PM and Business Lead met with Project Sponsor and Head of Knowledge Management & Planning to discuss options for presenting the costs to the stakeholder groups.
Revised costs drafted and sent 20/11/19 for presentation to SLT w/c 25/11/19.
Issues
PM and Business Lead spending minimal time on project while awaiting a steer from SLT.
Journyx have indicated that the license unit costs are increasing from January 2020 therefore if agreement is not forthcoming in December, the current offer will no longer be available and the cost model will no longer be valid.
Next Steps
Decision on project scope and timeline, or close project.
If agreement to continue, internal signoff required to commit to costs and request JournyX to schedule migration work.
Work continues on contract checklist and snagging list.
Accessibility commitment letter received from TOPdesk and passed to UoE's Disability Information Officer.
Policy on fair use of storage has been shared with PUG and agreed.
High level migration planning work has been impacted by the delay to contract negotiations. A copy of the UoE DB was provided to TOPdesk for analysis and to test out the migration process, w/c 18/11/19.
Issues
As a result of delays on the procurement, there is still uncertainty when the contract will be in place. PM is working with Project Sponsor, Chair of the PUG, UoE Legal, Academia, and TOPdesk to deliver a draft set of paperwork for review w/c 02/12/19 ahead of the UniDesk Board 11/12/19.