Report for Jan 2013

Report Date
January 2013

 

 

Report compiled by Jamie Thin (IS Apps Programme Manager) for Jim McGeorge (SASG), Shelagh Green (Careers), Steve Norman (Careers), John Cavani (C&M) , Ronnie Millar (Counselling) , Richard Bizley (ELTC), Con Gillen (OLL) , Sheila Williams (Student Disability Service), Scott Rosie (Timetabling unit in the Academic Registry) , Susan Graham (Records Management) (and other business area owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

The Student services programme has 9 projects in progress (some of these with  multiple work packages / phases).

The  STU programme  budget for 2012-13 was 1486 days (this is now under review as part of the mid-year review and expected to be set at 1460 days)

 

 

 

Current STU out-turn for 2012-13 is estimated as 1561 days  ( of whic 795 days (delivered) and 766 (estimate to complete this year))

 

 

 Section Two: Projects Not Started

 

 

Project InfoProgramme Manager's Commentary

AP23-041

Replace OLLIE and CUPID

 

Funded 

Planning Month Year Jan 2013

Delivery Month Year  tbc ( in  2015)

RAG Status

GREEN

Plan

This is the vehicle to deliver replacements for OLLIE and CUPID, an initial 75 days have  been assigned to STU229 for the options appraisal and IS Apps work associated with enabling OLL credit students to be keyed into EUCLID.

The shape of this future work is dependant on the outcome of the STU229 Options Appraisal,  the requirements for OLLIE and CUPID could be dealt with separately and met via a procurement for a 3rd party system or via inhouse development or modification to existing systems. This project will need to deliver future procurements and implementations as required - this activity is likely to be spread over 2 years.

Subject to the outcome of the options appraisal, the 2013-14 annual planning round and available funding from the project sponsor, the future profile of effort has been re-estimated as a multi-year project with place-holders for the potential spend over the next 3 years:

100 days in remainder of 12-13,

then 400 days in 13-14 and 300 days in 14-15

(these estimates are just to aid resource planning in 2013-14 , and will be updated as a result of the decision from the options appraisal)

 

Dependencies

STU229 OLLIE and CUPID Options appraisal

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

STU220 

ELTC Implement Class.net

 

Category: Funded

Milestones

 

Feb-2013Closure

 

RAG Status

GREEN

Report by Donna Cruickshank for Jan 2013

Achievements in Last Period

ELTC have moved to the Live VM and are now using the Live service.

Issues

 None

Next Steps

Project closure

 

 

STU224

 

Category: C

Milestones

TBC

 

 

 

 

 

 

 

RAG Status

 

 

RED

 

Report by Morna FIndlay for Jan 2013

Achievements in this period

 

The project sponsor, who is now on maternity leave, was not able to complete the required user acceptance testing and so this project has made no progress.

 

 

Outstanding Issues

Awaiting results of BOXI testing from sponsor.

 

The is now no project sponsor assigned to this project.

 

Next Steps

 

The Programme manager has asked Records management to assign a new project sponsor, who will be able to esnure UAT is completed.

 

The project manager cannot assign any new milestones in the absence of a project sponsor.

 

STU226  

Timetabling Extended Implementation

 

Category: Funded

Milestones

 

These rough milestones are provisional awaiting analysis and input from the technical teams

Target dateTitle
  
29-Mar-2013Build
24-May-2013Acceptance Sign off review (ASOR)
28-Jun-2013Deployment
27-Sep-2013Deployment Sign off Review (DSOR)
25-Oct-2013Closure

 

 

 

 

 

 

 

 

RAG Status

AMBER

Report by Jamie Thin for Jan 2013

This project has multiple work packages.

Student Allocator is in build stage, the other work packages are at analysis / design stage.

STU226 will deliver the critical elements required to enable personalised timetables to be available for Students for the Start of Semester 1 2013, including the Scientia Student Allocator module and integration to MyEd.

3 work packages have been split-out of STU226 to provide clarity to milestones :

These are:

STU226 - WP1 Timetabling : MyEd Personalised Web Timetables (budget 20 days)

STU226 - WP2 Timetabling : Feed to Learn VLE (budget 80 days)

STU226 - WP3 Timetabling : XML Data Feed for Schools ( budget 30 days)

The overall budget for STU226 (incl. these work packages above) is now provisionally set to 420 days (was 235 days)

Estimates for this future work will be refined as analysis and design work progresses.

This increase in estimate is not yet agreed / approved.

The scope may need to trimmed to fit available resources in 12-13.

 

Achievements in Last Period

Student Allocator

  • Deployed into development environment
  • Web interface design prepared
  • Test and Live virtual machines specified and ordered
  • Schools comms plan prepared.

MyEd Integration

  • Initial investigation of MyEd calendar plug-in startedIssues
  • Purchase of additional licence for the Scientia iCal Calendar Service, needs sign-off within IS, to check alignment to other calendar integration initiatives

  • How to manage roll-out of SAM client application to School users.
  • Large comms effort will be required to explain the impact of Student Allocator on local school business processes.
  • Project remains at AMBER until tasks are re-estimated.
Next Steps  

Student Allocator

  • Execute comms engagement plan starting with Business User Group on 12/02/2013
  • Document business requirements and UAT approach
  • Deploy into test.
  • Prepare training materials and training session content.

 

MyEd Integration

  • Complete options appraisal - iCal feed or SWS
  • Confirm purchase order of Scientia iCal Calendar Service with Scientia (and book consultancy for initial install)

STU227 

TED Scientia Enterprise Upgrade to v3.2 

 

Category: Funded

Milestones

 

Feb 2013Reporting M5 : Go-Live
22-Feb 2013Reporting M6 : Deployment Sign-Off Review (DSOR)
27-Feb 2013Reporting M7 : Closure

RAG Status

GREEN

Report by Donna Cruickshank for Jan 2013

 

Achievements in Last Period

3.2 Upgrade

Completed

 

Reporting

Completed - awaiting final sign-off from the Timetabling Unit to enable reports to be deployed to LIVE and project to be closed

Issues

none

Next Steps

Project Closure

 

STU228 

Timetabling Interfaces- Extended

 

Category: Funded

Milestones

 

Target dateTitle
21-Nov-2012Incoming Interfaces from EUCLID - Business Analysis Review - Complete
12-Dec-2012Incoming Interfaces from EUCLID - Design Review - Complete
10-Jan-2013Build Review Phase 2a - Complete
11-Jan-2013Roll Forward Requirements Sign off Review - Complete
18-Jan-2013Design Sign Off Roll Forward
31-Jan-2013Design Sign Off Phase 2b - Complete
06-Feb-2013Build Review Phase 2b
06-Feb-2013Build Review Roll Forward

RAG Status

AMBER

Report by Craig Middlemass for January 2013

Achievements in Last Period

  • Design reviews for Phase 2a and 2b complete
  • Build for Phase 2a complete
  • Testing for Kx link in Dev complete
  • High Level design agreed for roll forward agreed
  • Estimates complete for remaining build
  • CCAM Changes phase 1 build complete ready for test

Issues

  • Illness in the team has held up some of the development work but revised approach to account for time has been agreed
  • Time constraints have forced phasing of roll forward developement (however this is more in line with when the development are required)

Next Steps

  • Organise MVM room booking investigation (de-prioritised below roll forward requirements)
  • Deploy phase 2a to Test
  • Deploy Kx link to Test
  • Completed Build for Phase 2b
  • Complete Design and Build for Roll Forward
  • Test CCAM phase 1 build
  • Progress CCAM phase 2 requirements and build
  • Increased budget to be agreed with WIS

 

STU229

Replace OLLIE & CUPID - options Appraisal

Category: Funded

Milestones

 

 

RAG Status

AMBER

Report by Maurice Franceschi for January 2013

Achievements in Last Period

Phase 1b - Requirements sign-off

Phase 2

A draft document outlining the options has been prepared, to be reviewed and discussed by Apps and SACS.

The aim is to make a recommendation to OLL by w/c 11th Feb, so we can come to a final decision that week, by senior OLL management and IS amnagement.

 

Issues

Cost of options are all high, and resourcing of them in a single year unlikely.

Next Steps

 

Phase 1b -  start of build

Phase 2 Meeting with IS and SACS colleagues Present recommendation to OLL Decide

Milestones

 

Phase 1b - Acceptance sign-off and deploy to LIVE - March-2013 (after SITS upgrade)

Phase 2 Recommendation 11th February

                Decision w/c 18th February

List of Tasks

Options Appraisal Phase of the project may overrun its budget by 3-4 days.

STU230

Bookable Rooms Replacement Website

Category: Funded

Milestones

 

 

 

RAG Status

GREEN

Report by Alex Wood for January 2013

Achievements in Last Period
  • Project brief documented
  • Business requirements understood
  • Approach to providing XML feed confirmed
  • Meetings held with Service Management and resource identified
  • Proposal document outlining scope of works completed.
Issues
  • N/A
Next Steps  
  • Estimates to be provided by Service Management
  • Estimates, Milestones and Project Brief to be signed off
  • XML Presentation Layer to be installed

SSG002

Student Marketing Services Infrastructure Migration

Category: Compliance

Milestones

14-Feb-2013     PPBR of UG Port and UG Admin      08-Mar-2013     ASOR of UG Port and UG Admin      12-Mar-2013     Delivery of UG Port and UG Admin      01-Mar-2013     PPBR of PG Port and PG Admin      26-Mar-2013     ASOR of PG Port and PG Admin      30-Mar-2013     Delivery of PG Port and UG Admin      13-Feb-2013     PPBR of MAPs and A-Z Port and Admin      26-Feb-2013     ASOR of Maps and A-Z Port and Admin      28-Feb-2013     Delivery of Maps and A-Z Port and Admin    

RAG Status

Green

Report by Maurice Franceschi  for January 2013

Achievements in Last Period

Due to issues with server Praline, the project priority and urgency have increased, so we may decomiision the server asap.

This, and the availability of two additional developers, has seen a significant replanning of the project, and much effort by CAM and Apps, in bringing milestones forward by a few months so we can deliver the port and admin modules by  end of March.

The BRD and SDS for UG Prospectus have been approved and build is scheduled to be ready for review and sign-off by 8th February.

The BRD and SDS for A-Z and Maps have been approved and build is scheduled to be ready for review and sign-off by 8th February.

Issues Senior Supplier has different priorities to business, but the new planning has resolved this.

One or more systems on Praline (owned by SRA it is believed) with dependancies on the PG or UG system/database have been identified. Accordingly, the project team is to meet SRA and come to an assessment of the need and estimate to port these SRA systems off Praline. This will be additional scope and additional effort to be funded. This has to be agreed with the business and senior supplier again taking a different view.

Next Steps Move onto UAT for UG Prospectus and complete by time of next report. Move onto UAT for A-Z and Maps and complete by time of next report. Complete BRD and SDS for PG Prospectus by time of next report. Assessment and planning for SRA systems.

 

 

 

SSG003

Student Marketing Services Enhancements (CAM)

Category: Funded

Milestones

Target dateTitleStageComplete    

TBCProject BrefPlanNoeditview

No further milestones has been set

RAG Status

RED

Report by Maurice Franceschi  for January 2013

Achievements in Last Period

A project brief was presented to WIS in December but rejected. Senior Supplier to communicate why.

Project Manager waiting on Senior Supplier to arrange meeting to discuss as instructed by WIS.

 

Issues Status set to RED as although the scope has been agreed by Project Manager and Business, this is not agreed by WIS.

Planning is in place for SSG003 based on the heavily revised timetable for SSG002, so hopefully if project brief can be approved then we can proceed. Some analysis is going on in any case, and a BRD is scheduled for early March.

Next Steps request Senior Supplier to arrange meeting so we can get project progressed Milestones TBC due to new resourcing for SSG002, need to re-assess PG delivery. UG has a target date for early April delivery.

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

AP23-040

OLL HESA 12/13

 

Category: Funded

 

This project was withdrawn on 03-Aug-2012.

For 12-13 , OLL will key OLL credit students into EUCLID , so there is no future requirement to do a separate OLL HESA return

STU204

Coldfusion Upgrade - Careers

Category: Core

Closed

STU204 Completion report

AP12-038 STU223 

OLL HESA 11-12 

 

Category: Funded

Completion report completed and STU223 project has been Closed on 10/10/2012

STU222

CAM UG/PG Prospectus

Category : Funded

 

Completion Report completed and STU222 project has been closed.

The STU222 Completion Report

 

STU215  

Shared Academic Timetabling Phase 2- Implementation Minimum Change Year 1

Category : Funded

Closed

STU215 Completion report