Report for November 2012

Report Date
November 2012

 

Report compiled by Jamie Thin (IS Apps Programme Manager) for Jim McGeorge (SASG), Shelagh Green (Careers), Steve Norman (Careers), John Cavani (C&M) , Ronnie Millar (Counselling) , Richard Bizley (ELTC), Con Gillen (OLL) , Sheila Williams (Student Disability Service), Scott Rosie (Timetabling unit in the Academic Registry) , Susan Graham (Records Management) (and other business area owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

 

Section One: Programme Commentary, RAG and Resources Update

 

The Student services programme has 8 projects in progress (some of these in multiple phases).

The agreed STU programme baseline budget for 2012-13 is 1526 days.

 

 

 

 

Programme Budget for STU for 2012-13 is 1526 days,

Current STU out-turn estimate :2012-13 is 431 days (spent ytd) + 825 + 300 (estimate to complete) = 1556 days  (30 days over)

however if the effort for OLLIE & CUPID replacement is spread over 18 months , then 300 days effort is in 2013-14,  with only 1256 days effort in 2012-13 (this will bring the STU programme back into balance for 2012-13)

 

 

** AP23-041 (Replace OLLIE and CUPID) now expected to be delivered over 18 months - hence an initial estimate of the split in effort between 2012-13 and 2013-14 has been indicated - this is just a provisional estimate - the actual estimate will be refined as the options appraisal (STU229) progresses

 

 

 Section Two: Projects Not Started

 

 

Project InfoProgramme Manager's Commentary

AP23-041

Replace OLLIE and CUPID

 

Funded 

Planning Month Year Jan 2013

Delivery Month Year  tbc ( in  2014)

RAG Status

GREEN

Plan

This is the pot of remaining OLL funded days to deliver replacements for OLLIE and CUPID, an initial 75 days have  been assigned to STU229 for the options appraisal and IS Apps work assocaiated with enabling OLL credit students to be keyed into EUCLID.

Currently it is likely that OLL will wish to explore the options of buying in a 3rd party system , which will likely require future procurement and implementation projects to be funded from AP23-041, this activity is likely to be spread over 18-months. It is also likely that the requirements for OLLIE and CUPID will be dealt with separately , but that is dependant on the outcome of the STU229 Options Appraisal

 

Dependencies

STU229 OLLIE and CUPID Options appraisal

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

STU215  

Shared Academic Timetabling Phase 2- Implementation Minimum Change Year 1 

 

Category: Funded

Milestones

  
Dec 2012Closure (year 1 - Minimum Change)

 

 

 

 

RAG Status

BLUE

Report by Jamie Thin for Nov 2012

  • Achievements in Last Period
The last task (AT DR server build) for completion by the Tech Mgmnt team in IS Apps Production Management was completed
  • Issues

None

  • Next Steps

Project Closure. Closure approved by the project board.

 

STU220 

ELTC Implement Class.net

 

Category: Funded

Milestones

 

17-Dec-2012Deploy to LIVE
09-Jan-2013Closure

 

RAG Status

GREEN

Report by Donna Cruickshank for November 2012

Achievements in Last Period

 

ELTC are in the process of moving to the Live server.

Infospeed, the 3rd party supplier have been authorised to access both the test and live virtual machines directly and this was fully tested during a Class.net upgrade in November.

Issues

 ELTC are to advise their preferred go-live date (they do not currently have a date in mind).

Next Steps

The Live VM is prepared and we are awaiting the go-ahead from ELTC to move to it.

ELTC will move to the Live VM until Dec 2012

 

STU224

 

Category: C

Milestones

TBC

 

 

 

 

 

 

 

RAG Status

 

 

RED

Report by Morna Findlay for Nov 2012

Stalled awating the business area to complete UAT on BOXI reports

 

Achievements in this period

 

Escalated UAT testing issue to business area manager

 

Outstanding Issues

Business area resource conflict - with high priority freedom of information request

 

Next Steps

 

The projext status has been set to RED as no milestones can be set. 

STU226  

Timetabling Extended Implementation

 

Category: Funded

Milestones

 

These rough milestones are provisional awaiting analysis and input from the technical teams

Target dateTitle
  
29-Mar-2013Build
24-May-2013Acceptance Sign off review (ASOR)
28-Jun-2013Deployment
27-Sep-2013Deployment Sign off Review (DSOR)
25-Oct-2013Closure

 

 

 

 

 

 

 

 

RAG Status

AMBER

Report by Jamie Thin for Nov 2012

This project is the 2nd year of the Timetabling implementation and  builds on the initial delivery from STU215.

Project is in analysis stage.

STU226 will deliver the critical elements required to enable personalised timetables to be available for Students for the Start of Semester 1 2013.

Two further timetabling projects will deliver other components for the full solution: STU227 to deliver the Upgrade to v3.2 Enterprise and Reporting Phase 1, and STU228 to deliver Timetabling Planning and other Interfaces.

Budget for IS Apps for Timetabling in 12/13 is 640 days effort.

The provisional budget allocations are now :

STU226 (personalised student timetables) 285 days

STU227 (v3.2 upgrade) 70 days + (reporting) 60 days = 130 days

STU228 (interfaces) 225 days

Estimates for this future work will be refined as initial analysis and design work progresses.

 

  • Achievements in Last Period

Student Allocator installed on DEV.  Transfer of data between S+ and Student allocator configured in DEV.

Requirements are being gathered for the Student Allocator application and a demonstration of Student Allocator was delivered to users on 4-Dec (by a Scientia Consultant). The demo was well attended.

Analysis for Student Feed complete (as part of the Feeds from EUCLID work in STU228)

Timetabling Team visited Manchester Met University to gain an understanding of how Student Allocator was used there.

User Acceptance of Enterprise Timetabler v3.2 completed and the upgrade was implemented in the live environment with no issues reported (26-Nov as part of work in STU227).

Reports are being built for Reporting Phase1 (as part of STU227)

  • Issues

Issue with Single-sign-on via Shibboleth still has to be resolved for Student Allocator in DEV (for Student and Staff web front-ends)

How to manage roll-out of SAM client application to School users.

Large comms effort will be required to explain the impact of Student Allocator on local school business processes.

Project remains at AMBER until tasks are re-estimated.

  • Next Steps

 Further gathering of school requirements will define configuration options  for the delivery of the Student Allocator.

User Acceptance of the timetabling Reports (for the Timetabling Unit)

STU227 

TED Scientia Enterprise Upgrade to v3.2 

 

Category: Funded

Milestones

 

26-Nov-20123.2 Upgrade M4a: Go-Live - Database
27-Nov-20123.2 Upgrade M4b: Go-Live - Portal
28-Nov-20123.2 Upgrade M4c: Go-Live - WRB/SWS Images
10-Dec-20123.2 Upgrade M5 : Deployment Sign-Off Review (DSOR)
18-Jan-20133.2 Upgrade M6 : Closure
05-Dec-2012Reporting M1 : Analysis/Design Review (PPDR)
05-Dec-2012Reporting M2 : Build Review (PPBR)
10-Dec-2012Reporting M4 : Acceptance Sign-Off Review (ASOR)
13-Dec-2012Reporting M5 : Go-Live
10-Jan-2013Reporting M6 : Deployment Sign-Off Review (DSOR)
18-Jan-2013Reporting M7 : Closure

RAG Status

GREEN

Report by Donna Cruickshank for November 2012

 

Achievements in Last Period

3.2 Upgrade

Successful UAT in the test environment took place on all the appropriate platforms on 14 Nov 2012.

Go-Live was completed by 28 Nov and no issues have been reported.

 

Reporting

The reports are being designed and built simultaneously with the Config Team and Timetabling Team. These are on track to be built by the agreed  Build milestone.

Issues

none

Next Steps

Progress with the design/build of the Reporting Tool and UAT

 

STU228 

Timetabling Interfaces- Extended

 

Category: Funded

Milestones

Target dateTitleStage
21-Nov-2012Incoming Interfaces from EUCLID - Business Analysis ReviewAnalyse
03-Dec-2012Incoming Interfaces from EUCLID - Design ReviewDesign

RAG Status

AMBER

Report by Craig Middlemass for November 2012

Achievements in Last Period

  • Resource Conflict for Lead Developer Resolved
  • Incoming interfaces from EUCLID requirements signed off
  • Draft of System Design Specification for incoming interfaces circulated
  • Kx Link installed (need to progress to full testing)
  • Roll forward requierments reviewed will be re-issued
  • New Dev Tech resource allocated

Issues

  • Still awaiting estimates for the build - although agreed a phase approach to secure critical milestones

Next Steps

  • Gather estimates and plan the reorganised project
  • Organise MVM room booking investigation (possible delay to January)

SSG002

Student Marketing Services Infrastructure Migration

Category: Compliance

Milestones

Project Brief 12 October Port BRD 7th Dec UG Admin BRD 7th Dec No further milestones has been set, awaiting re-estimates

RAG Status

AMBER

Report by Maurice Franceschi  for November 2012

Develop TAD and SDS - have slipped into December as the SDS will now cover Port of UG and new UG Admin module.

BRD of Port for waiting for sign-off by 7th BRD of Ug Admin waiting for sign-off by 7th. TAD draft prepared. SDS expected by 10th. Machine build started.

Re-estimate effort outstanding - ocne we have the SDS we can estimate rest of SSG002 and SSG003

The plan outline has been agreed with the business, to deliver UG Port and Admin, UG Enhancements, PG Port and Admin, PG Enahcements, A-Z & Maps Port and Amdin.

 

Issues Senior Supplier has different priorities to business, so PM has to resolve this conflict.

Next Steps Develop TAD and SDS by end of December. Re-estimate effort. Check that budget for SSG002 can cover all the Admin pieces. Resolve conflict betwen senior supplier and business.

List of Tasks

Milestones TBC

 

 

 

SSG003

Student Marketing Services Enhancements (CAM)

Category: Funded

Milestones

Target dateTitleStageComplete  
07-Dec-2012Project BriefPlanNoeditview

No further milestones has been set, awaiting estimates

RAG Status

AMBER

Report by Maurice Franceschi  for November 2012

Achievements in Last Period

The re-evaluation of the requirements for SSG003 is under way, but is taking longer. The UG Enhancements draft is not required until mid-January, but we do need a sense of the requirements so we can have a project brief readied by end of December.

Issues Status changed from Red to Amber as we are clearer on the scope of the SSG003. Namely, it wil cover the enhancements to the UG and PG prospectus applications, but not the Admin pieces needing developed.

We also need to re-estimate SSG003 now that we plan to do all Admin work under SGG002. SDS exteced next week so estimation by 14th Dec.

Just need the enhancements listed for the brief to happen, and to check the budgets for SSG002 and SSG003 will be sufficient.

Next Steps Completion of requirements and new brief. Milestones Project Brief 21st December.

STU229

Replaement of OLLIE and CUPID

Category: ID Core

Milestones

Target dateTitleStageComplete  
12-Oct-2012Project BriefPlanYeseditview
25-Oct-2012Phase 1a - Acceptance ReviewAcceptNoeditview
05-Nov-2012Phase 1a - Deployment to LIVEDeliverNoeditview
14-Nov-2012Phase 1b - Change to Most Current - Acceptance ReviewAcceptNoeditview
28-Nov-2012Phase 1b - Change to Most Current - Deployment to LIVEDeliverNoeditview
30-Nov-2012Phase 2 - Business Requirements (BRD)AnalyseNoeditview
18-Dec-2012Phase 2 - Costed OptionsAnalyseNoeditview
14-Jan-2013Phase 2 - Decide on optionDeliverNoeditview

RAG Status

Time: 
GREEN
Cost: 
GREEN
Scope: 
GREEN
Overall: 
GREEN
Report by Maurice  Franceschi  for November 2012

Achievements in Last Period

Phase 1a - Deployment review

Phase 1b - Requirements sign-off and start of build

Phase 2

Some preliminary market research by Maurice and Graham. Other institutions do not have 3rd Party systems we could adopt, although a trip to Glasgow may help us with some scenarios. However, a first review of ELTC's  CLASSsystem functionality does provide enough positive feedback to recommend further exporation of the ELTC option with the vendor and also with IS Applications who are currently preparing to deploy the system. State business requirements - not ready yet, 14th December is the date. Evaluate risk to current systems (server failure, operating system patching risk to application, etc.) - completed.

 

Issues

The ELTC option may need more time to expore. Not known yet.

Next Steps

Phase 1a - Deployment review

Phase 1b - Requirements sign-off and start of build

Phase 2 Meeting to discuss how we will put together the estimates, and then team to work for a week on producing the costs, effort, risks.

Milestones

Phase 1a - Deployment Review - 19-Nov 2012

Phase 1b - Acceptance sign-off and deploy to LIVE - 28-Nov 2012

Phase 2 BRD 14th December.

                Costed Options - 18th December

List of Tasks

Options Appraisal Phase of the project still on budget, time and scope.

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

  

 AP23-040

OLL HESA 12/13

 

Funded 

Report by Jamie Thin

This project was withdrawn on 03-Aug-2012.

For 12-13 , OLL will key OLL credit students into EUCLID , so there is no future requirement to do a separate OLL HESA return

 

 

 

 

 

STU204

Coldfusion Upgrade - Careers

 

Report by David Watters

Closed

STU204 Completion report

AP12-038 STU223 

OLL HESA 11-12 

 

Category: Funded

Report by Anne Mathison for October 2012

 

Completion report completed and STU223 project has been Closed on 10/10/2012

STU222

CAM UG/PG Prospectus

Category : Funded

Report by Donna Cruickshank for October 2012

Completion Report completed and STU222 project has been closed.

The STU222 Completion Report

 

 

** Potential In-year projects for 2012-13 **

Disability Office in-year project work  - Enhancements to KELSO (for Summer 2013)

Careers - SAGE - upgrade from Coldfusion 6 to Coldfusion 9 (so that it remains on a supported platform)