

 

RAG Status

GREEN

Report by Maurice Franceschi  for February 2013

Achievements in Last Period Project Brief approved. Planning and Milestones set.

Issues Some of the SSG003 build has already been done by SSG002, as it made sense to do it with the other changes. So this effort is still to be reflected in project costs. Next Steps Complete UG Enhanecments Analysis and Design by time of next report. Get an early draft of PG Enhancements so we can be confident that the project budget is sufficient to do all the work.

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

AP23-040

OLL HESA 12/13

 

Category: Funded

 

This project was withdrawn on 03-Aug-2012.

For 12-13 , OLL will key OLL credit students into EUCLID , so there is no future requirement to do a separate OLL HESA return

STU204

Coldfusion Upgrade - Careers

Category: Core

Closed

STU204 Completion report

AP12-038 STU223 

OLL HESA 11-12 

 

Category: Funded

Completion report completed and STU223 project has been Closed on 10/10/2012

STU220 

ELTC Implement Class.net

 

Category: Funded

Closed

STU222

CAM UG/PG Prospectus

Category : Funded

 

Completion Report completed and STU222 project has been closed.

The STU222 Completion Report

 

STU215  

Shared Academic Timetabling Phase 2- Implementation Minimum Change Year 1

Category : Funded

Closed

STU215 Completion report